This document contains a bid abstract and related federal contract opportunity notice for construction services. The bid abstract lists 38 line items for services required to construct approximately 3,000 linear feet of earthen dike flood control structures, including clearing, excavation, fill, riprap, concrete structures, utility relocations and road modifications. Five contractors provided lump sum or unit price bids for each line item, with total bid amounts ranging from $24.5 million to $38.6 million. The related federal contract opportunity notice identifies the solicitation number, name of the Alcoa Aluminum Plant Dike Phase II project, provides a project description matching the work outlined in the bid abstract, estimates the cost range to be between $10-25 million, specifies this as a 100% small business set-aside, lists the NAICS code and size standard, and notes the project may be delayed, postponed, canceled or revised at any time prior to award.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SECTION 00 10 00 | |||||
| Solicitation Contract Line Item (CLIN) Schedule | EMPIRE | SILVERSTRAND | ZUSSER | LARISON | CJW |
| CONTRACTOR MUST FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. | |||||||||||||||||||||||||
| Quantity | Unit | Unit Price | Amount | Quantity | Unit | Unit Price | Amount | Quantity | Unit | Unit Price | Amount | Quantity | Unit | Unit Price | Amount | Quantity | Unit | Unit Price | Amount | ||||||
| Bidding Schedule | |||||||||||||||||||||||||
| 0001 | Construction Dewatering of Groundwater | 1 | Job | JA | $ 458,651 | 1 | Job | JA | $ 142,000.00 | 1 | Job | JA | $ 151,200.00 | 1 | Job | JA | $ 50,000.00 | 1 | Job | JA | $ 450,000.00 | 1 | Job | JA | $ 1,200,000.00 |
0002 Treatment of Dewatering Effluent 1 Job JA $ 155,758 1 Job JA $ 98,000.00 1 Job JA $ 151,200.00 1 Job JA $ 30,000.00 1 Job JA $ 125,000.00 1 Job JA $ 80,000.00
0003 Control of Surface Water 1 Job JA $ 106,126 1 Job JA $ 158,000.00 1 Job JA $ 76,137.00 1 Job JA $ 80,000.00 1 Job JA $ 295,500.00 1 Job JA $ 5,900,000.00
0004 Well Abandonment 2 EA $3,160 $ 6,320 2 EA $4,250.00 $ 8,500.00 2 EA $15,139.57 $ 30,279.00 2 EA $30,000.00 $ 60,000.00 2 EA $5,725.00 $ 11,450.00 2 EA $1,600.00 $ 3,200.00
0005 Clear Site and Remove Obstructions 16 AC $11,052 $ 176,832 16 AC $3,200.00 $ 51,200.00 16 AC $17,236.26 $ 275,780.00 16 AC $50,000.00 $ 800,000.00 16 AC $20,000.00 $ 320,000.00 16 AC $36,000.00 $ 576,000.00
0006 Stripping 25,000 CY $14.50 $ 362,500 25,000 CY $2.40 $ 60,000.00 25,000 CY $4.32 $ 108,056.00 25,000 CY $20.00 $ 500,000.00 25,000 CY $4.00 $ 100,000.00 25,000 CY $5.00 $ 125,000.00
0007 Excavation 126,000 CY $5.50 $ 693,000 126,000 CY $2.90 $ 365,400.00 126,000 CY $2.61 $ 329,418.00 126,000 CY $10.00 $ 1,260,000.00 126,000 CY $4.00 $ 504,000.00 126,000 CY $4.00 $ 504,000.00
0008 Overexcavation
0008AA First 4,000 CY 4,000 CY $5.75 $ 23,000 4,000 CY $3.60 $ 14,400.00 4,000 CY $3.00 $ 12,018.00 4,000 CY $30.00 $ 120,000.00 4,000 CY $11.50 $ 46,000.00 4,000 CY $26.00 $ 104,000.00
0008BB Over 4,000 CY 4,000 CY $5.25 $ 21,000 4,000 CY $3.50 $ 14,000.00 4,000 CY $2.74 $ 10,964.00 4,000 CY $35.00 $ 140,000.00 4,000 CY $11.50 $ 46,000.00 4,000 CY $24.00 $ 96,000.00
0009 General Fill 10,300 CY $27.00 $ 278,100 10,300 CY $13.00 $ 133,900.00 10,300 CY $4.64 $ 47,777.00 10,300 CY $25.00 $ 257,500.00 10,300 CY $43.00 $ 442,900.00 10,300 CY $4.00 $ 41,200.00
0010 Zone I Material 306,600 CY $31.00 $ 9,504,600 306,600 CY $23.00 $ 7,051,800.00 306,600 CY $23.65 $ 7,249,813.00 306,600 CY $17.00 $ 5,212,200.00 306,600 CY $13.00 $ 3,985,800.00 306,600 CY $4.80 $ 1,471,680.00
0011 Select Zone I Material 7,000 TON $43.00 $ 301,000 7,000 TON $31.00 $ 217,000.00 7,000 TON $37.95 $ 265,660.00 7,000 TON $75.00 $ 525,000.00 7,000 TON $147.75 $ 1,034,250.00 7,000 TON $140.00 $ 980,000.00
0012 Zone II Material 79,000 CY $37.50 $ 2,962,500 79,000 CY $24.90 $ 1,967,100.00 79,000 CY $28.40 $ 2,243,624.00 79,000 CY $18.00 $ 1,422,000.00 79,000 CY $10.00 $ 790,000.00 79,000 CY $8.00 $ 632,000.00
0013 15 Inch Riprap 19,800 TON $54.50 $ 1,079,100 19,800 TON $51.00 $ 1,009,800.00 19,800 TON $54.04 $ 1,070,077.00 19,800 TON $56.00 $ 1,108,800.00 19,800 TON $86.00 $ 1,702,800.00 19,800 TON $52.00 $ 1,029,600.00
0014 Bedding 17,400 TON $43.25 $ 752,550 17,400 TON $48.00 $ 835,200.00 17,400 TON $39.23 $ 682,530.00 17,400 TON $40.00 $ 696,000.00 17,400 TON $59.00 $ 1,026,600.00 17,400 TON $38.00 $ 661,200.00
Item Description Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount
0015 Aggregate Base Course 5,700 TON $33.00 $ 188,100 5,700 TON $31.00 $ 176,700.00 5,700 TON $36.67 $ 209,005.00 5,700 TON $60.00 $ 342,000.00 5,700 TON $43.00 $ 245,100.00 5,700 TON $50.00 $ 285,000.00
0016 Floodgate 1 Job JA $ 1,650,607 1 Job JA $ 910,150.00 1 Job JA $ 1,244,405.00 1 Job JA $ 1,500,000.00 1 Job JA $ 1,305,000.00 1 Job JA $ 2,800,000.00
0017 Floodwall 168 LF $5,268 $ 885,024 130 LF $4,450.00 $ 747,600.00 130 LF $6,431.80 $ 1,080,542.00 130 LF $3,000.00 $ 504,000.00 130 LF $7,380.00 $ 1,239,840.00 130 LF $14,000.00 $ 2,352,000.00
0018 Culvert 1 - Station 91+44.45 1 Job JA $ 349,749 1 Job JA $ 268,000.00 1 Job JA $ 565,607.00 1 Job JA $ 400,000.00 1 Job JA $ 686,675.00 1 Job JA $ 900,000.00
0019 Culvert 2 - Station 119+60 1 Job JA $ 240,865 1 Job JA $ 182,000.00 1 Job JA $ 334,731.00 1 Job JA $ 190,000.00 1 Job JA $ 439,250.00 1 Job JA $ 800,000.00
0020 AC Paving 130 TON $94.00 $ 12,220 130 TON $132.00 $ 17,160.00 130 TON $117.13 $ 15,227.00 130 TON $250.00 $ 32,500.00 130 TON $200.00 $ 26,000.00 130 TON $200.00 $ 26,000.00
0021 4 Foot Wide Concrete Swale 710 LF $80.00 $ 56,800 710 LF $68.00 $ 48,280.00 710 LF $154.62 $ 109,778.00 710 LF $165.00 $ 117,150.00 710 LF $120.00 $ 85,200.00 710 LF $124.00 $ 88,040.00
0022 10 Foot Wide Concrete Swale 380 LF $119.00 $ 45,220 380 LF $149.00 $ 56,620.00 380 LF $245.98 $ 93,473.00 380 LF $300.00 $ 114,000.00 380 LF $150.00 $ 57,000.00 380 LF $142.00 $ 53,960.00
0023 Test Trench 6 EA $895.00 $ 5,370 6 EA $2,500.00 $ 15,000.00 6 EA $2,928.35 $ 17,570.00 6 EA $5,000.00 $ 30,000.00 6 EA $4,430.00 $ 26,580.00 6 EA $2,600.00 $ 15,600.00
0024 Settlement Monuments 25 EA $1,714 $ 42,850 25 EA $4,180.00 $ 104,500.00 25 EA $6,927.30 $ 173,183.00 25 EA $5,000.00 $ 125,000.00 25 EA $7,200.00 $ 180,000.00 25 EA $2,400.00 $ 60,000.00
0025 Settlement Bases 2 EA $6,364 $ 12,728 2 EA $15,950.00 $ 31,900.00 2 EA $32,797.52 $ 65,595.00 2 EA $15,000.00 $ 30,000.00 2 EA $10,000.00 $ 20,000.00 2 EA $10,000.00 $ 20,000.00
0026 Geotechnical Instrumentation 1 Job JA $ 240,092 1 Job JA $ 435,000.00 1 Job JA $ 56,810.00 1 Job JA $ 350,000.00 1 Job JA $ 240,000.00 1 Job JA $ 140,000.00
0027 Soil-Cement-Bentonite (SCB) Cutoff Wall 8,600 SF $125.50 $ 1,079,300 8,600 SF $129.00 $ 1,109,400.00 8,600 SF $29.28 $ 251,838.00 8,600 SF $180.00 $ 1,548,000.00 8,600 SF $145.00 $ 1,247,000.00 8,600 SF $798.00 $ 6,862,800.00
0028 CIP Wall Section 1 Job JA $ 83,698 1 Job JA $ 38,000.00 1 Job JA $ 565,705.00 1 Job JA $ 100,000.00 1 Job JA $ 108,600.00 1 Job JA $ 80,000.00
0029 Sound Wall 10,000 LF $67.50 $ 675,000 10,000 LF $42.00 $ 420,000.00 10,000 LF $52.71 $ 527,112.00 10,000 LF $60.00 $ 600,000.00 10,000 LF $30.00 $ 300,000.00 10,000 LF $28.00 $ 280,000.00
0030 Swing Gate 1 Job JA $ 14,983 1 Job JA $ 21,000.00 1 Job JA $ 16,065.00 1 Job JA $ 16,000.00 1 Job JA $ 37,650.00 1 Job JA $ 32,000.00
0031 Landscape Planting and Hydroseeding 97 AC $6,797 $ 659,309 97 AC $7,300.00 $ 708,100.00 97 AC $4,649.13 $ 450,966.00 97 AC $8,000.00 $ 776,000.00 97 AC $11,850.00 $ 1,149,450.00 97 AC $3,200.00 $ 310,400.00
0032 Temporary Irrigation 97 AC $8,421 $ 816,837 97 AC $5,975.00 $ 579,575.00 97 AC $4,649.13 $ 450,966.00 97 AC $5,000.00 $ 485,000.00 97 AC $12,280.00 $ 1,191,160.00 97 AC $2,200.00 $ 213,400.00
0033 Landscape Establishment 97 AC $1,676 $ 162,572 97 AC $2,520.00 $ 244,440.00 97 AC $2,801.55 $ 271,751.00 97 AC $7,500.00 $ 727,500.00 97 AC $7,125.00 $ 691,125.00 97 AC $1,800.00 $ 174,600.00
0034 City of Corona 12 Inch Domestic Water Steel Casing Annular Space Fill 1 Job JA $ 780,898 1 Job JA $ 28,000.00 1 Job JA $ 89,777.00 1 Job JA $ 50,000.00 1 Job JA $ 88,500.00 1 Job JA $ 150,000.00
0035 Borrow Area Closure 1 Job JA $ 893,120 1 Job JA $ 325,000.00 1 Job JA $ 234,268.00 1 Job JA $ 125,000.00 1 Job JA $ 666,500.00 1 Job JA $ 60,000.00
Item Description Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount
0036 City of Corona Street Improvements 1 Job JA $ 7,880,432 1 Job JA $ 5,044,053.00 1 Job JA $ 9,751,242.00 1 Job JA $ 9,400,000.00 1 Job JA $ 9,765,550.00 1 Job JA $ 6,800,000.00
0037 City of Corona Sewer and Force Main Relocation and Protection 1 Job JA $ 1,088,973 1 Job JA $ 401,752.00 1 Job JA $ 684,896.00 1 Job JA $ 650,000.00 1 Job JA $ 1,092,750.00 1 Job JA $ 1,600,000.00
0038 Santa Ana River Trail - Phase 4 1 Job JA $ 1,026,540 1 Job JA $ 456,878.00 1 Job JA $ 750,347.00 1 Job JA $ 1,025,000.00 1 Job JA $ 1,180,000.00 1 Job JA $ 1,100,000.00
| TOTAL AMOUNT: | $ 35,772,324 | Total Amount: | $ 24,495,408.00 | Total Amount: | $ 30,715,393.00 | Total Amount: | $ 31,498,650.00 | Total Amount: | $ 32,949,230.00 | Total Amount: | $ 38,607,680.00 |