BITTERROOT NATIONAL FOREST - Little Rock Creek Trail Bridge Replacement
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 1240LU24Q0059
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Montana, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Department of Agriculture Forest Service is seeking offers for the removal of an existing 35-ft single log foot bridge and the installation of a new 41-ft glulam stringer pack/pedestrian trail bridge over Little Rock Creek on Forest Service Trail #580 in the Bitterroot National Forest, Montana. The project includes associated trail approach work, footings, and drainage improvements. The contract period of performance is 60 days, with work anticipated to be completed between September 15, 2025 and November 14, 2025. The estimated magnitude of construction is between $100,000 and $250,000. The solicitation will be awarded based on the offeror's past performance and experience.
This opportunity is set aside for small businesses. The project is located approximately 3 miles west of the Lake Como Recreation Area, with no vehicular access to the bridge site. Helicopter flights and mechanized/motorized use are allowed at the site. Offers are due by September 3, 2024, and the contract will be awarded to the best value offeror.
Notice text
3 versions
Update #3 · Latest ·
PROJECT DESCRIPTION: The project is for the removal of an existing 35-ft single log
foot bridge over Little Rock Creek on Forest Service Trail #580 at milepost 2.87, and
installing a new 41-ft glulam stringer pack/pedestrian trail bridge with rock-filled
gabion basket foundation.
This project includes:
1) Dispose of an existing approximate 35-ft long single log foot bridge,
2) Construction of a new 41-ft, glulam stringer bridge, including associated trail
approach work, footings, and drainage improvements.
PROJECT LOCATION: This project is located at milepost 2.87 over Little Rock Creek on
Forest Trail # 580 on the Darby Ranger District, USFS, in Ravalli County, MT, Section 35,
Township 4 North, Range 22 West. The project is approximately 3 miles west of the
Lake Como Recreation Area, which is located approximately 8 miles northwest of
Darby, MT.
This project is located three miles from the closest road. Helicopter flights and
mechanized/motorized use is allowed at the site. There is no vehicular access to the
bridge site.
PERIOD OF PERFORMANCE: It is anticipated that work can begin September 15, 2025
with work being completed by November 14, 2025. Contract period of performance is
60 days.
MAGNITUDE OF CONSTRUCTION (per FAR 36.204(b)): Between $100,000 and $250,000.
AMENDMENT 001 - Updated Attachment J-2 Standard Glulam Stringer Trail Bridge Drawings
Question and Answers as of 8/23/2024
Updated Questions and Answers as of 8/27/2024
Update #2 ·
PROJECT DESCRIPTION: The project is for the removal of an existing 35-ft single log
foot bridge over Little Rock Creek on Forest Service Trail #580 at milepost 2.87, and
installing a new 41-ft glulam stringer pack/pedestrian trail bridge with rock-filled
gabion basket foundation.
This project includes:
1) Dispose of an existing approximate 35-ft long single log foot bridge,
2) Construction of a new 41-ft, glulam stringer bridge, including associated trail
approach work, footings, and drainage improvements.
PROJECT LOCATION: This project is located at milepost 2.87 over Little Rock Creek on
Forest Trail # 580 on the Darby Ranger District, USFS, in Ravalli County, MT, Section 35,
Township 4 North, Range 22 West. The project is approximately 3 miles west of the
Lake Como Recreation Area, which is located approximately 8 miles northwest of
Darby, MT.
This project is located three miles from the closest road. Helicopter flights and
mechanized/motorized use is allowed at the site. There is no vehicular access to the
bridge site.
PERIOD OF PERFORMANCE: It is anticipated that work can begin September 15, 2025
with work being completed by November 14, 2025. Contract period of performance is
60 days.
MAGNITUDE OF CONSTRUCTION (per FAR 36.204(b)): Between $100,000 and $250,000.
AMENDMENT 001 - Updated Attachment J-2 Standard Glulam Stringer Trail Bridge Drawings
Question and Answers as of 8/23/2024
Update #1 ·
PROJECT DESCRIPTION: The project is for the removal of an existing 35-ft single log
foot bridge over Little Rock Creek on Forest Service Trail #580 at milepost 2.87, and
installing a new 41-ft glulam stringer pack/pedestrian trail bridge with rock-filled
gabion basket foundation.
This project includes:
1) Dispose of an existing approximate 35-ft long single log foot bridge,
2) Construction of a new 41-ft, glulam stringer bridge, including associated trail
approach work, footings, and drainage improvements.
PROJECT LOCATION: This project is located at milepost 2.87 over Little Rock Creek on
Forest Trail # 580 on the Darby Ranger District, USFS, in Ravalli County, MT, Section 35,
Township 4 North, Range 22 West. The project is approximately 3 miles west of the
Lake Como Recreation Area, which is located approximately 8 miles northwest of
Darby, MT.
This project is located three miles from the closest road. Helicopter flights and
mechanized/motorized use is allowed at the site. There is no vehicular access to the
bridge site.
PERIOD OF PERFORMANCE: It is anticipated that work can begin September 15, 2025
with work being completed by November 14, 2025. Contract period of performance is
60 days.
MAGNITUDE OF CONSTRUCTION (per FAR 36.204(b)): Between $100,000 and $250,000.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| BITTERROOT NATIONAL FOREST - Little Rock Creek Trail Bridge Replacement | Award Notice | |
| This notice | Solicitation | |
| BITTERROOT NATIONAL FOREST - Little Rock Creek Trail Bridge Replacement | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Purchase of 2 or 3 Temporary Road Bridges | Forest Service | No set-aside | |
| GRSM 321788 - Oconaluftee River Trail | — | No set-aside | |
| ID FLAP KOOTEN 8450(1), Yellowstone Trail Road, Segment 1 | Federal Highway Administration | No set-aside | |
| YELL 338223 - Bridge Preservation | National Office | No set-aside | |
| Big Springs Horse Corral Replacement | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity