Alcoa Aluminum Plant Dike Phase II

Closed Solicitation Posted

Solicitation number
W912PL21B0004
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
California, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks construction services for Phase II of the Alcoa Aluminum Plant Dike project located in Corona, Riverside County, California. The U.S. Army Corps of Engineers, Los Angeles District will award a firm fixed-price contract to construct approximately 3,000 linear feet of earthen dike flood control structure averaging 22 feet in height. Key requirements include modifying roads, installing riprap and hydroseed slopes protection, and constructing a concrete floodwall and floodgate. Bids will be evaluated based on technical qualifications and price, with award made to the responsible bidder offering the lowest price. The bid due date is August 12, 2021.

This is a 100% total small business set-aside reserved for firms with average annual gross receipts not exceeding $39.5 million over the last three fiscal years. The primary NAICS code is 237990 for other heavy and civil engineering construction. The estimated value ranges from $10-25 million to be completed within a period of performance of 1,095 calendar days, with interim completion deadlines for certain items within 730 days and landscape establishment/borrow area closure within 365 days of completion. The place of performance is California.

Notice text

7 versions

Update #7 · Latest ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Amendment 0002 iussed on 7/27/2021 - Soliciation Due date updated to 5 August 2021

Amendemnt 0003 issued on 7/29/2021 - Soliciation Due date remains 5 August 2021

Amendment 0004 issued on 8/3/2021 - Solicitation Due date Updated to 12 August 2021

Amendment 0005 Issued on 8/6/2021 - Soliciation due date remains 12 August 2021

Bid Abstract : Posted on 8/13/2021

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #6 ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Amendment 0002 iussed on 7/27/2021 - Soliciation Due date updated to 5 August 2021

Amendemnt 0003 issued on 7/29/2021 - Soliciation Due date remains 5 August 2021

Amendment 0004 issued on 8/3/2021 - Solicitation Due date Updated to 12 August 2021

Amendment 0005 Issued on 8/6/2021 - Soliciation due date remains 12 August 2021

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #5 ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Amendment 0002 iussed on 7/27/2021 - Soliciation Due date updated to 5 August 2021

Amendemnt 0003 issued on 7/29/2021 - Soliciation Due date remains 5 August 2021

Amendment 0004 issued on 8/3/2021 - Solicitation Due date Updated to 12 August 2021

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #4 ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Amendment 0002 iussed on 7/27/2021 - Soliciation Due date updated to 5 August 2021

Amendemnt 0003 issued on 7/29/2021 - Soliciation Due date remains 5 August 2021

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #3 ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Amendment 0002 iussed on 7/27/2021 - Soliciation Due date updated to 5 August 2021

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #2 ·

Amendment 0001 Issued on 7/19/2021 - Solicitation due date updated to 30 July 2021

- FIO 2 DDR Addendum 2021 updated

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Update #1 ·

Alcoa Dike Phase 2, Corona, Riverside County, CA


The project is approximately 3,000 linear feet earthen filled dike flood control structure. The elevation of the top of the dike varies between elevations 569.50 and 573.50. The dike will have the following basic characteristics: average height of 22 feet above existing ground, width of crest is 15 feet, 2.25 horizontal to 1 vertical (2.25H:1V) side slopes, upstream slope will be protected with 15-inch layer of riprap over a 12-inch layer of bedding, downstream slope will be hydroseeded. Butterfield Drive, W. Rincon Street, and Auburndale Street will be impacted by the construction of the dike. A concrete floodwall and floodgate will be constructed across Auburndale Street. Butterfield Drive will be modified and a new connector road constructed to connect to Rincon Street.

Total Period of Performance is 1095 Calendar Days. Completion of Bid Item’s 0001 through 0032, 0034, and 0036 through 0038 will be within the first 730 Calendar Days. Completion of Bid Item 0033 and 0035 Landscape Establishment and 0034 Borrow Area Closure will be 365 Calendar Days and be completed prior to the end of the Total Period of Performance period.”


The Estimate cost range for this procurement is $10,000,000 - $25,000,000.

This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.


Be advised this project may delayed, postponed, canceled or revised at any time prior to award.

Files

Show all 18

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Alcoa Aluminum Plant Dike Phase II Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Brine pipeline access improvements City of Menifee, Riverside County, CA · NAICS 237110 ENDIST Los Angeles Total Small Business
USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA Sacramento, California 95837 · NAICS 237990 ENDIST Sacramento No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity