FY23 Savannah Inner Harbor Dredging
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912HN23B5002
- Agency
-
ENDIST Savannah
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation is issued by the U.S. Army Corps of Engineers Savannah District to procure maintenance dredging services for the Savannah Inner Harbor navigation project located in Georgia. The contractor will provide dredging, disposal, and related services to maintain depths and widths in the Savannah Harbor navigation project. Key requirements include removing up to four million cubic yards of sediment from the inner harbor using a hydraulic dredge, with disposal at upland confined areas over a one-year period from notice to proceed. Bids are due by the date specified on the solicitation cover sheet, and evaluation will result in award of a single firm fixed price contract.
There is no set-aside designation for this procurement. The primary NAICS code is 237990 and PSC code is D302. The estimated value is between $25-100 million. Current contractors performing work in the Savannah Harbor include those maintaining the confined upland disposal areas. Key details include dredging depths ranging from 30-47 feet and potential cadmium sediment management. The place of performance is the Savannah Inner Harbor navigation project located in Chatham County, Georgia.
Notice text
3 versions
Update #3 · Latest ·
This SOLICITATION is for the FY23 Savannah Inner Harbor Maintenance Dredging. This acquisition is being offered as an unrestricted competitive solicitation and will result in a Firm Fixed Price Contract Award. The magnitude of this requirement per DFARS 236.204(ii) is between $25,000,000.00 and $100,000,000. Project Location: The work is located in the deep draft Savannah Harbor navigation project in Georgia. The Savannah Habor project is located on the border of Georgia (GA) and South Carolina (SC) in Chatham and Jasper Counties. Project Description: The Savannah Inner Harbor Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a hydraulic cutterhead dredge, and the duration is expected to be one year from Notice to Proceed. Up to four million cubic yards of maintenance material is expected to be removed from the inner harbor. The work is located in the deep draft Savannah Harbor navigation project in Georgia in the vicinity of Chatham County, Georgia (GA) and Jasper County, South Carolina (SC). The Savannah Inner Harbor channel is 47 ft. deep MLLW and 500 ft. wide to the upper end of Kings Island Turning Basin: 36 ft. deep MLLW and 400 ft. wide to the upper end of Argyle Island Turning Basin; and 30 ft. deep MLLW and 200 ft. wide to the upper limit of the project. Savannah Harbor?s Kings Island Turning Basin (KITB) is the primary turning basin for large civilian and military ships, lying adjacent to the Georgia Ports Authority docks. KITB requires dredging twice a year to allow the loaded ships to freely turn when using the port. Up to 1.6 million cubic yards of maintenance material is removed from the KITB annually. Other contractor(s) may be working for the Savannah District on the Savannah Harbor, to include confined upland dredged material containment areas and designated staging areas. If such work occurs, the contractors shall coordinate activities under the direction of the Contracting Officer. A majority of the material dredged from the Savannah Inner Harbor must be placed in upland confined disposal areas adjacent to the Savannah River. Savannah confined upland disposal areas DMCAs 12A, 13A, 13B and Jones Oysterbed Island are owned by local sponsor Georgia Department of Transportation. Disposal areas DMCAs 14A and 14B are owned by the Joint Project Office of the Georgia and South Carolina Port Authorities. Portions of DMCAs 2A and Jones/Oysterbed are owned by the Georgia Department of Transportation and the US Fish and Wildlife Service. DMCA 1N is owned entirely by the US Fish and Wildlife Service. The Federal Government holds existing easements on all confined upland disposal areas in the Savannah Harbor except DMCA 1N which has a Memorandum of Understanding. Environmental windows limit the timing of dredging in the Savannah Inner Harbor. The environmental windows in Savannah include a Striped Bass spawning window (2 weeks between approximate dates 1 April through 15 May timeframe) which limits the amount and timing of dredging above station 63+360 (River Mile 12), and a dissolved oxygen window (approximately July 1 through September 30). To protect sturgeon aggregation areas in the upper river, no dredging is allowed above STA105+500 1 May through 31 October. Certain reaches of O and M sediments may contain cadmium (Cd) in levels significant enough to harm foraging avian species in the DMCAs. Therefore, O and M sediments in those reaches will be tested by the Government prior to dredging. If Cd is found in those sediments equal to or greater than 14 mg/kg, then options will be exercised that include disposal of the sediments in specific DMCAs under special handling conditions. Obstructions are objects or materials in the required side slope cross sections or in the existing ground surface which are unknown at the time of encounter by the dredge or identified by pre and post hydrographic surveys, and monthly condition surveys. Obstructions are objects which cannot be removed by a hydraulic pipeline dredge. The Contractor may encounter obstructions during dredging operations and must remove the objects or materials to provide the required section as shown on the cross-section plates. If the Contractor is performing maintenance dredging with a pipeline dredge, the dredge must act as a probe for obstructions. The object removed will be the property of the Contractor unless it has been determined to be culturally significant. The base contract will include mobilization/demobilization, maintenance dredging, moves, dive team diving, and equipment rental for obstruction removal. Contract options include Cd dredging with placement to the backside of DA 14B and maintenance dredging as cap material placed on top of the Cd dredged material.
Update #2 ·
This SOLICITATION is for the FY23 Savannah Inner Harbor Maintenance Dredging. This acquisition is being offered as an unrestricted competitive solicitation and will result in a Firm Fixed Price Contract Award. The magnitude of this requirement per DFARS 236.204(ii) is between $25,000,000.00 and $100,000,000. Project Location: The work is located in the deep draft Savannah Harbor navigation project in Georgia. The Savannah Habor project is located on the border of Georgia (GA) and South Carolina (SC) in Chatham and Jasper Counties. Project Description: The Savannah Inner Harbor Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a hydraulic cutterhead dredge, and the duration is expected to be one year from Notice to Proceed. Up to four million cubic yards of maintenance material is expected to be removed from the inner harbor. The work is located in the deep draft Savannah Harbor navigation project in Georgia in the vicinity of Chatham County, Georgia (GA) and Jasper County, South Carolina (SC). The Savannah Inner Harbor channel is 47 ft. deep MLLW and 500 ft. wide to the upper end of Kings Island Turning Basin: 36 ft. deep MLLW and 400 ft. wide to the upper end of Argyle Island Turning Basin; and 30 ft. deep MLLW and 200 ft. wide to the upper limit of the project. Savannah Harbor?s Kings Island Turning Basin (KITB) is the primary turning basin for large civilian and military ships, lying adjacent to the Georgia Ports Authority docks. KITB requires dredging twice a year to allow the loaded ships to freely turn when using the port. Up to 1.6 million cubic yards of maintenance material is removed from the KITB annually. Other contractor(s) may be working for the Savannah District on the Savannah Harbor, to include confined upland dredged material containment areas and designated staging areas. If such work occurs, the contractors shall coordinate activities under the direction of the Contracting Officer. A majority of the material dredged from the Savannah Inner Harbor must be placed in upland confined disposal areas adjacent to the Savannah River. Savannah confined upland disposal areas DMCAs 12A, 13A, 13B and Jones Oysterbed Island are owned by local sponsor Georgia Department of Transportation. Disposal areas DMCAs 14A and 14B are owned by the Joint Project Office of the Georgia and South Carolina Port Authorities. Portions of DMCAs 2A and Jones/Oysterbed are owned by the Georgia Department of Transportation and the US Fish and Wildlife Service. DMCA 1N is owned entirely by the US Fish and Wildlife Service. The Federal Government holds existing easements on all confined upland disposal areas in the Savannah Harbor except DMCA 1N which has a Memorandum of Understanding. Environmental windows limit the timing of dredging in the Savannah Inner Harbor. The environmental windows in Savannah include a Striped Bass spawning window (2 weeks between approximate dates 1 April through 15 May timeframe) which limits the amount and timing of dredging above station 63+360 (River Mile 12), and a dissolved oxygen window (approximately July 1 through September 30). To protect sturgeon aggregation areas in the upper river, no dredging is allowed above STA105+500 1 May through 31 October. Certain reaches of O and M sediments may contain cadmium (Cd) in levels significant enough to harm foraging avian species in the DMCAs. Therefore, O and M sediments in those reaches will be tested by the Government prior to dredging. If Cd is found in those sediments equal to or greater than 14 mg/kg, then options will be exercised that include disposal of the sediments in specific DMCAs under special handling conditions. Obstructions are objects or materials in the required side slope cross sections or in the existing ground surface which are unknown at the time of encounter by the dredge or identified by pre and post hydrographic surveys, and monthly condition surveys. Obstructions are objects which cannot be removed by a hydraulic pipeline dredge. The Contractor may encounter obstructions during dredging operations and must remove the objects or materials to provide the required section as shown on the cross-section plates. If the Contractor is performing maintenance dredging with a pipeline dredge, the dredge must act as a probe for obstructions. The object removed will be the property of the Contractor unless it has been determined to be culturally significant. The base contract will include mobilization/demobilization, maintenance dredging, moves, dive team diving, and equipment rental for obstruction removal. Contract options include Cd dredging with placement to the backside of DA 14B and maintenance dredging as cap material placed on top of the Cd dredged material.
Update #1 ·
This SOLICATATION is for the FY23 Savannah Inner Harbor Maintenance Dredging. This acquisition is being offered as an unrestricted competitive solicitation and will result in a Firm Fixed Price Contract Award. The magnitude of this requirement per DFARS 236.204(ii) is between $25,000,000.00 and $100,000,000. Project Location: The work is located in the deep draft Savannah Harbor navigation project in Georgia. The Savannah Habor project is located on the border of Georgia (GA) and South Carolina (SC) in Chatham and Jasper Counties. Project Description: The Savannah Inner Harbor Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a hydraulic cutterhead dredge, and the duration is expected to be one year from Notice to Proceed. Up to four million cubic yards of maintenance material is expected to be removed from the inner harbor. The work is located in the deep draft Savannah Harbor navigation project in Georgia in the vicinity of Chatham County, Georgia (GA) and Jasper County, South Carolina (SC). The Savannah Inner Harbor channel is 47 ft. deep MLLW and 500 ft. wide to the upper end of Kings Island Turning Basin: 36 ft. deep MLLW and 400 ft. wide to the upper end of Argyle Island Turning Basin; and 30 ft. deep MLLW and 200 ft. wide to the upper limit of the project. Savannah Harbor?s Kings Island Turning Basin (KITB) is the primary turning basin for large civilian and military ships, lying adjacent to the Georgia Ports Authority docks. KITB requires dredging twice a year to allow the loaded ships to freely turn when using the port. Up to 1.6 million cubic yards of maintenance material is removed from the KITB annually. Other contractor(s) may be working for the Savannah District on the Savannah Harbor, to include confined upland dredged material containment areas and designated staging areas. If such work occurs, the contractors shall coordinate activities under the direction of the Contracting Officer. A majority of the material dredged from the Savannah Inner Harbor must be placed in upland confined disposal areas adjacent to the Savannah River. Savannah confined upland disposal areas DMCAs 12A, 13A, 13B and Jones Oysterbed Island are owned by local sponsor Georgia Department of Transportation. Disposal areas DMCAs 14A and 14B are owned by the Joint Project Office of the Georgia and South Carolina Port Authorities. Portions of DMCAs 2A and Jones/Oysterbed are owned by the Georgia Department of Transportation and the US Fish and Wildlife Service. DMCA 1N is owned entirely by the US Fish and Wildlife Service. The Federal Government holds existing easements on all confined upland disposal areas in the Savannah Harbor except DMCA 1N which has a Memorandum of Understanding. Environmental windows limit the timing of dredging in the Savannah Inner Harbor. The environmental windows in Savannah include a Striped Bass spawning window (2 weeks between approximate dates 1 April through 15 May timeframe) which limits the amount and timing of dredging above station 63+360 (River Mile 12), and a dissolved oxygen window (approximately July 1 through September 30). To protect sturgeon aggregation areas in the upper river, no dredging is allowed above STA105+500 1 May through 31 October. Certain reaches of O and M sediments may contain cadmium (Cd) in levels significant enough to harm foraging avian species in the DMCAs. Therefore, O and M sediments in those reaches will be tested by the Government prior to dredging. If Cd is found in those sediments equal to or greater than 14 mg/kg, then options will be exercised that include disposal of the sediments in specific DMCAs under special handling conditions. Obstructions are objects or materials in the required side slope cross sections or in the existing ground surface which are unknown at the time of encounter by the dredge or identified by pre and post hydrographic surveys, and monthly condition surveys. Obstructions are objects which cannot be removed by a hydraulic pipeline dredge. The Contractor may encounter obstructions during dredging operations and must remove the objects or materials to provide the required section as shown on the cross-section plates. If the Contractor is performing maintenance dredging with a pipeline dredge, the dredge must act as a probe for obstructions. The object removed will be the property of the Contractor unless it has been determined to be culturally significant. The base contract will include mobilization/demobilization, maintenance dredging, moves, dive team diving, and equipment rental for obstruction removal. Contract options include Cd dredging with placement to the backside of DA 14B and maintenance dredging as cap material placed on top of the Cd dredged material.
Files
| File | Type | Posted |
|---|---|---|
| C.02 - Bid Abstract_W912HN23B5002(signed by KO).pdf | ||
| C.02 - Bid Abstract_W912HN23B5002.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Award Notice - W912HN23B5002/W912HN23C5003 - FY23 Savannah Inner Harbor Dredging | Award Notice | |
| This notice | Solicitation | |
| Pre-Solicitation Notice - FY23 Savannah Inner Harbor Dredging | Pre-Solicitation | |
| FY23 Savannah Inner Harbor Dredging | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Sources Sought for FY26 Atlantic Intracoastal Waterway Maintenance Dredging ��������� Select Sites | ENDIST Savannah | No set-aside | |
| Tybee Island Shoreline Protection Project | ENDIST Savannah | No set-aside | |
| Annual Maintenance Dredging of Morehead City Inner Harbor | ENDIST Wilmington | No set-aside | |
| New Orleans Harbor and Various Bar Channels Cutterhead Dredge 3-2025 | ENDIST New Orleans | No set-aside | |
| Calcasieu Bar River Channel, Pascagoula Harbor, and Panama City Harbor Maintenance Dredging | ENDIST Wilmington | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity