127EAW21R0039 - South Gate Bridge Project
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 127EAW21R0039
- Agency
-
Region 5 - Pacific Southwest Region
Forest Service, Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- McCloud, California 96057, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks bridge construction services for the South Gate Bridge Project located on the Shasta-Trinity National Forest in McCloud, California. The USDA Forest Service Pacific Southwest Region is procuring the replacement of an existing bridge over a 90 calendar day performance period. Offerors must visit the site and submit any requests for information to the contracting officer by June 30, 2021. Proposals will be evaluated based on the ability to complete the project within the performance period timeline. The submission deadline for proposals is July 22, 2021.
This is a total small business set-aside designated under NAICS 237310 and PSC C-212. The estimated value of the contract is between $100,000 and $250,000 to replace a 28-foot long by 16-foot wide concrete bridge. Unsuitable material from excavation and demolition can be disposed of onsite. The place of performance is the Shasta-Trinity National Forest in McCloud, California. The contract is to be awarded by August 2, 2021 and have a 90 day period of performance from notice to proceed.
Notice text
4 versions
Update #4 · Latest ·
127EAW21R0039 - South Gate Bridge Project - Amendment A00003
The purpose of this solicitation amendment is post RFI Official Responses. Attached is "RFI Official Responses - 1" which are hereby incorporated into any subsequent contract award. All other terms and conditions remain unchanged.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project - Amendment A00002
The purpose of this solicitation amendment is extend the solicitation date.
Proposal due date shall be extended from July 8th, 2021 to July 22nd, 2021, 1300 PST
Contract time shall read on all aspects of the solicitation to 90 days. All other terms remain unchanged.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project - Amendment A00001
The purpose of this solicitation amendment is inform all offerors of site access gate codes. The gates to access the site now have new brass colored Master locks with USFS etched in the side with a combo of 1966.
There is monitored 24/7 surveillance in the area and offerors are cautioned to only use the codes to access the site and lock them upon exiting the site.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, June 30th, 2021.
An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Update #3 ·
127EAW21R0039 - South Gate Bridge Project - Amendment A00002
The purpose of this solicitation amendment is extend the solicitation date.
Proposal due date shall be extended from July 8th, 2021 to July 22nd, 2021, 1300 PST
Contract time shall read on all aspects of the solicitation to 90 days. All other terms remain unchanged.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project - Amendment A00001
The purpose of this solicitation amendment is inform all offerors of site access gate codes. The gates to access the site now have new brass colored Master locks with USFS etched in the side with a combo of 1966.
There is monitored 24/7 surveillance in the area and offerors are cautioned to only use the codes to access the site and lock them upon exiting the site.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, June 30th, 2021.
An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Update #2 ·
127EAW21R0039 - South Gate Bridge Project - Amendment A00001
The purpose of this solicitation amendment is inform all offerors of site access gate codes. The gates to access the site now have new brass colored Master locks with USFS etched in the side with a combo of 1966.
There is monitored 24/7 surveillance in the area and offerors are cautioned to only use the codes to access the site and lock them upon exiting the site.
////////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW21R0039 - South Gate Bridge Project
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, June 30th, 2021.
An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Update #1 ·
127EAW21R0039 - South Gate Bridge Project
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, June 30th, 2021.
An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Files
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| 127EAW21C0020 - South Gate Bridge Project - Award | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Stove Prairie Campground Gate Replacement | Forest Service | Total Small Business | |
| GOGA 336173 - Repair Conzelman Road | National Office | No set-aside | |
| Cisco Branch Ontonagon River Bridge Replacement | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity