Renovate Travis AFB B243/B54 Fire Suppression Systems
Closed Solicitation Posted
- Solicitation number
- FA442720R0022
- Agency
- Air Mobility Command Air Force, Department of Defense
- Responses due
- Set-aside
- HUBZone
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Place of performance
- Travis Afb Ca 94535 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals to renovate the fire suppression systems in two server rooms at Travis Air Force Base, California to comply with Air Force Engineering Technical Letter 01-18. The Department of the Air Force Air Mobility Command is procuring these services to upgrade the existing wet pipe sprinkler systems with clean agent fire extinguishing systems as a supplement in Building 243, Bay A and Building 54. Offerors must have experience with similar construction projects at military installations and will be evaluated based on past performance and technical approach. Proposals are due by June 26, 2020.
This requirement has been set aside for HUBZone small businesses. The primary NAICS code is 238210 and PSC code R499 covers construction of buildings. The place of performance is Travis Air Force Base in Fairfield, California. The contractor must complete the renovations to both buildings within 120 calendar days according to the statement of work and design documents provided. The total value of this firm-fixed price contract is between $250,000 and $500,000.
Notice text
B243 XDAT 15-1123
The Contractor shall be responsible for all professional services, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the task to renovate the fire suppression system in the server room area of building 243, Bay A to comply with Air Force Engineering Technical Letter (ETL) 01-18. Description of Work: The existing server room located in building 243, Bay A is currently protected with a conventional wet pipe automatic fire protection system. This system will remain active as required by ETL 01-18. The scope of this project is to provide a Clean Agent Fire Extinguishing system to supplement the existing fire protection system Contractor shall make these renovations to the facility in compliance with the completed design documents.
B54 XDAT 15-1124
The Contractor shall be responsible for all professional services, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the task to renovate the fire suppression system in the server room area of building 54 to comply with Air Force Engineering Technical Letter (ETL) 01-18 The existing server room located in building 54 is currently protected with a conventional wet pipe automatic fire protection system. This system will remain active as required by ETL 01-18. The scope of this project is to provide a Clean Agent Fire Extinguishing system to supplement the existing fire protection system. Contractor shall make these renovations to the facility in compliance with the completed design documents.