HUBZone_Price_Evaluation.pdf
PDF 6 KB Posted
- Attached to
- AZ FLAP234(3), Lake Mary Road
- Solicitation number
- AZ-FLAP-234(3)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Summary_-_AZ_FLAP_234(3,_Lake_Mary_Road.pdf | ||
| QA.docx | DOCX document | |
| Plans.pdf | ||
| AZ.FLAP.234(3).Lake_Mary_Road.Geotech.2016.Rev1.zip | ZIP file | |
| AZ_FLAP_234(1)_Lake_Mary_SWPPP.pdf | ||
| Cross_Sections.pdf | ||
| sample_subcontracting_plan.doc | DOC document | |
| DTFH6817B00003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HUBZone Price Evaluation (preliminary)
AZ FLAP 234(3), Lake Mary Road 3/29/2017 Bid Amount
Contractor Schedule A 10% factor Adjusted Bid Amount F&F Construction (LBC) $7,825,288.00 $782,528.80 $8,607,816.80 Intermountain West Civil Constructors (HUBZone) $9,834,920.10 $9,834,920.10 LB Civil Construction (HUBZone) $9,309,015.00 $9,309,015.00 Fann Construction (LBC) $7,844,500.00 $784,450.00 $8,628,950.00 Stormwater Plans (HUBZone) $8,197,716.50 $8,197,716.50
Engineers Estimate $9,300,721.00 $9,300,721.00