AZ_FLAP_234(1)_Lake_Mary_SWPPP.pdf
PDF 417 KB Posted
- Attached to
- AZ FLAP234(3), Lake Mary Road
- Solicitation number
- AZ-FLAP-234(3)
About this file
SWPPP
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HUBZone_Price_Evaluation.pdf | ||
| Bid_Opening_Summary_-_AZ_FLAP_234(3,_Lake_Mary_Road.pdf | ||
| QA.docx | DOCX document | |
| Plans.pdf | ||
| AZ.FLAP.234(3).Lake_Mary_Road.Geotech.2016.Rev1.zip | ZIP file | |
| Cross_Sections.pdf | ||
| sample_subcontracting_plan.doc | DOC document | |
| DTFH6817B00003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stormwater Pollution Prevention Plan (SWPPP)
AZ FLAP 234(3) – LAKE MARY ROAD,
WILLOW VALLEY CREEK BRIDGE
August 2016
For Construction Activities At:
AZ FLAP 234(3) – Lake Mary Road, Willow Valley Creek Bridge Coconino National Forest
Coconino County, Arizona
SWPPP Prepared For:
Federal Highway Administration Central Federal Lands Highway Division
Edward Martinez 12300 W. Dakota Avenue, Lakewood, CO 80228 720.963.3731
Edward.Martinez@dot.gov
SWPPP Prepared By:
Federal Highway Administration Central Federal Lands Highway Division
Opal Forbes 12300 W. Dakota Avenue, Lakewood, CO 80228 720.963.3431
Opal.Forbes@dot.gov
SWPPP Preparation Date:
08/2016
Estimated Project Dates:
Project Start Date: 04/03/2017 Project Completion Date: 10/20/2017
WILLOW VALLEY CREEK BRIDGE
i
This page intentionally left blank.
WILLOW VALLEY CREEK BRIDGE
August 2016 ii
Contents SECTION 1 Project/Site Information
1.2 Contact Information/ Responsible Parties
1.3 Nature and Sequence of Construction Activity
1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns
1.5 Construction Site Estimates
SECTION 2 Site Features and Sensitive Areas to be Protected
2.1 Receiving Waters
2.2 Endangered Species Certification
2.3 Historic Preservation
SECTION 3 Potential Sources of Pollution (ADEQ CGP 6.3.9)
3.1 Spill Prevention and Control Plan(ADEQ CGP 6.3.11)
3.2 Allowable Non-Stormwater Discharge Management (ADEQ CGP 1.3.2) SECTION 4: Erosion and Sediment Control
4.1 Phase Construction Activity
4.2 Structural Practices for Erosion and Sediment Control
4.4 Good Housekeeping BMPs (ADEQ CGP 3.1.3.3)
4.5 Post Construction BMPs
SECTION 5: Inspection and Corrective Action (ADEQ CGP 4.0, 5.0)
5.1 Inspections
SECTION 6: Recordkeeping and Training (ADEQ CGP 6.4)
6.1 Recordkeeping
6.2 SWPPP Updates and Modification Requirements (ADEQ CGP 6.5)
6.3 Training (ADEQ CGP 6.3.1)
6.4 Delegation of Authority
SECTION 7: Final Stabilization (ADEQ CGP 3.1.2.2) SECTION 8: Certification
SWPPP APPENDICES
List of Appendices Appendix A – Figures
Appendix B – Photo Documentation
Appendix C – Construction General Permit
Appendix D – NOI and Acknowledgement Letter from EPA/State
Appendix E – Corrective Action Log
Appendix F – SWPPP Amendment Log
Appendix G – Inspection Reports
Appendix H – Subcontractor Certifications/Agreements
Appendix I – Grading and Stabilization Activities Log
Appendix J – Training Log
Appendix K – Delegation of Authority
Appendix L – NEPA CatEx Documentation
Appendix M – Soil Survey
WILLOW VALLEY CREEK BRIDGE
SECTION 1 Project/Site Information 1
Project/Site Name: AZ FLAP 234(3) – LAKE MARY ROAD
Project Street/Location: Forest Highway 3 (Lake Mary Road)
State: AZ
County: Coconino Latitude/Longitude (Use one of three possible formats, and specify method) Beginning of project: Latitude: 34.898653° N Longitude: -111.438453° W Ending of Project: Latitude: 34.823895º N Longitude: -111.436345° W Willow Valley Creek Bridge: Latitude: 34.636518º N Longitude: -111.360685° W
Method for determining latitude/longitude:
USGS topographic map (specify scale: ) EPA Web site GPS
Other (please specify): Google Earth
Is the project located in Indian country? Yes No
If yes, name of Reservation, or if not part of a Reservation, indicate "not applicable."
Not Applicable
Is this project considered a federal facility? Yes No
Does your project/site discharge stormwater into a Municipal Separate Storm Sewer System (MS4)? Yes No
Are there any surface waters that are located within 50 feet of your construction disturbances?
Yes No
AZDPES project or permit tracking number*:
*(This is the unique identifying number assigned to your project by your permitting authority after you have applied for coverage under the appropriate Arizona Pollutant Discharge Elimination System (NPDES) construction general permit.)
WILLOW VALLEY CREEK BRIDGE
August 2016
1.2 Contact Information/ Responsible Parties
Operator(s):
U.S. Department of Transportation Federal Highway Administration Central Federal Lands Highway Division 12300 W. Dakota Ave Lakewood, CO 80228 Micah Leadford, Project Manager
(720) 963-3498 Fax (720) 963-3596 Email: Micah.Leadford@dot.gov and
Contractor TBD
On-Site Project Manager(s) or Site Supervisor(s):
Insert Company or Organization Name: CONTRACTOR TBD Insert Name:
Insert Address:
Insert City, State, Zip Code:
Insert Telephone Number:
Insert Fax/Email:
Insert area of control (if more than one operator at site) :
Repeat as necessary
SWPPP Contact(s):
Contractor TBD
WILLOW VALLEY CREEK BRIDGE
August 2016
Subcontractor(s):
Insert Company or Organization Name: CONTRACTOR TBD Insert Name:
Insert Address:
Insert City, State, Zip Code:
Insert Telephone Number:
Insert Fax/Email:
Insert area of control (if more than one operator at site) :
Emergency 24-Hour Contact:
Insert Company or Organization Name: CONTRACTOR TBD Insert Name:
Insert Telephone Number:
This SWPPP was prepared by:
Opal Forbes U.S. Department of Transportation Federal Highway Administration Central Federal Lands Highway Division 12300 W. Dakota Ave Lakewood, CO 80228 720-963-3431 Email: Opal.Forbes@dot.gov
WILLOW VALLEY CREEK BRIDGE
August 2016
1.3 Nature and Sequence of Construction Activity
The Federal Highway Administration, Central Federal Lands Highway Division (FHWA- CFLHD), in cooperation with the Coconino National Forest (CNF) and Coconino County, is proposing improvements to Lake Mary Road (Forest Highway 3 / County Road 209) to address safety concerns and general roadway deficiencies (drainage, curve radii, sight distance etc.).
Lake Mary Road is located approximately 40 miles to the southeast of Flagstaff, Coconino County, Arizona. This road provides access to private and U.S. Forest Service (USFS)-managed lands between Interstate 17 to the north and State Route 87 to the south. This route accesses Lake Mary, Mormon Lake, residential cabins and homes, and the recreational lands of the Coconino National Forest (CNF). The proposed project includes three priority areas. In summary, Priority Area 1 includes the rehabilitation of the Willow Valley Creek Bridge, located at the approximate milepost (MP) 297.5, and Priority Areas 2 and 3 include the roadway improvements of approximately 13.5 miles of roadway between MP 310.0 and 323.5.
Construction will begin in April 2017 and will be completed by October 2017. Construction will be completed in the following sequence:
1. Establish temporary Best Management Practices (BMPs)
2. Removal of obstructions
3. Topsoil management
4. Roadway excavation and ditch excavation
5. Culvert and headwall installation
6. Slope protection and sediment wattle installation
7. Roadway pulverizing and aggregate base finishing
8. Concrete Curb and ditch installation
9. Paving and asphalt curb installation
10. Final ditch grading and aggregate shouldering
11. Guardrail installation
12. Temporary seeding and hydro-mulching
13. Sign installation and roadway stripping
14. Remove temporary BMPs
What is the function of the construction activity?
Residential Commercial Industrial Road Construction Linear Utility
Other (please specify):
Estimated Project Start Date: 04/03/2017
Estimated Project Completion Date: 10/20/2017
Comment [t1]: Contractor to specify sequence of construction activity.
WILLOW VALLEY CREEK BRIDGE
August 2016
1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns
Soil type(s):
The dominant soil orders in this MLRA are Borolls, Boralfs, Ustolls, Ustalfs, Ostalfs, Orthents, and Orthids. They have a cyric, frigid, or mesic temperature regime depending mainly on elevation. Argiborolls and Cryoborolls are formed at the higher elevations in intrusive and extrusive volcanic materials, dominantly basalt. At lower elevations, Eutroboralfs, Ustorthents, Haplustalfs, Argiustolls, Haplustolls, Calciorthids, and Glossoboralfs overlie on schist, sandstone, shale, limestone, and old alluvium.
According to the U.S. Department of Agriculture - Natural Resources Conservation Service’s (USDA-NRCS) online Web Soil Survey (http://websoilsurvey.nrcs.usda.gov/app/WebSoilSurvey.aspx), soils for the majority of the project area are not mapped. However, the portion of mapped soils are typical for the entire project area. Mapped soils within the project area are composed of Friana soils (Fn) (Fn), and Brolliar very stony loam, 0 to 10 percent slopes (BrB). The Friana soils are generally described as moderately well drained alluvium soils derived from basalt, cinders, and/or pyroclastic rock.
These soils have very low to moderately low permeability and high water capacity. The Brolliar very stony loam is generally described as well drained colluvium soils derived from basalt.
These soils have very low to low permeability and low water capacity.
Slopes:
Elevation varies from 7300 ft to 7500 ft above mean sea level along the project length on Lake Mary Road. Willow Creek Bridge is at an elevation of 6735ft above mean sea level. Slopes are along the project are gradual with roadside ditches present along part of the alignment.
Vegetation:
Vegetative cover within this region of the MLRA typically consists of alpine vegetation, conifer forests, chaparral, and grasses because of the broad elevation range. The understory includes Thurber fescue, brome, bluegrasses, mountain muhly, Arizona fescue, lupine, aspen peavine, penstemons, and daisies. The major part of the area is a vast ponderosa pine forest.
Current Drainage Patterns:
The project area lies within the Colorado and Mogollon Plateau region of Arizona. Well established drainage on the Colorado Plateau does not exist due to the nature of the rock formations. Therefore, precipitation sinks down through underground channels and caverns which again reach surface at lower elevations.
WILLOW VALLEY CREEK BRIDGE
August 2016
1.5 Construction Site Estimates
The following are estimates of the construction site.
Total project area: XXX acres
Construction site area to be disturbed : XXX acres
Percentage impervious area before construction: XX %
Runoff coefficient before construction: 0.XX
Percentage impervious area after construction: XX %
Runoff coefficient after construction 0.XX
This project is a rehabilitation of an existing roadway with only a portion of the roadway being widened. Therefore the runoff coefficient changed slightly.
WILLOW VALLEY CREEK BRIDGE
August 2016
SECTION 2 Site Features and Sensitive Areas to be Protected The negligible to minor adverse impacts to ephemeral washes will occur as a result of roadway improvements.
2.1 Receiving Waters
Several unnamed tributaries and tributary wetlands to Mormon Lake pass through the project area. In addition, the project crosses Willow Valley Creek, an intermittent watercourse.
Table 1 – Names of Receiving Waters Name(s) of the first surface water that receives stormwater directly from your site and/or from the MS4 (note: multiple rows provided where your site has more than one point of discharge that flows to different surface waters)
1. Unnamed Intermittent and Tributary wetlands to Mormon Lake
2. Willow Valley Creek
Description of storm sewer systems:
The project site does not discharge stormwater into a municipal separate storm sewer system.
Description of impaired waters or waters subject to TMDLs:
Neither Mormon Lake nor Willow Valley creek are impaired waters.
Table 2 – Impaired Waters / TMDLs (Answer the following for each surface water listed in Table 1 above)
Is this surface water listed as “impaired”?
If you answered yes, then answer the following:
What pollutant(s) are causing the impairment?
Has a TMDL been completed? Title of the TMDL document
1. YES NO YES NO
2. YES NO YES NO
2.2 Endangered Species Certification
Are endangered or threatened species and critical habitats on or near the project area?
Please refer to the NEPA CatEx Document located in Appendix L.
WILLOW VALLEY CREEK BRIDGE
August 2016
2.3 Historic Preservation
Are there any historic sites on or near the construction site?
Please refer to the NEPA CatEx Document located in Appendix L.
WILLOW VALLEY CREEK BRIDGE
August 2016
WILLOW VALLEY CREEK BRIDGE
August 2016
SECTION 3 Potential Sources of Pollution (ADEQ CGP 6.3.9) The principal pollutant of concern in storm water runoff is sediment. Other pollutants may be found in the storm water runoff, though they are usually in substantially smaller amounts.
Roadway construction areas t could become potential sources of both sediment and other pollutants.
The table listed below takes these construction areas into consideration and lists the potential pollutants.
Table 1: Construction Site Pollutants
Construction Site Pollutants
Areas of Consideration
Primary Pollutant
Other Pollutants
S ed im en t
N ut ri en ts
H ea vy m et al s pH ac id s b as es
P es tic id es a nd h er bi ci de s
O il, g re as e, f ue ls
B ac te ri a v ir us es
T ra sh , d eb ri s, s ol id s Grading and excavating Pulverizing and paving operations Concrete washout and waste Demolition and debris disposal Material delivery and storage Material use during construction Solid waste Contaminated Spills Equipment fueling, use, and storage
Sanitary waste
3.1 Spill Prevention and Control Plan(ADEQ CGP 6.3.11)
The on-site construction contractor shall develop a plan describing what actions will be taken in case of a spill and incorporate preventative measures to be implemented (such as the placement of refueling facilities, storage and handling of materials, etc.). This plan must be made at least 2 days before beginning work and contain the following.
Spills of Petroleum Products or Hazardous Materials: Procedures to properly clean up, mitigate, and remedy, if necessary, all spills of petroleum products, hazardous materials, or other
WILLOW VALLEY CREEK BRIDGE
August 2016 chemical or biological products released from construction, fleet, or other support vehicles, or stationary sources. Respond in accordance with federal, state, and local regulations.
Immediately report to the CO any spill of petroleum products or a hazardous material. Report the spill to the appropriate federal, state, and local authorities as required by the SPCC plan or hazardous spill plan.
Contractor to insert additional information on spill plan.
Water pollution The on-site construction contractor shall not operate mechanized equipment or discharge or otherwise place any material within the wetted perimeter of any waters of the U.S.
within the scope of the Clean Water Act (33 USC § 1251 et seq.). This includes wetlands unless authorized by a permit issued by the U.S. Army Corps of Engineers according to 33 USC § 1344, and, if required, by any State agency having jurisdiction over the discharge of material into the waters of the U.S. In the event of an unauthorized discharge:
(1) Immediately prevent further contamination;
(2) Immediately notify appropriate authorities; and
(3) Mitigate damages as required.
Comply with the terms and conditions of any permits that are issued for the performance of work within the wetted perimeter of the waters of the U.S.
Separate work areas, including material sources, shall use a dike or other suitable barrier to prevent sediment, petroleum products, chemicals, or other liquid or solid material from entering the waters of the U.S. Use care in constructing and removing the barriers to avoid any discharge of material into, or the siltation of, the water. Remove and properly dispose of the sediment or other material collected by the barrier.
Vehicles and equipment All vehicles and equipment entering the project area must be clean of noxious weeds and free from oil leaks and are subject to inspection. Wash all construction equipment to thoroughly remove all dirt, plant, and other foreign material prior to entering the project. Particular attention must be shown to the under carriage and any surface where soil containing exotic seeds may exist. These efforts are critical to prevent the introduction and establishment of non-native plant species into the project area. Make arrangements for the CO to inspect each piece of equipment before entering the project. The CO will maintain records of inspections. Equipment found operating on the project that has not been inspected, or has oil leaks will be shut down and subject to citation.
In general, when gasoline, diesel fuel, antifreeze, hydraulic fluid or any other chemical contained within the vehicle is released to the pavement or ground, proper corrective, clean-up, and safety actions must be immediately implemented. All vehicles with load rating of 2 tons or greater should carry, at minimum, enough absorbent materials to effectively immobilize the total volume of fluids contained within the vehicle.
WILLOW VALLEY CREEK BRIDGE
August 2016
Repair oil leaks immediately on discovery. Do not use equipment that is leaking. Have oil pans and absorbent material in place prior to beginning repair work. Have the “on scene” capability of catching and absorbing leaks or spillages of petroleum products including antifreeze from breakdowns or repair actions with approved absorbent materials. Keep a supply of acceptable absorbent materials at the job site in the event of spills. Sand and/or soil are not approved absorbent materials.
Use oil pans and absorbent materials to prevent leaks, spills and draining petroleum fluids from falling onto bare ground and paved surfaces during servicing of equipment. Dig up soils contaminated with such fluids, place in appropriate safety containers, and dispose of according to state and/or federal regulations.
Clearances for Contractor-selected, noncommercial areas Noncommercial areas include material sources, disposal sites, waste areas, haul roads, and staging areas located outside project construction limits and permitted commercial areas. Permitted commercial areas are enterprises or developed areas providing same-type material or use over the last 2 years with appropriate permits.
Before using a Contractor-selected, noncommercial areas, submit the following:
Locate machinery servicing and refueling areas away from streambeds and washes to reduce the possibility and minimize the impacts of accidental spills or discharges.
Where the Contractor’s working area encroaches on a running or intermittent stream, construct and maintain adequate barriers to prevent the discharge of any contaminants into the stream.
Fording of running streams with construction equipment will not be permitted. Obtain approval from the CO to use temporary bridges or other structures whenever crossings are necessary.
Immediately clear ephemeral drainages, intermittent and perennial streams, lakes and reservoirs of all work items, debris or other obstructions resulting from construction operations.
WILLOW VALLEY CREEK BRIDGE
August 2016
Spill Prevention and Control Procedures BMP Description: A spill kit (i.e. fueling spill control blanket) will be provided for use during mobile refueling. Staff will be trained in the proper usage of the spill kit. Contractor will follow comprehensive handling and management procedures to prevent hazardous liquids from migrating across the site and to avoid groundwater contamination. Containment measures (e.g., drip pans, drip cloths, or absorbent pads) will be used when replacing spent fluids.
Contractor will train employees in proper equipment handling and refueling procedures.
Installation Schedule: Refueling and maintenance procedures to be established prior to construction.
Maintenance and Inspection:
Areas where refueling/maintenance occur will be inspected daily for signs of storm water pollutant exposure. Inspect equipment for leaks of oil, fuels, or hydraulic fluids before and during use. Maintenance and inspections will be documented in corrective action will be documented in Appendix E (Corrective Action Log) and Appendix G (Inspection Reports) of the
SWPPP.
Responsible Staff: Field Contractor
3.2 Allowable Non-Stormwater Discharge Management (ADEQ CGP
1.3.2)
The following are the only non-stormwater discharges allowed under ADEQ CGP. These discharges are allowed provided they are reduced or eliminated to the extent practicable. When allowable non-stormwater discharges cannot be practicably eliminated, the operator shall install appropriate control measures to reduce or eliminate pollutants in the discharge to assure compliance with Part 3 of the ADEQ CGP.
i. Discharges from emergency fire-fighting activities;
ii. Water used to control dust, provided reclaimed water or other process wastewaters are not used;
iii. Routine external building wash down where detergents are not used;
iv. Water used to rinse vehicles and equipment, provided that reclaimed water or other wastewater is not used and no soaps, solvents, detergents, oils, grease or fuels are present in the rinsate;
v. Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used;
vi. Uncontaminated air conditioning or compressor condensate;
vii. Uncontaminated groundwater or spring water;
viii. Foundation or footing drains where flows are not contaminated with process materials such as solvents;
WILLOW VALLEY CREEK BRIDGE
August 2016
ix. Water from fire fighting system testing and maintenance, including hydrant flushings;
x. Discharges related to installation and maintenance of potable water supply systems, including disinfection and flushing activities, discharges resulting from pressure releases or overflows, and discharges from wells approved by ADEQ for drinking water use;
xi. Hydrostatic testing of new pipes, tanks or vessels using potable water, surface water, or uncontaminated groundwater;
xii. Water used for compacting soil, provided reclaimed water or other wastewaters are not used;
xiii. Water used for drilling and coring such as for evaluation of foundation materials, where flows are not contaminated with additives; and
xiv. Uncontaminated waters obtained from dewatering operations/ foundations in preparation for and during excavation and construction provided the discharge are managed as specified in Part 3.1.4 of the ADEQ CGP.
Note: The ADEQ CGP does not prohibit the use of reclaimed or other process wastewaters on-site for dust control, soil compaction or for landscape irrigation. However, such activities shall be managed in a way that they are not discharged off site or applied during rain events.
Any changes in construction activities that produce other allowable non-stormwater discharges will be identified, the SWPPP will be amended, and the appropriate erosion and sediment controls will be implemented.
Water Used to Control Dust
BMP Description: Dust control will be implemented, as needed, once site grading has been initiated and during windy conditions while site grading is occurring. Dust control will continue on-site during construction activities, as needed.
Responsible Staff: Field Contractor
Uncontaminated Excavation Dewatering
BMP Description: Because construction for this site is being conducted during the dry season, dewatering activities are not expected to occur at the project site. If dewatering does occur, the SWPPP will be revised to address the need for appropriate BMPs.
Responsible Staff: Field Contractor
WILLOW VALLEY CREEK BRIDGE
August 2016
WILLOW VALLEY CREEK BRIDGE
August 2016
SECTION 4: Erosion and Sediment Control Contractor shall not disturb existing vegetation outside project limits and shall minimize the impacts to existing vegetation and side slopes within construction limits. Temporary and/or permanent seeding within the construction right of way shall be accomplished using a seed mix determined by the Coconino Forest Service. Supplemental seeding may be performed by the Forest Service upon completion of construction. Existing topsoil not be removed from site.
Specific locations for salvaging topsoil shall be identified during construction phases and located on the site plan. Only certified weed free erosion control devices will be used.
Stormwater flow shall be controlled by the existing, as the project progresses, replaced culverts.
Erosion control will consist of implementing the use of perimeter controls and sediment barriers including silt fence and check dams as shown on the plan set. During construction, temporary inlet and outlet protection shall as needed within the area of disturbance. Wind erosion control shall consist of application of water and/or application of city, state and federally approved chemical dust suppressants to exposed surfaces that cause a dust nuisance. Construction entrances will be stabilized (i.e. track out protection and wash down) through the duration of the project. The contractor shall minimize the amount of soil exposed during construction activities and subject to the deadlines for temporarily and/or permanently stabilizing portions of the site.
Initiate work to fix problem immediately after discovery, and complete such work by the close of the next work day, if feasible and the problem does not require significant maintenance, repair or replacement.
The contractor shall complete the installation of control measures by the time each phase of earth-disturbance has begun. Where practicable, implement standard erosion and sediment control practices to these areas and using stabilization practices designed to be used on steep grades. In the event it is infeasible to install one or more control measures prior to construction activity, the operator shall ensure that those controls are installed as soon as possible. SWPPP records must document why it is infeasible.
The contractor shall control discharges from stockpiles of sediment or soil. Stockpiles shall be place outside of washes or other surface waters, or stormwater conveyances, such as curb and gutter systems, or streets leading to such conveyances. Stockpiles shall be protect from contact with stormwater (including run-on) using a temporary perimeter sediment barrier. Silt fences or other effective sediment control measures shall be used around soil stockpiles except when they are being actively worked.
The contractor shall protect culverts present on the site by include measures to sufficiently minimize the threat of erosion at culvert locations and prevent the formation of rills and gullies during construction. The contractor shall place velocity dissipation devices along the length of any on-site outfall channel where discharges leaving the construction site cause rill erosion to maintain a non-erosive flow velocity.
Note: Inlet protection measures can be removed in the event of flood conditions that may endanger the safety of the public. Such actions are allowable only under extreme
WILLOW VALLEY CREEK BRIDGE
August 2016 conditions and shall be documented on the SWPPP. The contractor shall evaluate alternatives to be used in the future to prevent a recurrence of this problem.
If existing control measures need to be repaired or modified or if additional control measures are necessary, implementation shall be completed within 7 calendar days or before the next storm event (whichever is sooner). If implementation before the next storm event is impracticable, the reason(s) for delay shall be documented in the SWPPP and alternative control measures shall be implemented as soon as possible. Accumulations of sediment, debris, and other pollutants observed in off-site surface waters, drainage ways, catch basins, and other drainage features shall be removed in a manner and at a frequency sufficient to minimize impacts and to ensure no adverse effects on water quality. The following maintenance activities shall be implemented as follows:
Remove accumulated sediment when it reaches a maximum of one-third the height of the silt fence or one-half the height of a fiber roll.
Sediment shall be removed from temporary and permanent sedimentation basins, ponds and traps when the depth of sediment collected in the basin reaches 50% of the storage capacity.
Construction site egress location(s) shall be inspected for evidence of off-site tracking of sediment, debris, and other pollutants onto paved surfaces. Removal of sediment, debris, and other pollutants from all off-site paved areas shall be completed as soon as practicable.
4.1 Phase Construction Activity
The Federal Highway Administration (FHWA), Central Federal Lands Highway Division (CFLHD), in cooperation with the U.S. Forest Service (USFS), is proposing to rehabilitate, reconstruct, and resurface Lake Mary Road and the Willow Valley Creek Bridge in Coconino National Forest, Coconino County, Arizona. The proposed project would include roadway improvements of approximately 13.5 miles of roadway between milepost (MP) 310.0 and 323.5 as well as the bridge located approximately at MP 297.5. The project would involve roadway geometry improvements, roadway pavement improvements, roadway safety improvements, culvert replacements, and bridge replacement.
Construction will begin in April 2017 and will be completed by October 2017. Construction will be completed in the following sequence:
1. Contractor to outline sequence of activities
4.2 Structural Practices for Erosion and Sediment Control
The following list applicable BMPs that may be used for this project. Several of these BMPs have been called out on the site plan in Appendix A. When additional BMPs are added or modified, the site plan shall be updated by indicating the location of BMP, signed and date as to when it was installed and/or removed by marking up the plan set by hand. If the site plan
WILLOW VALLEY CREEK BRIDGE
August 2016 becomes hard to read, additional phases of the plan set can be attached to indicate the different phases of the plan.
