New Falcon Dam Administration Building

Awarded Award Notice Posted

Solicitation number
IBM15R0005
Agency
International Boundary and Water Commission U.S.-Mexico
Awarded
to Guzman & Munoz Engineering And Surveying, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
IBM16C0005 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Place of performance
Falcon Dam Reservoir Starr County, Texas, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Added: Jun 30, 2015 2:08 pm Modified: Aug 06, 2015 1:46 pmTrack Changes


THIS IS THE SOLICITATION NOTICE. THE USIBWC IS REQUESTING PROPOSAL AT THIS TIME.


Please refer to the Solicitation package.



General Project Information


A recent draft historic properties inventory report dated February 2011 identified the Falcon Dam and Falcon Village as a Historic District that is eligible for the National Register of Historic Places. The village was constructed to house personnel that operate and maintain Falcon International Dam and Power Plant.


The dam provides water conservation, irrigation, hydroelectric power generation, flood control, and recreational benefits, and serves as an international port of entry across the Rio Grande between Starr County, Texas, USA and Tamaulipas, México. Construction on the dam began in December 1950 and on October 19, 1953, as construction neared completion, U.S. President Dwight D. Eisenhower and Mexican President Adolfo Ruiz Cortines met at the center of the dam to dedicate it to the well-being of the residents of both countries.


Falcon International Dam was completed on April 8, 1954. The existing administrative building was constructed during the same time frame and is located within Falcon Village of off F.M. 2098, Reservoir Road, and is no longer meeting the needs of the staff due to its size and outdated design. The period of significance for the historic district is 1950 through 1965. The existing building will need to be demolished. Demolition is part of this project.


General Description of the Work


The USIBWC plans to construct a new administration building.


1. The total building foot print is proposed to be between 5,300 and 5,600 square feet. The new building will consist of a minimum of nine (9) offices, hydro laboratory, conference room, and security office area including a weapons locker room, break room, fireproof vault room, IT server room, and reception area.


2. This building will replace the existing Falcon Dam's Administration Building. The existing building is no longer functional with respect to building codes, OSHA requirements, office space, needed technological improvements, and mechanical efficiency.


3. The objective is to demolish and dispose of the existing administration, security, and hydro lab buildings in their entirety, and construct a new Administration Building in the same area but not in the same footprint to provide a more efficient and effective working environment.


4. The existing administration office accommodates the administration functions for the field office and dam and houses the offices for the Area Operations Manager, technical staff, and administrative staff. The Falcon Dam Field Office staff will remain in the existing building while the new administration building is constructed.


5. Demolition of the existing administration, security, and hydro lab buildings will be accomplished after all administrative staff has been moved in to the new administration building.


6. At the conclusion of the project, the new administration building shall be a fully commissioned (turn-key) building able to operate for its intended use with all utilities, to include, but not limited to water, sanitary sewer, communications, electrical, fire protection system(s), etc.


Major Construction Tasks


1. Design and construct a new Administration Building, including all planning, design work, coordination, permitting, labor, material, tools, equipment, construction, testing, inspection, commissioning, demolition, cleanup, and all necessary general conditions, that may be reasonably inferred from the Contract Documents to provide for all work for the design and construction of a new single-story administration building and demolition of the existing buildings.


2. Provide a minimum of two (2) floor plans for USIBWC to choose from.


3. Create all construction specifications and drawings required to complete the project.


4. Design and build to a minimum LEED Silver certification.


5. Encompass the historical and architectural aspects of the surrounding buildings. The purpose is to minimally affect the historic integrity of the district.


6. Construct in a vacant, previously disturbed area.


7. Meet federal OSHA standards and current environmental laws to provide a more efficient and effective working environment.


Magnitude


The magnitude of the project is between $1,000,000 and $5,000,000.


Performance Period


All work shall be completed within four hundred (400) calendar days after the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.


This requirement is a 100% Small Business Set Aside.


This requirement shall be solicited using Two-Phase Design-Build Selection Procedures in accordance with Federal Acquisition Regulation (FAR) SUBPART 36.3. 

PLEASE NOTE THE SITE VISIT INFORMATION LISTED UNDER SECTION L.01 PRE-PROPOSAL CONFERENCE AND SITE VISIT OF THE SOLICITATION DOCUMENT RFP IBM15R0005

Amendment A001 is now posted.

Acknowledgement of this Amendment A001 is required.

Update #2 ·

Added: Jun 30, 2015 2:08 pm Modified: Jul 15, 2015 6:05 pmTrack Changes


THIS IS THE SOLICITATION NOTICE. THE USIBWC IS REQUESTING PROPOSAL AT THIS TIME.


Please refer to the Solicitation package.



General Project Information


A recent draft historic properties inventory report dated February 2011 identified the Falcon Dam and Falcon Village as a Historic District that is eligible for the National Register of Historic Places. The village was constructed to house personnel that operate and maintain Falcon International Dam and Power Plant.


The dam provides water conservation, irrigation, hydroelectric power generation, flood control, and recreational benefits, and serves as an international port of entry across the Rio Grande between Starr County, Texas, USA and Tamaulipas, México. Construction on the dam began in December 1950 and on October 19, 1953, as construction neared completion, U.S. President Dwight D. Eisenhower and Mexican President Adolfo Ruiz Cortines met at the center of the dam to dedicate it to the well-being of the residents of both countries.


Falcon International Dam was completed on April 8, 1954. The existing administrative building was constructed during the same time frame and is located within Falcon Village of off F.M. 2098, Reservoir Road, and is no longer meeting the needs of the staff due to its size and outdated design. The period of significance for the historic district is 1950 through 1965. The existing building will need to be demolished. Demolition is part of this project.


General Description of the Work


The USIBWC plans to construct a new administration building.


1. The total building foot print is proposed to be between 5,300 and 5,600 square feet. The new building will consist of a minimum of nine (9) offices, hydro laboratory, conference room, and security office area including a weapons locker room, break room, fireproof vault room, IT server room, and reception area.


2. This building will replace the existing Falcon Dam's Administration Building. The existing building is no longer functional with respect to building codes, OSHA requirements, office space, needed technological improvements, and mechanical efficiency.


3. The objective is to demolish and dispose of the existing administration, security, and hydro lab buildings in their entirety, and construct a new Administration Building in the same area but not in the same footprint to provide a more efficient and effective working environment.


4. The existing administration office accommodates the administration functions for the field office and dam and houses the offices for the Area Operations Manager, technical staff, and administrative staff. The Falcon Dam Field Office staff will remain in the existing building while the new administration building is constructed.


5. Demolition of the existing administration, security, and hydro lab buildings will be accomplished after all administrative staff has been moved in to the new administration building.


6. At the conclusion of the project, the new administration building shall be a fully commissioned (turn-key) building able to operate for its intended use with all utilities, to include, but not limited to water, sanitary sewer, communications, electrical, fire protection system(s), etc.


Major Construction Tasks


1. Design and construct a new Administration Building, including all planning, design work, coordination, permitting, labor, material, tools, equipment, construction, testing, inspection, commissioning, demolition, cleanup, and all necessary general conditions, that may be reasonably inferred from the Contract Documents to provide for all work for the design and construction of a new single-story administration building and demolition of the existing buildings.


2. Provide a minimum of two (2) floor plans for USIBWC to choose from.


3. Create all construction specifications and drawings required to complete the project.


4. Design and build to a minimum LEED Silver certification.


5. Encompass the historical and architectural aspects of the surrounding buildings. The purpose is to minimally affect the historic integrity of the district.


6. Construct in a vacant, previously disturbed area.


7. Meet federal OSHA standards and current environmental laws to provide a more efficient and effective working environment.


Magnitude


The magnitude of the project is between $1,000,000 and $5,000,000.


Performance Period


All work shall be completed within four hundred (400) calendar days after the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.


This requirement is a 100% Small Business Set Aside.


This requirement shall be solicited using Two-Phase Design-Build Selection Procedures in accordance with Federal Acquisition Regulation (FAR) SUBPART 36.3. 

PLEASE NOTE THE SITE VISIT INFORMATION LISTED UNDER SECTION L.01 PRE-PROPOSAL CONFERENCE AND SITE VISIT OF THE SOLICITATION DOCUMENT RFP IBM15R0005

Update #1 ·

Added: Jun 30, 2015 2:08 pm This is ONLY a Presolicitation Notice. A forthcoming solicitation will include information on how to obtain all relevant documentation. All responsible sources may submit a proposal to be considered by the Agency when the solicitation is posted.

This is NOT a request for proposal. Please do not submit a proposal in response to this Presolicitation Notice.


General Project Information


A recent draft historic properties inventory report dated February 2011 identified the Falcon Dam and Falcon Village as a Historic District that is eligible for the National Register of Historic Places. The village was constructed to house personnel that operate and maintain Falcon International Dam and Power Plant. 


The dam provides water conservation, irrigation, hydroelectric power generation, flood control, and recreational benefits, and serves as an international port of entry across the Rio Grande between Starr County, Texas, USA and Tamaulipas, México. Construction on the dam began in December 1950 and on October 19, 1953, as construction neared completion, U.S. President Dwight D. Eisenhower and Mexican President Adolfo Ruiz Cortines met at the center of the dam to dedicate it to the well-being of the residents of both countries.


Falcon International Dam was completed on April 8, 1954. The existing administrative building was constructed during the same time frame and is located within Falcon Village of off F.M. 2098, Reservoir Road, and is no longer meeting the needs of the staff due to its size and outdated design. The period of significance for the historic district is 1950 through 1965. The existing building will need to be demolished. Demolition is part of this project.


General Description of the Work

The USIBWC plans to construct a new administration building.


1.  The total building foot print is proposed to be between 5,300 and 5,600 square feet. The new building will consist of a minimum of nine (9) offices, hydro laboratory, conference room, and security office area including a weapons locker room, break room, fireproof vault room, IT server room, and reception area.


2.  This building will replace the existing Falcon Dam's Administration Building. The existing building is no longer functional with respect to building codes, OSHA requirements, office space, needed technological improvements, and mechanical efficiency. 


3.  The objective is to demolish and dispose of the existing administration, security, and hydro lab buildings in their entirety, and construct a new Administration Building in the same area but not in the same footprint to provide a more efficient and effective working environment.   


4.  The existing administration office accommodates the administration functions for the field office and dam and houses the offices for the Area Operations Manager, technical staff, and administrative staff. The Falcon Dam Field Office staff will remain in the existing building while the new administration building is constructed.


5.  Demolition of the existing administration, security, and hydro lab buildings will be accomplished after all administrative staff has been moved in to the new administration building.


6.  At the conclusion of the project, the new administration building shall be a fully commissioned (turn-key) building able to operate for its intended use with all utilities, to include, but not limited to water, sanitary sewer, communications, electrical, fire protection system(s), etc. 


Major Construction Tasks

1.  Design and construct a new Administration Building, including all planning, design work, coordination, permitting, labor, material, tools, equipment, construction, testing, inspection, commissioning, demolition, cleanup, and all necessary general conditions, that may be reasonably inferred from the Contract Documents to provide for all work for the design and construction of a new single-story administration building and demolition of the existing buildings.


2.  Provide a minimum of two (2) floor plans for USIBWC to choose from.


3.  Create all construction specifications and drawings required to complete the project.


4.  Design and build to a minimum LEED Silver certification.


5.  Encompass the historical and architectural aspects of the surrounding buildings. The purpose is to minimally affect the historic integrity of the district. 

6.  Construct in a vacant, previously disturbed area. 


7.  Meet federal OSHA standards and current environmental laws to provide a more efficient and effective working environment.


Magnitude


The magnitude of the project is between $1,000,000 and $5,000,000. 


Performance Period


All work shall be completed within four hundred (400) calendar days after the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.


Other Information


The solicitation, plans, and specifications are expected to be posted on or about July 15, 2015 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by July 15, 2015 that is because the solicitation is not available for posting). The solicitation will be available for a minimum of thirty (30) calendar days. Award is expected to be made on or before September 30, 2015.


This is a Presolicitation Notice. The solicitation will include information on how to obtain the relevant documentation. There is no charge for the solicitation documents. All responsible sources may submit a proposal to be considered by the Agency. 


This requirement is a 100% Small Business Set Aside.


This requirement shall be solicited using Two-Phase Design-Build Selection Procedures in accordance with Federal Acquisition Regulation (FAR) SUBPART 36.3.

Attachments

Files attached to this notice, newest first
File Type Posted
IBM15R0005_SOW_DB_Falcon_Admin_Bldg_20150730_1.pdf PDF
Amendment_A001.pdf PDF
QUESTIONS_ _ANSWERS.pdf PDF
Pre-solicitation_Meeting_-_Sign_In_Sheet.pdf PDF
J12_Evaluation_Factors_for_Award_20150804.pdf PDF
MOA_with_THC.pdf PDF
Geotechnical_Report.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Client_Authorization_Letter.docx DOCX document
Evaluation_Factors_for_Award.docx DOCX document
SOW_Falcon_Admin_Bldg.pdf PDF
THC_response_on_FRP.pdf PDF
Asbestos_Lead_Paint_Survey_2014.pdf PDF
RFP_IBM15R0005.pdf PDF
Falcon_Sewer_System.pdf PDF
Asbestos_Lead_Paint_Survey_04.pdf PDF
Fiber_optic_system.pdf PDF
Weather_Records.docx DOCX document
Show all 18

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
New Falcon Dam Administration Building Latest Award Notice
New Falcon Dam Administration Building This notice · Original Award Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity