Cross Drive Dynamometer
Closed Solicitation Posted
- Solicitation number
- W91QVN-17-T-0008
- Agency
-
RCO Yongsan 411th CSB
Expeditionary Contracting Command, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W91QVN19C0003 Federal contract award
- Awardee
- Suntech Co., LTD.
- NAICS code
- 334519 Other Measuring and Controlling Device Manufacturing
- PSC
- Not on record
- Place of performance
- Delivery to Camp Carroll, South Korea, United States
Notice details come from SAM.gov. Updated .
Notice text
10 versions
Update #10 · Latest ·
Added: Apr 27, 2017 10:45 pm
Modified: Jul 24, 2017 2:41 amTrack Changes
AMENDMENT 0009
The Solicitation cited in Block 9a is amended to:
a) respond to questions received,
b) provide information on a second site visit as a result of the questions received,
c) extend the offer due date from 28 July 2017, 10:00am Korea Standard Time (KST) to 04 August 2017, 10:00am KST.
Amendment 0008 is also uploaded.
******
AMENDMENT 0008
The Solicitation cited in Block 9a is amended to extend the offer deadline from 21 July 2017, 10:00 am Korea Standard Time (KST) to 28 July 2017, 10:00 am KST.
******
AMENDMENT 0007
The Solicitation cited in Block 9a is amended to respond to additional questions. The offer due date is not extended. See attached.
*****
AMENDMENT 0006
The Solicitation cited in Block 9a is amended to extend the offer due date from 07 July 2017, 10:00am Korea Standard Time (KST) to 21 July 2017, 10:00am KST.
(Also re-uploading Amendment 0006)
*****
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #9 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jul 20, 2017 7:58 pmTrack Changes
AMENDMENT 0008
The Solicitation cited in Block 9a is amended to extend the offer deadline from 21 July 2017, 10:00 am Korea Standard Time (KST) to 28 July 2017, 10:00 am KST.
******
AMENDMENT 0007
The Solicitation cited in Block 9a is amended to respond to additional questions. The offer due date is not extended. See attached.
*****
AMENDMENT 0006
The Solicitation cited in Block 9a is amended to extend the offer due date from 07 July 2017, 10:00am Korea Standard Time (KST) to 21 July 2017, 10:00am KST.
(Also re-uploading Amendment 0006)
*****
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #8 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jul 14, 2017 2:45 amTrack Changes
AMENDMENT 0007
The Solicitation cited in Block 9a is amended to respond to additional questions. The offer due date is not extended. See attached.
*****
AMENDMENT 0006
The Solicitation cited in Block 9a is amended to extend the offer due date from 07 July 2017, 10:00am Korea Standard Time (KST) to 21 July 2017, 10:00am KST.
(Also re-uploading Amendment 0006)
*****
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #7 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jul 07, 2017 5:07 amTrack Changes
AMENDMENT 0006
The Solicitation cited in Block 9a is amended to extend the offer due date from 07 July 2017, 10:00am Korea Standard Time (KST) to 21 July 2017, 10:00am KST.
(Also re-uploading Amendment 0006)
*****
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #6 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jul 06, 2017 2:10 amTrack Changes
AMENDMENT 0006
The Solicitation cited in Block 9a is amended to extend the offer due date from 07 July 2017, 10:00am Korea Standard Time (KST) to 21 June 2017, 10:00am KST.
*****
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #5 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jun 30, 2017 1:21 amTrack Changes
AMENDMENT 0005
The Solicitation cited in Block 9a is amended to correct the offer due date to 07 July 2017, 10:00am to 30 June 2017, 10:00am as stated in Amendment 0003.
*****
AMENDMENT 0004
The Solicitation cited in Block 9a is amended to respond to an additional question. The offer response date is not extended.
*****
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #4 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jun 28, 2017 2:49 amTrack Changes
AMENDMENT 0003
The Solicitation cited in Block 9a is amended to:
a) Provide responses to questions submitted timely to the Government
b) Update the Statement of Work (SOW), Acceptance Test Standard, Minimum Salient Characteristics, and Shipping Instructions as a result of Q&A
c) Include Room Diagram and List of 411th CSB M IDIQ contractors as a result of Q&A
d) Extend the offer response date from 30 June 2017, 10:00am to 07 July 2017, 10:00am.
See attached Amendment.
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #3 ·
Added: Apr 27, 2017 10:45 pm
Modified: Jun 07, 2017 3:34 amTrack Changes
*****
AMENDMENT 0002
The Solicitation cited in Block 9a is amended to extend the offer deadline from 09 June 2017, 10:00 am Korea Standard Time (KST) to 30 June 2017, 10:00 am KST.
The responses to the questions submitted will be posted in a subsequent Amendment.
*****
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #2 ·
Added: Apr 27, 2017 10:45 pm
Modified: May 17, 2017 3:16 amTrack Changes
***
AMENDMENT 0001
The Solicitation cited in Block 9a is amended to extend the offer deadline from 19 May 2017, 10:00 am Korea Standard Time to 09 June 2017, 10:00 am Korea Standard Time.
The responses to the questions submitted will be posted in a subsequent amendment on or around 31 May 2017.
******
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.
Update #1 ·
Added: Apr 27, 2017 10:45 pm
One (1) Cross Drive Dynamometer with Installation, Training, and annual Maintenance/Calibration. See attached Solicitation (W91QVN-17-T-0008) and attachments.
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program. The vendor must be a Republic of Korea (ROK) owned company per the definition of a "Korean Contractor" in the solicitation. The prohibition of using off-shore manufacturers is waived for this requirement.
Site Visit scheduled for May 10, 2017, 10:00am, Korea Standard Time.
Offer due date is May 19, 2017, 10:00am, Korea Standard Time.