AZ FLAP234(3), Lake Mary Road

Award Notice Posted

Solicitation number
AZ-FLAP-234(3)
Agency
Awarded
to Stormwater Plans, LLC
Set-aside
No set-aside

Opportunity facts

Contract number
DTFH6817C00016 Federal contract award
PSC
Not on record
Place of performance
Coconino County, Arizona 86004, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·


The project includes one schedule that consists of 4R improvement of portions of Forest Highway 3, also known as Lake Mary Road in Coconino County Arizona.  The project is also within the Coconino National Forest.  The project consists of minor shoulder widening, pulverizing of pavement, new pavement 4R work includes removal of Willow Creek Bridge deck and replacing with a widened bridge deck on existing substructure.  The project includes new guardrail approaches, final signing and striping. There are minor culvert pipe extensions with the shoulder widening and one large box culvert replacement.


Significant quantities for Schedule A include:



  • Total of 15,000 CY of Embankment
  • 139,000 SY of Full Depth Reclamation, Method 2, 8 inch depth
  • 145,000 SY of Prime Coat Method 1
  • 102,000 LB of Reinforcing Steel
  • 33,000 LB of Reinforcing Steel Epoxy
  • 102,300 LB of Structural Steel Furnished, Fabricated and Erected
  • 120,000 LF of Rumble Strip
  • 8,000 CY of Conserved Topsoil
  • 15,000 Tons of Roadway Aggregate Method 2
  • 30,000 Tons of Asphalt Concrete Pavement
  • 252 CY of Structural Concrete
  • 85 LF of Reinforced 12 foot x 9 foot Precast Reinforced Box Culvert

  • 201 LF of Guardrail System G4

    The contracting range for this project is $8 to $12 million.



 


Update #1 ·

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.  THE TENTATIVE ADVERTISEMENT IS LATE FEBRUARY, 2017.  THIS PROJECT WILL BE ADVERTISED ON A FULL AND OPEN BASIS. 


The project includes one schedule that consists of 4R improvement of portions of Forest Highway 3, also known as Lake Mary Road in Coconino County Arizona.  The project is also within the Coconino National Forest.  The project consists of minor shoulder widening, pulverizing of pavement, new pavement 4R work includes removal of Willow Creek Bridge deck and replacing with a widened bridge deck on existing substructure.  The project includes new guardrail approaches, final signing and striping. There are minor culvert pipe extensions with the shoulder widening and one large box culvert replacement.


Significant quantities for Schedule A include:



  • Total of 15,000 CY of Embankment
  • 139,000 SY of Full Depth Reclamation, Method 2, 8 inch depth
  • 145,000 SY of Prime Coat Method 1
  • 102,000 LB of Reinforcing Steel
  • 33,000 LB of Reinforcing Steel Epoxy
  • 102,300 LB of Structural Steel Furnished, Fabricated and Erected
  • 120,000 LF of Rumble Strip
  • 8,000 CY of Conserved Topsoil
  • 15,000 Tons of Roadway Aggregate Method 2
  • 30,000 Tons of Asphalt Concrete Pavement
  • 252 CY of Structural Concrete
  • 85 LF of Reinforced 12 foot x 9 foot Precast Reinforced Box Culvert

  • 201 LF of Guardrail System G4

    The contracting range for this project is $8 to $12 million.



 


Files

File Type Posted
HUBZone_Price_Evaluation.pdf PDF
Bid_Opening_Summary_-_AZ_FLAP_234(3,_Lake_Mary_Road.pdf PDF
QA.docx DOCX document
sample_subcontracting_plan.doc DOC document
Plans.pdf PDF
AZ_FLAP_234(1)_Lake_Mary_SWPPP.pdf PDF
AZ.FLAP.234(3).Lake_Mary_Road.Geotech.2016.Rev1.zip ZIP file
DTFH6817B00003.pdf PDF
Cross_Sections.pdf PDF

Notice history

Notice Type Posted
This notice Latest Award Notice
AZ FLAP 234(3), Lake Mary Road Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity