About this opportunity
This solicitation seeks offers to repair approximately 5.49 miles of Beasore Road located on the Sierra National Forest in California. Work will be performed for the United States Department of Agriculture Forest Service and includes cleaning and reconditioning culverts, replacing 600 linear feet of culvert pipe, installing metal end sections and a spillway, performing 6 inches of full depth reclamation from mile post 24.14 to 29.63 which may include installing geogrid, grading, placing base rock and riprap, paving with 4 inches of asphalt, and painting double centerlines. Offers are due by June 16, 2023 at 4:00 pm PDT and must be submitted via email to Catherine Whitted, the contracting officer.
The opportunity is set aside for total small business concerns. The primary NAICS code is 237110 for water and sewer line and related structures construction, and the PSC code covers highway and street construction. The estimated value of construction is between $5-10 million to be awarded by the Department of Agriculture Forest Service. Offerors must plan deliveries using Beasore Road and an alternate access route as Norris Creek Bridge is closed. The place of performance is Oakhurst, California, encompassing approximately 33.5 miles of Beasore Road on the Sierra National Forest.
Notice text
The project consists of repairing 5.49 miles of Beasore Road on the Sierra National Forest, California. Work shall include but is not limited to cleaning and reconditioning the culverts along the road, replacing 600 linear feet of 36” corrugated metal pipe, installing metal end sections, and installing a metal spillway. Work will also include the 6 inches full depth reclamation from mile post 24.14 to 29.63, installing a geogrid Tensar TriAx TX7 or equivalent (Optional item), grading & compacting the pulverized material, importing & placing base rock to correct lower areas, placing rip rap on outlets and ditches, placing a 4” layer of hot mix asphalt and painting two coats of a double yellow center line.
Currently Norris Creek Bridge is closed, contractors shall plan to deliver supplies and materials using Beasore road to complete the work west from Norris Creek bridge and use Minarets Road and for the remain work east from Norris Creek Bridge. There is an alternative detour route but only for high clearance vehicles and pickup trucks.
The project location is from Oakhurst, CA (93644), travel 3.2 miles North on highway 41, turn right onto Road 222/Bass Lake Road, continue South for approximately 2.4 miles, slight left onto Beasore Road, continue for approximately 33.5 miles until reach the beginning of the project (37.504292, -119.370184).
The magnitude of construction for this project is between $5,000,000.00 and $10,000,000.00.
Offers should be emailed to Catherine Whitted at catherine.whitted@usda.gov by June 16, 2023 at 4:00 pm PDT.
Attachments
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| Creek Fire Beasore Road Repairs | Solicitation | |
| Creek Fire Beasore Road Repairs | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity