Pre-Bid RFIs 11-19 Combined B243 B54 Fire Supp Final.pdf

PDF 74 KB Posted

Attached to
Renovate Travis AFB B243/B54 Fire Suppression Systems Federal contract opportunity
Solicitation number
FA442720R0022
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains a pre-bid request for information and related federal contract opportunity solicitation for fire suppression system renovations at Travis Air Force Base. The solicitation seeks a contractor to upgrade the fire suppression systems in server rooms located in buildings 243 and 54 in accordance with Air Force Engineering Technical Letter 01-18. The work will supplement existing wet pipe fire protection systems with clean agent fire extinguishing systems. The contractor will be responsible for all professional services, permits, labor, materials and equipment to complete the renovations in compliance with completed design documents. Questions from potential offerors involve the scope of demolition work, requirements for additional monitoring equipment, plans for an existing Advantor monitoring system, and coordination responsibilities for programming the new systems. Offerors must submit proposals in response to solicitation number FA442720R0022 by the specified due date. The contracting agency is the Department of the Air Force Air Mobility Command.

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Travis AFB B243/B54 Fire Suppression Systems, newest first.
File Type Posted
Solicitation Amendment FA442720R00220002 SF 30.pdf PDF
B54 As-Builts.pdf PDF
Pre-Bid RFIs Combined - B243 B54 Fire Supp - Final.pdf PDF
Solicitation Amendment FA442720R00220001 SF 30.pdf PDF
Past Performance Questionnaire.pdf PDF
Attachment 11 Engineering Technical Letter ETL 01 18 Fire Protection Engineering.pdf PDF
Attachment 3 Travis AFB Fire Suppression Building 243 Final Drawings.pdf PDF
Attachment 9 Travis AFB Fire Suppression Building 54 Final Specifications.pdf PDF
Attachment 5 Vicinity Map 243.pdf PDF
Solicitation - FA442720R0022 Request for Proposal.pdf PDF
Attachment 2 Travis AFB Fire Suppression Building 243 Final Design Analysis.pdf PDF
Attachment 14 TAFB Security Requirements.pdf PDF
Attachment 12 2008 Travis Design Guide FEG.PDF PDF
Attachment 13 Wage Determination Applicability.pdf PDF
Attachment 6 SOW Renovate Fire Supp B54 XDAT 15 1124.pdf PDF
Attachment 8 Travis AFB Fire Suppression Building 54 Final Drawings.pdf PDF
Attachment 4 Travis AFB Fire Suppression Building 243 Final Specifications.pdf PDF
Attachment 1 SOW Renovate Fire Supp B243 XDAT 15 1123.pdf PDF
Attachment 10 Vicinity Map 54.pdf PDF
Attachment 7 Travis AFB Fire Suppression Building 54 Final Design Analysis.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI 011) Is there any existing smoke detection system that needs to be Demo-ed?

No, but there may be redundant detectors. The new detectors are intended to activate the clean agent systems and could serve as replacements for the existing detectors within the protected areas.

RFI 012) Is there any fire alarm equipment that needs to be demo-ed before the installation of fire suppression system?

None that the government is aware of at this time. The existing fire alarm control panels will remain and monitor the new systems.

RFI 013) Will Graphic Annunciator be required for fire suppression system?

This is not a requirement of the project.

RFI 014) Will LCD Annunciator be required for fire suppression system?

Beyond the displays on the system control panel and the fire alarm control panels, this is not a requirement of the project

RFI 015) Specs say UL #5555 Dampers are being provided? Who is providing these?

Contractor to supply/install.

RFI 016) ETL states there is a monitoring Advantor system above the ceiling tile, what is the plan for this system Deactivate temp, Modification, Removal?

Advantor system will be deactivated by AF personnel (likely to be deactivated during construction activities then restored to operation during evenings and weekends.)

RFI 017) If Advantor system is powered down, does the system have items that will interfere with construction work?

Unknown – to be site verified by contractor

RFI 018) Will Facility personnel take care of the Advantor system Deactivate temp, Modification, Removal, or will this be handled by contractor?

Government personnel

RFI 019) Will arrangements be made with Simplex, to have them out to program monitoring points into their system to monitor for New fire suppression system?

Responsibility of contractor