C.02 - Bid Abstract_W912HN23B5002(signed by KO).pdf
PDF 310 KB Posted
- Attached to
- FY23 Savannah Inner Harbor Dredging
- Solicitation number
- W912HN23B5002
About this file
This solicitation is for a firm fixed price contract for maintenance dredging services in the Savannah Inner Harbor, Georgia. The contractor will provide dredging, disposal, and related services to maintain depths and widths in the Savannah Harbor navigation project. Key requirements include removing up to four million cubic yards of sediment from the inner harbor using a hydraulic dredge, with disposal at upland confined areas. Dredging will take place over approximately one year from notice to proceed. The solicitation was issued by the US Army Corps of Engineers Savannah District and bids are due by the date specified on the solicitation cover sheet. Evaluation will result in award of a single firm fixed price contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C.02 - Bid Abstract_W912HN23B5002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LINE ITEM
DESCRIPTION
QTY UNIT IGE Unit Price Marinex Construction Compared to IGE Michels Corp Compared to IGE Week Marine Inc. Compared to IGE IGE
AMOUNT AMOUNT AMOUNT AMOUNT
0001 Mobilization and Demobilization 1 Job 1,964,000.00$ $900,000.00 $4,790,822.11 $10,750,000.00 $1,964,000.00 0002 Maintenance Dredging King Island Turning Basin (INFORMATION ONLY)
0002AA First 1,400,000 cubic Yards 1,400,000 CY 5.15$ $7,000,000.00 $7,532,000.00 $11,200,000.00 $7,210,000.00 0002AB All Over 1,400,000 Cubic Yards 100,000 CY 5.15$ $500,000.00 $538,000.00 $1,000,000.00 $515,000.00
Maintenance Dredging Station 103+000 to 70+000 and March Island Turning Basin
1,650,000
CY
6.50$ $8,943,000.00 $8,877,000.00
$19,387,500.00 $10,725,000.00
0004 Maintenance Dredging Rental (INFORMATION ONLY)
0004AA First 24hrs 24 hr $ 4,900.00 $76,800.00 $41,550.72 $240,000.00 $117,600.00 0004AB All Over 24hrs 12 hr $ 4,900.00 $38,400.00 $20,775.36 $120,000.00 $58,800.00
Maintenance Dredging Station 170+000 to 30+000 and Fig Island Turning Basin (INFORMATION ONLY)
0005AA
First 375,000 Cubic Yards
375,000 CY $ 4.75 $1,695,000.00 $2,058,750.00 $6,562,500.00
$1,781,250.00
0005AB
All over 375,000 Cubic Yards
100,000 CY $ 4.75 $452,000.00 $521,000.00 $1,750,000.00
$475,000.00
Maintenance Dredging Station 30+00 to 0+000
0006AA
First 100,000 Cubic Yards
100,000 CY $ 6.40 $568,000.00 $521,000.00 $1,875,000.00
$640,000.00
0006AB
All over 100,000 Cubic Yards
25,000 CY $ 6.40 $142,000.00 $130,250.00 $468,750.00
$160,000.00
Moves greater than 10,000 Feet
(INFORMATION ONLY)
0007AA
First Move
1 EA $ 90,000.00 $90,000.00 $91,512.89 $50,000.00
$90,000.00
0007AB
All Over 1 Move
5 EA $ 90,000.00 $375,000.00 $457,564.25 $250,000.00
$450,000.00
Dive team to include Mobilization and Demobilization of Personnel, materials and Equipment
(INFORMATION ONLY)
0008AA
Dive team to include Mobilization and Demobilization of Personnel, materials and Equipment
1 day $ 6,000.00 $5,000.00 $16,435.93 $7,500.00 $6,000.00
0008AB
Dive team to include Mobilization and Demobilization of Personnel, materials and Equipment
2 day $ 6,000.00 $10,000.00 $24,580.42 $15,000.00 $12,000.00
Equipment Rental for Obstruction Removal To include Mobilization and Demobilization of all equipment with a minimum of 100-ton crane (INFORMATION ONLY)
009AA
Equipment Rental for Obstruction Removal To include Mobilization and Demobilization of all equipment with a minimum of 100-ton crane 1 day $ 25,000.00 $10,000.00 $10,500.00 $35,000.00 $25,000.00
0009AB
Equipment Rental for Obstruction Removal To include Mobilization and Demobilization of all equipment with a minimum of 100-ton crane 2 day $ 25,000.00 $20,000.00 $21,000.00 $70,000.00 $50,000.00
Subtotal Base Bid CLINs 0001 - 0009 $20,825,200.00 -14.23% $25,652,741.68 5.66% $53,781,250.00 121.51% $24,279,650.00
OPTION: Maintenance Dredging with disposal in backside of DA 14B to include management of Cadmium Station
37+000 to 24+000 (INFORMATION ONLY)
0010AA OPTION 1: First 50,000 Cubic Yards 50,000 CY $ 6.40 $44,500.00 $260,500.00 $75,000.00 $320,000.00
0010AB OPTION 2: All Over 50,000 Cubic Yards 25,000 CY $ 6.40 $22,250.00 $128,750.00 $62,500.00 $160,000.00
Maintenance Dredging with disposal in backside of DA 14B to include management of Cadmium Station 45+000 to
41+000 (INFORMATION ONLY)
0011AA OPTION 3: First 50,000 Cubic Yards 50,000 CY $ 8.05 $44,500.00 $226,000.00 $75,000.00 $402,500.00
0011AB OPTION 4: All Over 50,000 Cubic Yards 25,000 CY $ 8.05 $22,250.00 $113,000.00 $62,500.00 $201,250.00
Maintenance Dredging with disposal in backside of DA 14B to include management of Cadmium Station
55+000 to 53+000 (INFORMATION ONLY) 0012AA OPTION 5: First 50,000 Cubic YardsFFP 50,000 CY 9.90$ $44,500.00 $258,500.00 $75,000.00 $495,000.00 0012AB OPTION 6: All Over 50,000 Cubic Yards 25,000 CY 9.90$ $22,250.00 $129,250.00 $62,500.00 $247,500.00
0013 Maintenance Dredging With disposal in backside of DA 14B to cap the Cadmium material Station 24+000 to 16+000 (INFORMATION ONLY)
0013AA OPTION 7: First 50,000 Cubic Yards 50,000 CY $ 8.60 $44,500.00 $226,000.00 $75,000.00 $430,000.00 0013AB OPTION 8: All Over 50,000 Cubic Yard 30,000 CY $ 8.60 $26,700.00 $135,600.00 $75,000.00 $258,000.00
0014 Maintenance Dredging with disposal in backside of DA 14B to cap the of Cadmium material Station 41+000 to 37+000 (INFORMATION ONLY)
0014AA OPTION 9: First 50,000 Cubic Yards 50,000 CY $ 9.65 $ 44,500.00 $226,000.00 $75,000.00 $482,500.00 0014AB OPTION 10: All Over 50,000 Cubic Yards 30,000 CY $ 9.65 $ 26,700.00 $135,600.00 $75,000.00 $289,500.00
0015 Maintenance Dredging With disposal in backside of DA 14B to cap the Cadmium material Station 53+000 to 45+000 (INFORMATION ONLY)
0015AA OPTION 11: First 50,000 Cubic Yard 50,000 CY $ 9.85 $44,500.00 $260,500.00 $75,000.00 $492,500.00 0015AB OPTION 12: All Over 50,000 Cubic Yard 30,000 CY $ 9.85 $26,700.00 $156,300.00 $75,000.00 $295,500.00
0016 Maintenance Dredging 105+500 to 103+000 to include Widener and Argyle Island Turning Basin
(INFORMATION ONLY)
0016AA OPTION 13: First 100,000 Cubic Yards 100,000 CY $ 3.50 $450,000.00 $715,000.00 $800,000.00 $350,000.00 0016AB OPTION 14: All Over 100,000 Cubic Yards 100,000 CY $ 3.50 $450,000.00 $715,000.00 $800,000.00 $350,000.00
0017 OPTION 15: Maintenance Dredging Station 103+000 to 70+000 and Marsh Island Turning Basin
600,000 CY $ 6.50 $3,252,000.00 $3,228,000.00 $6,000,000.00
$3,900,000.00
0018 OPTION 16: Maintenance Dredging Station 103+000 to 70+000 and Marsh Island Turning Basin
200,000 CY $ 6.50 $1,084,000.00 $1,076,000.00 $2,000,000.00
$1,300,000.00
$5,649,850.00 $7,990,000.00 $10,462,500.00 $9,974,250.00 $26,475,050.00 -22.71% $33,642,741.68 -1.78% $64,243,750.00 87.55% $34,253,900.00
OPTIONS TOTAL CLINS 0010AA - 0018
GRAND TOTAL BASE CLINS 0001-0018
Bid Abstract W912HN23B5002 - Savannah Inner Harbour Dredging
BID Abstract
| 2023-06-09T10:50:17-0400 | |
| CANTY.GLENDA.ADDIE.1056053952 |
File details come from the government source that posted it. Updated .