All temporary BMPs shall be removed and stabilized prior to submitting the Notice of Termination with ADEQ.
4.2.1 Natural Buffers or Equivalent Sediment Controls (CPG-2013 3.1.1.5, 6.3(5)e, 6.4(10))
Buffer Compliance Alternatives Are there any surface waters within 50 feet of your project’s earth disturbances? YES NO
Check the compliance alternative that you have chosen:
I will provide and maintain a 50-foot undisturbed natural buffer.
I will provide and maintain an undisturbed natural buffer that is less than 50 feet and is supplemented by additional erosion and sediment controls, which in combination achieves the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
It is infeasible to provide and maintain an undisturbed natural buffer of any size, therefore I will implement erosion and sediment controls that achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
I qualify for one of the exceptions in Part 2.1.2.1.e. (If you have checked this box, provide information on the applicable buffer exception that applies, below.)
Buffer Exceptions Which of the following exceptions to the buffer requirements applies to your site?
There is no discharge of stormwater to the surface water that is located 50 feet from my construction disturbances.
No natural buffer exists due to preexisting development disturbances that occurred prior to the initiation of planning for this project.
No buffer exists due to previous road construction disturbance For a “linear project” (defined in Appendix A), site constraints (e.g., limited right-of-way) make it infeasible for me to meet any of the CGP Part 2.1.2.1.a compliance alternatives.
All areas within 50 feet will have at least one sediment control device between the construction and the surface water if stormwater can flow from the construction area into a jurisdictional water.
The project qualifies as “small residential lot” construction (defined in Part 2.1.2.1.e.iv and in Appendix A).
Buffer disturbances are authorized under a CWA Section 404 permit.
This project meets the requirements of Section 404 NWP-14 (Linear Transportation). A copy of the 404 permit requirements is included in the appendices.
Buffer disturbances will occur for the construction of a water-dependent structure or water access area (e.g., pier, boat ramp, and trail).
WILLOW VALLEY CREEK BRIDGE
August 2016
4.2.2 Perimeter Controls
General
Perimeter controls will be placed prior to earth disturbance to prevent sediment from leaving the job site. Additional silt fence may be installed down gradient of a disturbance where sediment is anticipated to leave the job site.
Specific Perimeter Controls (ADEQ CGP 3.1.1.4.1)
Perimeter Control # 1 Silt Fence
Silt fence will be installed prior to beginning earth disturbances along the project on the down gradient side where water leaves the project.
Specifications and standard detail drawings are included in the contract documents.
Installation Perimeter controls will be installed prior to earth disturbances on the project.
Maintenance Requirements Sediment will be removed before it has accumulated to one-half of the above-ground height of any perimeter control.
4.2.3 Sediment Track-Out (ADEQ CGP 3.1.3.2, 6.3(8)d)
General
Where sediment has been tracked-out from the site onto the surface of off-site streets, other paved areas, and sidewalks, remove the deposited sediment by the end of the same work day in which the track-out occurs or by the end of the next work day if track-out occurs on a non-work day. Remove the track-out by sweeping, shoveling, or vacuuming these surfaces, or by using other similarly effective means of sediment removal. You are prohibited from hosing or sweeping tracked-out sediment into any stormwater conveyance (unless it is connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water.
4.2.4 Stockpiled Sediment or Soil (ADEQ CGP 3.1.1.4)
General
Stockpiles of material will be limited at the site, but may occur occasionally while specific operations are taking place. Potential earthen materials that may be stockpiled for short periods of time include riprap and structural backfill materials. Sediment controls will be placed around stockpiles that may release sediment in a storm event.
The type of sediment control device used will depend on the location of the stockpile (on paved or unpaved surfaces). The contractor may choose the type of control that best fits the conditions of the project.
Specific Stockpile Controls
Stockpile Control # 1 Perimeter controls to prevent run-on to and run off from the stockpile will be installed when the stockpile remains in place during non-work periods and when there is a forecast rain event.
Installation Dates of installation will be dependent on when stockpiles are needed. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
WILLOW VALLEY CREEK BRIDGE
August 2016
Maintenance Requirements Sediment will be removed from the sediment control devices before it reaches 50% of the height of the sediment control device.
Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any stormwater conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water.)
Stockpile Control #2 Stockpile Stabilization or Covers will be used on soil stockpiles that remain on the project site for more than 14 days to prevent both water and wind erosion. Stabilization may include mulch, tackifier, or manmade physical covers such as rolled erosion control products, tarps, or plastic sheeting.
If tarps or plastic are used, the material will be anchored with sand or gravel bags to prevent removal by the wind.
Visibly inspect stockpiles on work days to ensure that covers remain securely in place and add devices to anchor if needed.
4.2.5 Minimize Dust
Topsoil Control # 1 Topsoil Control Description
Dates of installation will be dependent on when stockpiles are needed. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
Installation Dates of installation will be dependent on when stockpiles are needed. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
Maintenance Requirements Sediment will be removed from the sediment control devices before it reaches 50% of the height of the sediment control device.
Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any stormwater conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water.)
4.2.6 Minimize the Disturbance of Steep Slopes (ADEQ CGP 3.1.1.3)
Slope Stabilization # 1 Slope Stabilization Description
Unavoidable impacts to steep slopes will be stabilized using riprap and gabion walls underlain with geocomposite or geotextile fabric. Perimeter controls will be placed prior to earth disturbance.
Installation Dates of installation will be dependent on when steep slopes are impacted. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
Maintenance Requirements
WILLOW VALLEY CREEK BRIDGE
August 2016
Sediment will be removed from the sediment control devices before it reaches 50% of the height of the sediment control device.
Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any stormwater conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water.)
Slope Control # 2 Slope Stabilization Description
Unavoidable impacts to steep slopes will be stabilized using geotextile fabric and geocomposite. Perimeter controls will be placed prior to earth disturbance.
Installation Dates of installation will be dependent on when steep slopes are impacted. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
Maintenance Requirements Sediment will be removed from the sediment control devices before it reaches 50% of the height of the sediment control device.
Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any stormwater conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water.)
4.2.7 Topsoil (ADEQ CGP 3.1.1.4.2)
General If topsoil is encountered during excavation and grading activities, the topsoil will be removed from vegetated areas and conserved for replacement on the final fill slopes.
Specific Topsoil Controls
Topsoil Control # 1 Topsoil Control Description
If topsoil is encountered during excavation and grading activities, the topsoil will be removed from vegetated areas and conserved for replacement on the final fill slopes.
Installation Dates of installation will be dependent on when stockpiles are needed. Perimeter controls will be placed no later than the end of the work day that the stockpile is placed.
Maintenance Requirements Sediment will be removed from the sediment control devices before it reaches 50% of the height of the sediment control device.
Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any stormwater conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control, storm drain inlet, or surface water.)
4.2.8 Soil Compaction (ADEQ CGP 3.1.1.6)
General Finished slopes will be seeded and mulched once construction is complete. The slopes will be prepared per
Section 625 of the Standard Specifications and Special Contract Requirements prior to be seeded.
Specific Soil Compaction Controls
WILLOW VALLEY CREEK BRIDGE
August 2016
Soil Compaction Control # 1 Soil Compaction Control Description
Slopes will be graded as shown in the plans. All weeds, sticks, and stones 2 inches in diameter and larger, and other large debris will be removed prior to seeding.
See the Plan details and Special Contract Requirements for design details of slope compaction and preparing the seedbed prior to seeding.
Installation Soil will be compacted prior to final vegetative stabilization requirements.
Maintenance Requirements Maintenance of BMP’s will be implemented as soon as practical and all corrective actions will begin within
72 hours of deficiencies being noted during inspections.
4.2.9 Storm Drain Inlets
General:
Storm drain inlet BMPs will be used if needed and incorporated into the SWPPP as outlined above.
4.2.10 Constructed Stormwater Conveyance Channels
General Roadway ditches and embankments will be re-graded and reconstructed as part of the new typical section along Lake Mary Road.
Stormwater Conveyance Channel Control # 1 Stormwater Conveyance Channel Control Description
The ditches will be stabilized with hydro-seed as shown on the plans.
Installation Ditch reconstruction dates will vary and will coincide with the roadway repairs.
Maintenance Requirements Ditches stabilized with hydro-seed will be monitored for revegetation progress.
Stormwater Conveyance Channel Control # 2 Stormwater Conveyance Channel Control Description
The embankments will be constructed using native material and stabilized with hydro-seed and mulching and shown on the plans.
Installation Embankment reconstruction dates will vary and will coincide with the roadway repairs.
Maintenance Requirements
WILLOW VALLEY CREEK BRIDGE
August 2016
Embankments stabilized with hydro-seed will be monitored for revegetation progress.
Inspect embankments after major storms to ensure that they are structurally sound and have not eroded.
4.2.11 Sediment Traps
N/A
4.2.12 Check Dams
Stormwater Check dams Control # 2 Check Dam Description
Check dams of sediment logs, riprap, or gravel bags may be used as approved by the CO, to meet the functional requirements of the check dam.
Check dams will be installed perpendicular to the flowline.
Installation Sediment trap construction dates will vary and will coincide with the roadway repairs.
Maintenance Requirements Remove accumulated sediment from check dams as needed.
Maintain a properly functioning check dam throughout construction or until disturbed areas contributing to the basin have been pave or seeded and mulched.
4.2.12 Sediment Basins
N/A
4.2.13 Chemical Treatment
N/A
4.2.14 Dewatering Practices
N/A
4.2.15 Other Stormwater Controls
General [Contractor to compete as necessary. Repeat as needed.]
Instructions:
― Describe any other stormwater controls that do not fit into the above categories.
WILLOW VALLEY CREEK BRIDGE
August 2016
4.2.15 Site Stabilization (ADEQ CGP 6.3(6)e)
Site Stabilization Practice (only use this if you are not located in an arid, semi-arid, or drought-stricken area)
Vegetative Non-Vegetative Temporary Permanent
Description of Practice The primary site stabilization practices will include paving the road , installing cross culverts with velocity dissipation at the outlet, placing aggregate surfacing along the edges of the pavement for shoulder stability and safety; using geotextile fabric, seed and mulch on earthen disturbances to re-establish vegetation; and silt fence around perimeter of disturbance.
Installation Perform all final seeding and mulching on completed slopes and disturbed areas on the project no more than 14 days calendar days after stabilization activities begin.
Maintenance Requirements Topsoil will be placed on slopes and tracked as the work progresses. Temporary non-vegetative stabilization may need to be added to the slopes until the next seeding window opens. Once the seed and mulch is installed, the temporary sediment control BMP’s can be removed and the area will be monitored and maintained by the USFS personnel until such time as an NOT can be filed. The project will be transferred to the USFS upon final inspection and completion of the construction contract. The stormwater permit will be terminated using the semi-arid termination requirements of yearly inspections and maintenance in accordance with CGP 2.2.2.1.b.
[Repeat as needed for additional stabilization practices.]
WILLOW VALLEY CREEK BRIDGE
August 2016
4.4 Good Housekeeping BMPs (ADEQ CGP 3.1.3.3)
Good housekeeping shall be used to keep potential areas where pollutants exist clean and orderly. Containers, drums, and bags shall be stored away from direct traffic routes to reduce the risk of accidental spills. Stack containers according to manufacturer’s instructions to avoid damaging the containers from improper weight distribution. Containers will be stored on pallets or similar devices to prevent corrosion of containers that results from containers coming in contact with moisture on the ground. Hazardous liquids shall be stored within curbed areas or secondary containment. Secondary containment will be placed around (i.e. sediment control logs) or under (i.e. tarps) semi-stationary portable equipment such as generators and compressors, as this equipment is generally maintained and re-fueled while on-site.
At the end of a shift and before an oncoming storm event, the site inspector shall ensure that all trash bins are secured, and spills have been cleaned up.
Power wash all vehicles and equipment offsite, prior to entering the jobsite to remove dirt, mud, plant materials, non-native seed and noxious weed seed-bearing material. Hauling vehicles shall meet the same requirement before their initial entrance into the park; subsequent entries will not require cleaning unless ordered by the Contracting Officer.
Waste Materials
BMP Description: All waste materials will be collected and disposed of daily into trash dumpsters located in the materials storage area. Dumpsters will have a secure watertight lid, be placed away from storm water conveyances and drains, and meet all federal, state, and municipal regulations. Only trash and construction debris from the site will be deposited in the dumpster.
No construction materials will be buried on-site. All personnel will be instructed, during tailgate training sessions, regarding the correct disposal of trash and construction debris. Notices that state these practices will be posted in the office trailer and the individual who manages day-to-day site operations will be responsible for seeing that these practices are followed.
Installation Schedule: Trash dumpsters will be installed once the materials storage area has been established.
Maintenance and Inspection:
The dumpsters will be inspected weekly and immediately after storm events and will be emptied at least weekly and taken off-site for disposal.
WILLOW VALLEY CREEK BRIDGE
August 2016
Hazardous Waste Materials
BMP Description: A comprehensive waste-management program will be implemented for the storage, handling, inventory, and spill cleanup of hazardous waste (e.g. diesel fuel used for on-site refueling of construction equipment). Hazardous waste will be stored in a designated hazardous-waste collection area with secondary containment. Employees will be trained in proper material use, storage and disposal of hazardous waste.
Installation Schedule: Waste-management program will be implemented prior to construction.
Maintenance and Inspection:
Hazardous waste storage area will be inspected to ensure that hazardous waste containers are properly labeled and to verify no leaks are present.
Responsible Staff: Field Contractor
Sanitary Waste
BMP Description: Temporary sanitary facilities (portable toilets) will be provided at the site throughout the construction phase. The toilets will be in the staging area, located away from concentrated flow paths and traffic flow and will have collection pans underneath as secondary containment where possible. Facilities shall be secured to prevent being inadvertently knocked or blown over.
Installation Schedule: The portable toilets will be brought to the site once the staging area has been established.
Maintenance and Inspection:
All sanitary waste will be collected from the portable facilities as needed, a minimum of once per week, by the assigned company.
The portable toilets will be inspected weekly for evidence of leaking holding tanks. Toilets with leaking holding tanks will be removed from the site and replaced with new portable toilets.
Responsible Staff: Field Contractor
Recycling
BMP Description: Wood pallets, cardboard boxes, and other recyclable construction scraps will be disposed of in a designated dumpster for recycling. The dumpster will have a secure watertight lid, be placed away from storm water conveyances and drains and meet all local and state solid-waste management regulations. Only solid recyclable construction scraps from the site will be deposited in the dumpster. All personnel will be instructed, during tailgate training sessions, regarding the correct procedure for disposal of recyclable construction scraps. Notices that state these procedures will be posted in the office trailer, and the individual who manages
WILLOW VALLEY CREEK BRIDGE
August 2016 day-to-day site operations will be responsible for seeing that these procedures are followed.
Installation Schedule: Designated recycling dumpsters will be installed once the combined staging area has been established.
Maintenance and Inspection:
The recycling dumpster will be inspected weekly and immediately after storm events. The recycling dumpster will be emptied weekly and taken to an approved recycling center by the assigned company. If recyclable construction wastes are exceeding the dumpster’s capacity, the dumpsters will be emptied more frequently.
Responsible Staff: Field Contractor
Staging Areas
BMP Description: Construction equipment and maintenance materials will be stored at the combined staging area and materials storage areas. Maximize the use of previously disturbed areas to minimize ground disturbance. Gravel bag berms will be installed around the perimeter to designate the staging and materials storage area. A watertight shipping container will be used to store hand tools, small parts, and other construction materials. Nonhazardous building materials such as packaging material (e.g., wood, plastic, and glass), and construction scrap material (e.g., wood, steel, metal scraps, and pipe cuttings) will be stored in a separate covered storage facility adjacent to the shipping container. All bagged materials such as concrete, fertilizers, etc. must be covered and all liquid materials must be covered and elevated. Very large items, such as framing materials and stockpiled lumber, will be stored in the open in the materials storage area.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .