Culvert Replacement Two Phases
Awarded Award Notice Posted
- Solicitation number
- AG-82D7-S-16-0007
- Agency
- Region 2 - Rocky Mountain Region Forest Service, Department of Agriculture
- Awarded
- to ACA Products Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- AG-82D7-S-16-0007 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- The East Fork Eagle culvert is located on the Eagle/Holy Cross District on the White River National Forest approximately 16.3 miles south of Minturn, CO on National Forest System Road 714. Second phase option Muddy Creek Culvert is located on the Eagle/Holy Cross District approximately 4 mile north of Wolcott, CO. Glenwood Springs, Colorado 81601, United States
Notice details come from SAM.gov. Updated .
Notice text
7 versions
Update #7 · Latest ·
Added: May 05, 2016 3:22 pm
Modified: Jun 20, 2016 11:49 amTrack Changes
BID PACKAGE SUBMISSION:
Bid Packages MUST be marked AG-82D7-S-16-0007 and submitted in writing and addressed to Lonnie D. Root, Contracting Officer either by email to lroot@fs.fed.us, or hard copy to the address below.
Lonnie D. Root
Contracting Officer
White River National Forest
900 Grand Ave
Glenwood Springs, CO 81601
*******************************************************************
SOLICITATION PERIOD: 05/19/16 - 06/20/16
BID DUE DATE: 06/20/2016 5:00PM MT
*******************************************************************
East Fork Eagle Culvert Replacement with an Optional Second Phase for Muddy Creek Culvert Replacement contingent on funding
Purpose: The intent of the project is to replace undersized culverts on National Forest System Roads with aquatic organism passages for the purposes of habitat restoration, flood capacity and resiliency, road reconstruction, and to upgrade aging infrastructure to current forest standards.
Scope of Work: The work shall consist of what is shown on the plans and stated in the specifications for East Fork Eagle Road and second phase option Muddy Pass/Red Sandstone road. Work includes, but is not limited to: traffic control signs, install stream flow diversion system at existing culvert, remove existing culvert, excavation, construction or placement of footings, construction of stream channel and banks, erect plate box culvert, structural backfill and embankment, surface aggregate placement, seeding, planting, and final site work.
Update #6 ·
Added: May 05, 2016 3:22 pm
Modified: Jun 17, 2016 3:58 pmTrack Changes
BID PACKAGE SUBMISSION:
Bid Packages MUST be marked AG-82D7-S-16-0007 and submitted in writing and addressed to Lonnie D. Root, Contracting Officer either by email to lroot@fs.fed.us, or hard copy to the address below.
Lonnie D. Root
Contracting Officer
White River National Forest
900 Grand Ave
Glenwood Springs, CO 81601
*******************************************************************
SOLICITATION PERIOD: 05/19/16 - 06/20/16
BID DUE DATE: 06/20/2016 5:00am MT
*******************************************************************
East Fork Eagle Culvert Replacement with an Optional Second Phase for Muddy Creek Culvert Replacement contingent on funding
Purpose: The intent of the project is to replace undersized culverts on National Forest System Roads with aquatic organism passages for the purposes of habitat restoration, flood capacity and resiliency, road reconstruction, and to upgrade aging infrastructure to current forest standards.
Scope of Work: The work shall consist of what is shown on the plans and stated in the specifications for East Fork Eagle Road and second phase option Muddy Pass/Red Sandstone road. Work includes, but is not limited to: traffic control signs, install stream flow diversion system at existing culvert, remove existing culvert, excavation, construction or placement of footings, construction of stream channel and banks, erect plate box culvert, structural backfill and embankment, surface aggregate placement, seeding, planting, and final site work.
Update #5 ·
Added: May 05, 2016 3:22 pm
Modified: Jun 15, 2016 3:50 pmTrack Changes
BID PACKAGE SUBMISSION:
Bid Packages MUST be marked AG-82D7-S-16-0010 and submitted in writing and addressed to Lonnie D. Root, Contracting Officer either by email to lroot@fs.fed.us, or hard copy to the address below.
Lonnie D. Root
Contracting Officer
White River National Forest
900 Grand Ave
Glenwood Springs, CO 81601
*******************************************************************
SOLICITATION PERIOD: 05/19/16 - 06/20/16
BID DUE DATE: 06/20/2016 5:00am MT
*******************************************************************
East Fork Eagle Culvert Replacement with an Optional Second Phase for Muddy Creek Culvert Replacement contingent on funding
Purpose: The intent of the project is to replace undersized culverts on National Forest System Roads with aquatic organism passages for the purposes of habitat restoration, flood capacity and resiliency, road reconstruction, and to upgrade aging infrastructure to current forest standards.
Scope of Work: The work shall consist of what is shown on the plans and stated in the specifications for East Fork Eagle Road and second phase option Muddy Pass/Red Sandstone road. Work includes, but is not limited to: traffic control signs, install stream flow diversion system at existing culvert, remove existing culvert, excavation, construction or placement of footings, construction of stream channel and banks, erect plate box culvert, structural backfill and embankment, surface aggregate placement, seeding, planting, and final site work.
Update #4 ·
Added: Jun 03, 2016 3:14 pm
Modificaiton: 06/03
Includes the following documents:
Corrected SOW Package
Q&A from Pre-Bid Meeting
Davis Bacon Act Wage Determination
Mod also includes Price Range of $200,000 - $350,000 for both projects combined
also includes details on process for completing each phase/project as sited on revised OF1442 AG-82D7-S-16-0007
**************************************************************
Update #3 ·
Added: May 24, 2016 1:35 pm
PRE-BID & SITE VISIT MEETING
Date/Time:
June 1st, 2016 10:00am Mountain Standard Time
Location:
Minturn Ranger District Office
24747 US Hwy 24
Minturn, Colorado 81645
Meeting POC:
Erica Borum
970-945-3277
eborum@fs.fed.us
Update #2 ·
Added: May 05, 2016 3:22 pm
Modified: May 19, 2016 11:58 amTrack Changes
SOLICITATION PERIOD: 05/19/16 - 06/20/16
BID DUE DATE: 06/20/2016 5:00am MT
*******************************************************************
East Fork Eagle Culvert Replacement with an Optional Second Phase for Muddy Creek Culvert Replacement contingent on funding
Purpose: The intent of the project is to replace undersized culverts on National Forest System Roads with aquatic organism passages for the purposes of habitat restoration, flood capacity and resiliency, road reconstruction, and to upgrade aging infrastructure to current forest standards.
Scope of Work: The work shall consist of what is shown on the plans and stated in the specifications for East Fork Eagle Road and second phase option Muddy Pass/Red Sandstone road. Work includes, but is not limited to: traffic control signs, install stream flow diversion system at existing culvert, remove existing culvert, excavation, construction or placement of footings, construction of stream channel and banks, erect plate box culvert, structural backfill and embankment, surface aggregate placement, seeding, planting, and final site work.
Update #1 ·
Added: May 05, 2016 3:22 pm
East Fork Eagle Culvert Replacement with an Optional Second Phase for Muddy Creek Culvert Replacement contingent on funding
Purpose: The intent of the project is to replace undersized culverts on National Forest System Roads with aquatic organism passages for the purposes of habitat restoration, flood capacity and resiliency, road reconstruction, and to upgrade aging infrastructure to current forest standards.
Scope of Work: The work shall consist of what is shown on the plans and stated in the specifications for East Fork Eagle Road and second phase option Muddy Pass/Red Sandstone road. Work includes, but is not limited to: traffic control signs, install stream flow diversion system at existing culvert, remove existing culvert, excavation, construction or placement of footings, construction of stream channel and banks, erect plate box culvert, structural backfill and embankment, surface aggregate placement, seeding, planting, and final site work.
Attachments
| File | Type | Posted |
|---|---|---|
| Culvert_Replacements_Pre-bid.pdf | ||
| Revised_AG-82D7-S-16-0007.pdf | ||
| 11_-_geotech_report.pdf | ||
| EFE-Muddy_B-M_Clauses.pdf | ||
| davisbacon_CO13_CO23.pdf | ||
| EFE_SOI.xls | XLS spreadsheet | |
| Muddy_Schedule_of_Items.xls | XLS spreadsheet | |
| AG-82D7-S-16-0007_Solicitation.pdf | ||
| SectionMEvaluationCriteria.docx | DOCX document | |
| MuddyPlansMaps.pdf | ||
| EFE_UE-50_Proj_Specials_List.xls | XLS spreadsheet | |
| MuddyProj_Specials_List.xls | XLS spreadsheet | |
| EFE_UE-50_SOW_Specs_All.pdf | ||
| EFE_UE-50_drawings.pdf | ||
| Muddy_SOW_Specs_All.pdf | ||
| AG-82D7-S-16-0007_Solicitation.pdf | ||
| AG-82D7-S-16-0007_PreSolicitation.pdf |
Show all 17
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity