NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y Construct Of Structures/Facilities
Place of performance
Will Rogers Air National Guard Base 5901 Air Guard Drive Oklahoma City Ok 73179 USA

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Amendment 0001: Upload Drawings and Request for Information (RFI) Sheet to FBO.Gov. RFI's should be emailed to Christine.m.walker30.mil@mail.mil. All RFI's to be submitted No Later Than 3 July 2019 1200 PM CST with responses posted to FBO.Gov No Later Than 9 July 2019 3:00 PM CST. -- System not allowing for Drawings Upload.  Email Christine.m.walker30.mil@mail.mil for emailed Drawings or a disc can be picked up from Will Rogers Air National Guard Base 5901 Air Guard Drive OKC, OK 73179. 

Amendment 0002: Post Site Visit Sign In Sheet and Extend Response Date of Solicitation. Acknowledgement of RFI's 1 through 9 posted to FBO.Gov 26 June 2019.  Response Date Changed to: 16 July 2019 at 1400 PM CST.

Update #2 ·

Amendment 0001: Upload Drawings and Request for Information (RFI) Sheet to FBO.Gov. RFI's should be emailed to Christine.m.walker30.mil@mail.mil. All RFI's to be submitted No Later Than 3 July 2019 1200 PM CST with responses posted to FBO.Gov No Later Than 9 July 2019 3:00 PM CST. -- System not allowing for Drawings Upload.  Email Christine.m.walker30.mil@mail.mil for emailed Drawings or a disc can be picked up from Will Rogers Air National Guard Base 5901 Air Guard Drive OKC, OK 73179. 

Update #1 ·

 

Synopsis:

 

Entry Control Point (ECP) Upgrades, Main Gate Project Number: YZEU152007.

The work to be accomplished under this contract consists of furnishing all labor, tools, equipment, materials, accessories, and incidentals necessary to perform the task list below (but not limited to) description and also shown on the contract drawings and specifications.:

 

The objective of this project is to complete construction on entry-control upgrades to achieve compliance with current security criteria.

 

This project is being solicited as a Small Business Set Aside. The North American Industry Classification System (NAICS) code is 236220, and the Small Business Size Standard is $36.5M in average annual receipts for the past three years. Construction project magnitude is between $250,000.00 to $500,000.00. Persons who intend to bid are strongly encouraged to attend the Pre-Bid Conference. See Section 00100 for location and date. All documents including the plans and specifications will be available only from the Fed Biz Ops website: www.fbo.gov

 

Solicitation cover page:

 

 

SUMMARY OF WORK

 

 

PART 1 GENERAL

 

1.1 WORK COVERED BY CONTRACT DOCUMENTS

 

•1.1.1    Project Description

 

Complete construction on entry control upgrades.

 

Civil (where indicated on plans):

•           Demolition of existing asphalt pavement, concrete pavement and concrete curbs to prepare for installation of new pavement, islands and curbs.

•           Removal and reinstallation of existing bollards where indicated on the drawings.

•           Removal of existing cable barrier and footings.

•           Install new concrete raised center islands to separate inbound and outbound lanes in the response zones and to channelize the threat vehicle. Center islands to be colored and textured concrete and curbs.

•           Install new concrete pavements at roadway where indicated.

•           Re-core pavement and reinstall existing bollards.

•           Install concrete bollard storage area.

•           Install three swing gates to improve truck operations.

•           Install cable barrier for new inbound truck operations improvements.

•           Install new traffic signal pole, lighting and wiring. Coordinate with Electrical.

•           Install speed limit signage and concrete base.

•           Install new 12'x12' concrete pad.

•           Assorted roadway paint striping.

 

Electrical (where indicated on plans):

•           Removal and reinstallation of existing light poles.

•           Removal of existing traffic lights.

•           Installation of new lighting at Guard House.

•           Install new traffic signal pole, lighting and wiring. Coordinate with Civil.

•           Install new light fixtures on existing light poles.

•           Install new motion sensors on existing light poles.

•           Install new light poles, conduit and wiring at raised Concrete Island. Connect to existing Guard Shack Panel.

•           Install new receptacle outlet at covered inspection area.


A site visit will be held: 25 June 2019, 1300 PM CST

Will Rogers Air National Guard Base OKC, OK 73179

BLDG 1007 Conference Room

Attachments

Files attached to this notice, newest first
File Type Posted
152007_RFI__12_cable_barrier_spring_response.pdf PDF
RFI_0011.pdf PDF
152007_RFI__13_Bollard_Storage_Location.pdf PDF
19-R-5001-0003.pdf PDF
RFI_0010.doc DOC document
W912L619R50010002_Amendment_0002.pdf PDF
Front_Gate_ECP_Upgrade_Site_Visit_Sign_In_Sheet.pdf PDF
152007_RFI__2_-_Swing_Gate_Demo.pdf PDF
152007_RFI__8_UFC_requirements.pdf PDF
152007_RFI__5_-_signage_combined_V2_.pdf PDF
152007_RFI__7_removable_curbs.pdf PDF
152007_RFI__1_-_Barriers.pdf PDF
152007_RFI__6_signage_V3.pdf PDF
152007_RFI__9_cable_barriers_V2.pdf PDF
152007_RFI__4_-_E005_For_reference_only.pdf PDF
152007_RFI__3_-_Gate_Closure.pdf PDF
W912L619R50010001.pdf PDF
RFI.doc DOC document
WRANGB_COMBINED_SPECS_152007_FINAL_Upload_in_FBO.pdf PDF
W912L6-19-R-5001.pdf PDF
Show all 20

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity