South Barry Avenue Over Otter Creek Tidal Basin Bridge Replacement
Closed State & local contract opportunity Posted
- Solicitation number
- 2137214
- State
- New York
- Responses due
Opportunity facts
- Jurisdiction
- Points of contact
-
- Jason Watzka jwatzka@hveapc.com (845) 838-3600
- Deborah Reisner dreisner@ryetownny.gov (917) 817-9796
Updated .
About this opportunity
The Town of Rye is requesting sealed bids for the South Barry Avenue Over Otter Creek Tidal Basin Bridge Replacement project in the Village of Mamaroneck, Westchester County, with bids due August 27, 2026 at 1:00 p.m. at the Rye Town Office, 222 Grace Church Street, Port Chester, New York 10573, and a mandatory site visit on August 11, 2026 at 10:00 a.m. at the existing bridge location. This is a Federal Aid Project requiring NYSDOT compliance. MBE and WBE contracting goals of 22.60% and 6.90% respectively apply; no SDVOB or DBE goals are established.
The scope encompasses replacement of an existing 29-foot span steel girder bridge with a new 46-foot span prestressed concrete beam bridge, minor roadway reconstruction on approaches, guiderail installation, water main relocation work, and concrete sidewalk improvements for access to the Otter Creek Preserve. All labor, materials, machinery, tools, equipment, and other means of construction necessary to project completion are included per the final plans and NYSDOT Standard Specifications (effective May 1, 2026). Substantial completion is required 365 calendar days from Notice to Proceed, with final completion and payment readiness by December 31, 2027.
This is a unit price bid contract. Bid security of 5% of the bid amount is required. The successful bidder must furnish Performance and Payment Bonds at 100% of the accepted bid amount, be registered with the NYS Department of Labor prior to submission, and have an approved CCA-2 on file with NYSDOT prior to award. Prevailing wage rates apply. Bidders must use NYSDOT-approved Equitable Business Opportunities (EBO) software for civil rights compliance tracking. Employment goals include 22.6% minority and 6.9% women employment. The Town reserves the right to consider bids for 45 calendar days after receipt and to reject any bid withdrawn within 45 calendar days of opening.
Opportunity text
The work includes providing all labor, materials, machinery, tools, equipment and other means of construction necessary and incidental to the completion of the work shown on the plans and described in these specifications including, but not necessarily limited to the following: replacement of existing 29' span steel girder bridge with a new 46' span prestressed concrete beam bridge, minor roadway reconstruction on the approaches, guiderail installation, water main relocation work, and concrete sidewalk improvements for access to the Otter Creek Preserve. Business enterprises awarded an identical or substantially similar procurement contract within the past five years: None Service-Disabled Veteran-Owned Business (SDVOB) SDVOB Goal: 0.00% Minority / Women Business Enterprise contracting goals (MWBE) MBE Goal: 22.60% WBE Goal: 6.90% Disadvantaged Business Enterprise contracting goals (DBE) DBE Goal: 0.00%
Files
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity