Z2DA--666-22-117 Replace Building 9 Stairs and ADA Ramp
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 36C25923R0003
- Agency
-
Veterans Integrated Service Network 19
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Sheridan, Wyoming 82801, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to replace the stairs and Americans with Disabilities Act ramp at Building 9 of the Sheridan Veterans Affairs Medical Center in Sheridan, Wyoming. The Department of Veterans Affairs is soliciting proposals to demolish existing structures and construct new stairs, ramps, sidewalks, utilities, and landscaping per the provided plans and specifications. Proposals are due by November 29, 2022 and will be evaluated based on past performance, price, and certifications. The work must be completed within 90 calendar days of the notice to proceed.
This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses. The primary NAICS code is 238210 and PSC code is S206. The place of performance is Sheridan, Wyoming. The period of performance is 90 calendar days with a budget of $250,000-$500,000. Safety plans are due 10 days prior to the start of construction and infection control protocols must be followed to minimize disruption to medical center operations.
Notice text
4 versions
Update #4 · Latest ·
AN AMENDMENT TO SOLICITATION 36C25923R0003 POSTED ON NOVEMBER 17, 2022. The purpose of this amendment is as follows: Upload Site Visit Document and Sign in Sheet Upload corrected Bid Schedule to include Deductive Alternates 1 & 2 Post RFI s with responses All offers will be emailed to Jason Rankin at Jason.rankin@va.gov. All other items and conditions remain the same.
Update #3 ·
AN AMENDMENT TO SOLICITATION 36C25923R0003 POSTED ON OCTOBER 27, 2022. The purpose of this amendment is as follows: Change the Questions due date to November 14th, 2022 @ 10:00 AM MT. All offers will be emailed to Jason Rankin at Jason.Rankin@va.gov. All other items and conditions remain the same.
Update #2 ·
AN AMENDMENT TO SOLICITATION 36C25923R0003 POSTED ON OCTOBER 27, 2022.
The purpose of this amendment is as follows:
Change the Questions due date to November 14th, 2022 @ 10:00 AM MT.
All offers will be emailed to Jason Rankin at Jason.Rankin@va.gov.
All other items and conditions remain the same.
Update #1 ·
Project: 666-22-117
Project Name: Replace Building 9 Stairs and ADA Ramp
Project Scope
General
The stairs and ADA ramp in front of the west side of building 9, at the Sheridan HCS station located at 1898 Fort Road Sheridan, WY, are deteriorating and in need of removal and replacement to current ADA and VA Barrier Free standards. Contractor to provide all equipment, material, and labor to compete project and associated elements per plans and specifications provided. This shall be a firm Fixed Price Project.
Tasks and Requirements
Project Requirements
A. Construction activities shall include, but not be limited to, the following:
All construction standard practices (VA and OSHA) to ensure the successful, safe, construction activities to complete the project.
Coordination of construction activities to create minimal disruption to Sheridan VA station operations. Compliance with applicable station policies and procedures for construction activities.
Weekly progress meeting with station staff, conducted by the contractor, on current status of procurement, construction, and look ahead scheduling. Meeting setup, note-taking and minutes are contractor s responsibility. Distribution of meeting record to Sheridan staff no later than 3 business days after meetings.
Utility locates for all aspects of construction activities.
Confirmation of existing building and site grades for stair, ramp, sidewalk, and other components of construction as listed in the plans.
Demolition of existing structures, above and below ground with approved isolation of ALL affected utility systems.
Construction of all elements of project per plans and specifications, finished product to closely match existing building aesthetics as approved by COR.
Installation of new utility systems, including electrical, exterior lighting, Ice melt, data and control connections, irrigation, testing and commissioning as required.
Installation of Memorial Garden Landscaping and irrigation as per plans within project envelope including alternate fencing, if applicable.
All project cleanup and closeout activities as approved by COR or station Facilities representative.
General Contractor Requirements
Construction project is to be completed within 90-calendar days from date of notice to proceed.
Contractor shall provide all equipment, material and labor required for demolition work, construction of all structures, stairs, all ramp components and utilities, and providing finishes as indicated in the plans and specifications per VA construction standards.
Safety submittals shall be complete prior to the commencement of onsite construction work. Material selection submittals shall be complete and approved prior to ordering of materials for the project.
The building tenants not in the construction areas will remain, at work or traversing the tramway, in the buildings during this construction. Patients will remain in areas not under construction so the contractor shall make patient safety and infection control measures a priority. The contractor shall coordinate work locations and schedules with VA so as to minimize impact to building tenants. The contractor shall install and maintain orange safety fencing around the perimeter of the construction site throughout the project.
All electrical, carpentry, architectural, mechanical work, product design, project management and other work needed on this project shall be provided by the contractor. All electrical work low, medium or high voltage will be installed and terminated by the contractor with coordination with station facilities staff.
No wiring or cabling shall be abandoned in place.
All piping, cabling and wiring shall be labeled.
The installation must, as a minimum, be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA) Design Manuals and VA PUBLICATIONS (Master Construction Specifications, Construction Standards, National Fire Protection Association (NFPA) Underwriters Laboratory, International Building Code IBC 2003, NFPA and National Electric Code (NEC) building codes and standards and VA Information Security Handbook 6500.6, 6550.0 etc.).
Any penetrations through any floors, ceilings or walls, shall be fire caulked, or otherwise fire sealed, and shall be done in this contract to meet VA standards and National Fire Protection Association (NFPA) standards where applicable.
The contractor shall inquire of the VA if any doors, frames, associated hardware, and any other property removed is desired to be retained by the VA for reuse elsewhere within the medical center, at the time of removal.
If the VA desires to retain an item, the contractor shall deliver it to a location designated by the VA.
If the VA does not desire to retain an item, the contractor shall dispose of it.
The new components installed shall be tested and commissioned, recertified and/or tested before VA acceptance. All testing parameters will be provided by the contractor with source references to the COR and 3rd party reviewer before testing begins.
HVAC systems that have changes made to them as part of this project, beyond diffuser replacement, shall be tested and balanced by the contractor with coordination with station staff.
Any IT data cables installed or modified as part of this effort shall be tested after installation. Test methods and plans shall be coordinated with the COR.
Any Ice Melt systems installed or modified as part of this effort shall be certified to perform to ALL manufacturers standards including flow and temperature requirements. The contractor shall arrange testing verification with Sheridan Facilities staff prior to acceptance of the system.
A part of this contract and shall be to provide as-built plans and results, including acceptable flow and testing for all aspects and zones of the ice melt system, to the COR for approval.
Contractor shall coordinate with COR for any necessary operational training of systems installed with Sheridan VA station staff.
All operational guides and instruction manuals shall be delivered to the COR, via electronic or hard copy, prior to final acceptance of project.
At the conclusion of the project, the contractor shall provide the VA and AE with a redlined set of construction drawings, showing any as-built variations from the plans as called for in the specifications.
The contractor shall repair any disturbed earth around and in the construction areas. This shall include:
Removing any rocks or clumps that have been brought to the surface.
Filling in any ruts or depressions with approved fill material, such that the areas are level or at the required slope.
Returning the surface cover to what is was before the project, or as called out in the project drawings.
In the case of grass, the contractor shall provide topsoil as necessary to provide a good medium for grass growth. There shall be no more than ½ of grade difference between the existing adjacent ground and the prepared, imported soil for seeding. Contractor shall place grass seed per the station seed blend as stated in the plans. If the area(s) cannot be covered by the VA sprinkler system, then the contractor shall provide for the watering of the new grass until it is established or coordinate watering by Sheridan VA Grounds at contractor s own risk. Total new grass areas must produce a minimum of 80% successful coverage within the warranty period. Any areas that do not take to new grass seeding must be re-seeded until 80% coverage is achieved.
The contractor shall replace any trees, shrubs or other plants damaged or destroyed during construction, per the project landscape drawings.
General
The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the contractor have a Competent Person on the job at all times (must have a 30-hour OSHA card), and that all contractor employees have received a minimum of ten (10) hours of OSHA construction safety training. Documentation of these requirements shall be submitted and approved prior to performing the work.
Contractor must submit a company Site Specific Safety Plan (SSSP) that must be approved by VA Safety prior to work beginning. This plan shall detail fire, construction, and health-related safety measures, in addition to listing Training Records for all employees for the previous year. A company standard or boilerplate safety plan will not be acceptable plan should contain a detailed hazard analysis for each element of construction to be performed in the form of an Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA).
This entire project shall conform to 100% of all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes.
The Contractor shall be responsible for the health and safety of their own employees. The VA will inform the Contractor of any hazards such as designated permit confined spaces, electrical hazards, etc. which may affect Contractor employees. The Contractor must take precautions appropriate for the safety of their employees as well as provide equipment necessary for these actions. Contractor employees will notify the VA Representative before entering a designated permit required confined space, so precautions can be taken in advance of the work.
The Contractor shall hold harmless and indemnify the Government against any and all liability, claims, and costs of whatsoever kind and nature for injury to or death of any person or persons and for loss or damage to any property occurring in connection with, in any way incident to, or arising out of the occupancy , use, service, operation or performance of work under the terms of the contract, resulting in whole or in part from the negligence acts or omissions of the Contractor, any subcontractor, or any employee, agent, or representative of the Contractor or subcontractor.
The Contractor shall adhere to VHA Directive 1192.01: Seasonal Influenza Vaccination Program for VHA Healthcare Personnel. The VHA Directive requires all HCP covered by the policy to receive the annual seasonal influenza vaccination. All contractors and subcontractors will follow COVID screenings and mask regulations per CDC policy and VHA Directives.
The Contractor is responsible for protection of existing finishes, and VA property (FF&E), located in the areas where preventative maintenance and repair work is being performed, as well as along paths of travel to and from these areas. Both exterior and interior finishes and property must be maintained. The contractor is liable for any damage to VA property during the contract. Any damage to existing finishes must be repaired by the Contractor to equal or greater quality than existing finishes. All tasks accomplished by the Contractor personnel will be performed to preclude damage or disfigurement of government-owned furnishing, fixtures, equipment and architectural or building structures. Contractor will report any damage or disfigurement to these items when caused by the Contractor s personnel and will perform repairs or replace government-owned equipment, fixtures, furnishings, grounds and architectural or building structures to their previously existing condition.
Project Management
Based on the above list of work items, the general contractor selected must complete, maintain, and submit the following documentation and managerial requirements:
Construction schedule including sequencing and durations.
The schedule will be provided to the COR ten (10) working days prior to the start of work.
Site-Specific Safety Plan (SSSP) with an emphasis on, but not limited to, demolition, installation, and safety. The SSSP must:
Include a detailed description of how the work will be performed and be submitted with sketches, supporting documents, submittals etc.
Include a Job-Safety-Analysis (JSA) for all tasks associated with Statement of Work (SOW)
Be approved by VA-Safety prior to commencement of work.
Maintain site supervision by a competent individual(s) with OSHA-30 certificates. OSHA-30 certified technician shall be onsite anytime work is being performed.
Obtain VA identification PIV badges for all employees. Contractor to consider lead-time for badge procurement.
Manage job-site access and security.
Implement and maintain required ICRA and ILSM measures.
Code & Regulation Compliance
The Contractor shall comply with the public laws and statutes including all changes and amendments of federal, state, and local environmental statutes and regulations in effect of date of issuance of this delivery order, including, the applicable portions of the documents cited in the basic contract and below.
National Fire Protection Association (NFPA):
NFPA 101 Life Safety Code
International Code Council (ICC): IBC: International Building, 2015
International Conference of Building Officials (ICBO): UBC 1997: Uniform Building Code
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1926 Safety and Health Regulations for Construction
Federal Occupational Safety and Health Act (OSHA)
2018 International Plumbing Code
SBCCI Standard Plumbing Code
Submittals
Contractor shall submit the following prior to beginning scope of work:
Project schedule with sequencing, durations, phasing, and cost loading within 10 working days of Notice to Proceed (NTP), and monthly with invoices.
Site Specific Safety Plan (SSSP)
SSSP to be submitted to VA Safety staff for review 10 working days after issuance of NTP.
SSSP to be approved by VA Safety staff prior to start of construction activities.
Construction Demolition Removal / Handover Plan
Inspection reports, manufacturer approval certificates, and warranties.
Penetration and or hot work permits as necessary.
Manufacturer and construction warranties as noted in specifications.
Project Schedule including sequencing and durations.
SOV Schedule of Value
The schedule will be provided to COR 10 working days prior to start of the work.
Site superintendent OSHA-30, and tradesmen/laborer OSHA-10 certificates. OSHA-30 certified technician shall be onsite anytime work is being performed.
Material Submittals Submit for COR approval
Physical and electronic Redline drawings of the completed work.
Technical literature and/or descriptions of all materials, equipment and tools proposed for use by the Contractor shall be submitted to the Contracting Officer or his/her designee for approval prior to contract start and whenever a change is required. All Contractor-furnished materials, equipment and tools used shall be standard products all manufacturers regularly engaged in the production of such items. The Contractor shall secure all materials. The Government assumes no liability for loss of or damage to Contractor-owned property held upon Government premises.
Contractor shall submit hours worked, full report of completed piping which shall include location, hours worked, the full name of Contractor s employees on site, and digital photographs before and after work is completed. Reports shall be submitted within one day upon completion of work performed. Contractor will provide a completed redline drawing of the completed routing of piping. Reports shall be provided in hard copy as well as in an agreeable and compatible electronic format such as, but not limited to, pdf or Microsoft Word.
Electronic/Digital Deliverables
CD set with above documents (Report, Summary Report, Handwritten Notes) in a PDF format.
An electronic copy of redline drawings of the completed work in the latest AutoCAD version.
Acceptance Standards
The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA. Work must be approved for one location of each type of fixture prior to proceeding with all other locations specified. If conditions that exist that are not like the location previously approved the contractor shall get approval prior proceeding with work in locations with similar conditions.
Safety and Prevention
In the performance of this contract, the contractor shall take such safety precautions as necessary to protect the lives and health of occupants of the building.
The Contractor shall immediately correct any fire and safety deficiencies caused by his/her personnel. If the Contractor fails or refused to correct deficiencies promptly, the Contracting Officer may issue an order stopping all or any part of the work and hold the contractor in default of the contract.
The Contractor shall comply with applicable Federal, State and local safety and fire regulations and codes which are in effect at the beginning of the contract. The contractor shall keep abreast of and comply with changes in these requirements and codes applicable to the contract. The requirements include but are not limited to, those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees
The Contractor s personnel shall follow applicable facility policies concerning fire/disaster programs.
All materials and equipment will be removed from the facility or stored properly at the end of the workday and secured during the workday. Under no circumstances will the Contractor allow for any equipment to be left unattended for any length of time.
The Contractor shall comply with all applicable Federal, State and local legal requirements regarding workers health and safety.
The Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.
The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially about exits and exit way access. Utility shutdowns shall not compromise security, communication, or fire safety for occupants.
No flammable liquids shall be stored or used in the medical center.
The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241. Contractor shall keep certification onsite at all times of extinguisher inspections.
The Contractor shall receive from the COR a permit for all cutting, welding, and soldering 24 hours in advance. All permits shall be prominently displayed during all construction.
All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.
The Contractor shall assume responsibility of environmental protection of all material storage.
Accident Prevention
Precaution shall always be exercised for the protection of persons (including employees) and property. These shall include, but not be limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor shall comply with all applicable laws relating to safety precautions, including the safety regulations of the Division of Industrial Safety, Department of Industrial Regulations of the state.
Environmental Protection
In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of the Corps of Engineers Manual EM 385-1-1, General Safety Requirements as well as the specific requirements stated elsewhere in the Contract Documents.
The Contractor is responsible for daily cleanup of all areas affected by its work. Areas in use or affected shall be returned to condition in which they were turned over or initially found. VA Housekeeping shall not be dispatched for cleaning associated with contractor work.
The Contractor shall take every precaution in preserving flooring, finishes, equipment, and furniture in areas of work. The Contractor shall repair or replace any damage incurred during its work at their expense.
Contractor shall use freight elevators for transmission of materials and personnel. Contractor shall take every precaution in preserving the elevators, including the hoist way and lobby doors, interior finishes, and shall conduct all good practices in observing lifting and motor components tolerances. Any damage incurred to any elevator component due to negligence will be repaired at expense of the contractor, within the workday of incurred damage.
Work Standards and ICRA/ILSM
Work site shall be free of debris and returned to original condition upon completion of preventative maintenance or repairs.
All work is to be performed in areas used daily by facility clients and staff. Contractor will take suitable measures to control all material and equipment to produce a minimum of interference in facility routine. All work shall be performed in a safe and prudent manner.
Contractor shall so perform all work as to offer the least possible obstruction and inconvenience to staff and the public and shall have under construction no greater amount of work than can be completed promptly and properly with due regard to the rights of staff and the public. Any person the COR may deem incompetent or disorderly shall be promptly removed from the facility and not be allowed to return for the duration of the agreement.
The Contractor shall comply with an Infection Control Risk Assessment (ICRA) which will be
developed with the COR and the Infection Control Practitioner. Multiple ICRA s may be necessary to address specific risks at various stages of the project and must be approved prior to proceeding on each phase.
Period of Performance
Government intends to issue NTP immediately after kickoff meeting with Contractor. The period of performance for this contract is ninety (90) calendar days from NTP.
Hours of Work
The hours of work shall take place during the normal business hours of 7:30 AM and 4:00 PM, Monday through Friday, Federal Holidays excluded. Request for weekend, after-hour, and Federal holiday work is permitted with a request in writing submitted beforehand. Off hours are not to billed as overtime. Federal Holidays and any other day declared a federal holiday by the President of the United States are defined below.
New Year s Day Martin Luther King Jr s Day Presidents Day
Memorial Day Independence Day Labor Day
Columbus Day Veterans Day Thanksgiving Day
Christmas Day Juneteenth Day
If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government.
All work is to have a limited impact on the facility, veterans, and employees. This may require evening or weekend hours and will be identified in the schedule. All after hours work should be scheduled in advance.
Postponement/Delays: In the event climate or weather conditions become unsuitable for work or may induce an environmental hazard, then the entire work shall be rescheduled to a date and time satisfactory to the Contractor and the COR. Postponement due to inclement weather will not cause assessment of the penalty provision outlined above, nor should there be an additional cost to the Government.
All work shall be scheduled and performed within the date and time approved by the COR, in conjunction with the department occupying the space served by this equipment.
Privacy Statement
Information Security: The C&A requirements do not apply; a Security Accreditation Package is not required. Incidental exposure to protected health information may occur from accessing the work site. Staff will follow all Privacy & Security policies and procedures.
Post Construction Quality Validation
FAR 52.246 21 Warranty of Construction, the Contractor is to provide a one (1) year warranty
period, from the date of final acceptance of the work, covering defects related to all work
performed and any materials/equipment included in the project.
**End of Statement of Work**
Files
| File | Type | Posted |
|---|---|---|
| S05 - RFIs and Responses.docx | DOCX document | |
| S04 - Site Visit Sign in Sheet.pdf | ||
| 36C25923R0003 0002.docx | DOCX document | |
| S02 - Updated Bid Schedule with Deductive Alternatives.docx | DOCX document | |
| S04 - Site Visit Meeting Doc.pdf | ||
| 36C25923R0003 0001.docx | DOCX document | |
| S02 - 7 -Specs Gaurantee Period-B9 STAIRS ADA RAMP-COMPLETE.pdf | ||
| S02 - DRAWINGS-B9 STAIR AND ADA RAMP - COMBINED.pdf | ||
| 36C25923R0003.docx | DOCX document | |
| S02 - SPECIFICATIONS-B9 STAIR AND ADA RAMP - COMBINED.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z2DA--666-22-117 Replace B9 Stairs | Award Notice | |
| This notice | Solicitation | |
| Z2DA--666-22-117 Replace Building 9 Stairs and ADA Ramp | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Z2DA--666-27-102 Lightning Protection Update B71N | Veterans Integrated Service Network 19 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--Renovate Space for Patient Care Improvements | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| Y1DA--442-306 | Construct Physical Therapy Addition | Cheyenne, WY | VA Technology Acquisition Center | Service-Disabled Veteran-Owned Small Business | |
| Building 13 Stair and Roof Replacement at Castle Point VAMC | Veterans Integrated Service Network 2 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--612A4-27-018 | Replace B650 3rd and 2nd Flooring | Veterans Integrated Service Network 21 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity