X10 Drone Dock Manual_Installation and Specifications.pdf
PDF 7 MB Posted
- Attached to
- DRONE PLATFORM FABRICATION AND DELIVERY
- Solicitation number
- B27000148
- Issued by
- Hawaii
About this file
This is a Site Readiness Manual for the Skydio Dock for X10 drone docking station system, prepared by Skydio, Inc. in support of a Hawaii Department of Law Enforcement Invitation for Bid for drone platform fabrication and delivery. The manual provides comprehensive technical specifications and installation requirements for three drone docking platforms to be fabricated, transported, and installed on the roof of a single location on Oahu. The Skydio Dock for X10 is an autonomous drone charging and management system designed to support Law Enforcement Drone First Responder activities. The fully assembled dock weighs 240 pounds and measures 55.5 inches in height with a closed roof; it requires a minimum 4-foot by 4-foot concrete pad (6 inches thick) for permanent mounting or can be installed using non-bolted leveling feet rated for up to 80 miles per hour winds. Each dock requires dedicated electrical power (100-240V AC, 50-60 Hz), with 200-240V at 20A breaker mandatory for below-freezing operations to enable dock heater functionality and prevent ice accumulation that could cause aircraft crashes or performance degradation.
The dock system includes technical specifications for power consumption (2200W peak load, 1200W operational), battery charging capabilities (15-95% charge within 35 minutes at 77°F), onboard storage (512GB), and network connectivity (2x PoE 30W ports, 1x USB 3.0). Each dock must be paired with an External Radio antenna system (2.65 pounds, 19.7 inches height) mounted on a separate pole with minimum 17-foot horizontal distance from the dock, requiring shielded CAT6 Ethernet cabling (maximum 328 feet length). Installation demands site-specific planning including obstacle clearance within a 15-foot radius, GNSS considerations, approach/landing zones, and final verification through Skydio Pre-Site Survey. Multiple docks require minimum 5-foot spacing between units and 15-foot clearance for safe operation. The customer bears sole responsibility for infrastructure provisions including electrical work, networking, mounting, conduit installation, and site preparation, while Skydio provides hardware and installation/validation services through authorized technicians.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Skydio Dock for X10 Site Readiness Manual
Site Readiness Manual
Dock Specifications
Technical Specifications
Weights and Dimensions
External Radio Specifications
Technical Specifications
Weights and Dimensions
Site Preparation
Dock Power Requirements
External Radio Power Requirements
Wiring Configuration
Ethernet Cable Requirements
Computer System Requirements
Installation Requirements
Transport and Delivery
Dock Installation Requirements
External Radio Installation Requirements
Multiple Docks (Hive)
Appendixes
Corrosion Guidance
Safety Information
Revision History
Site Readiness Manual This document explains installation requirements, technical specifications, network and power provisioning, and flight‑zone design for one or more Skydio Dock for X10s.
NOTICE
Follow official documentation and updates.
Failure to follow any instructions or recommendations in Skydio documentation may void the Skydio Limited Warranty or other terms and conditions.
Please read all documentation provided with the Skydio Dock for X10, including but not limited to the Doc for X10 Safety Guidelines in the Safety and Operating Guide: www.skydio.com/safety.
© 2026 Skydio, Inc. All rights reserved. Proprietary. Printed copies are uncontrolled.
http://www.skydio.com/safety
Skydio Dock for X10 Site Readiness Manual | Page 4
Dock for X10 Specifications
Technical Specifications This section contains technical specifications for the Dock for X10.
Category Specification / Requirement
Launch Time 20 Seconds
Battery Charge Time 15% to 95% within 35 minutes at 77°F (25°C)
Cooling or heating will increase overall charge time to max of 73 minutes
Power Input 100 V to 240 V (200 V to 240 V required below 32°F (0°C)).
50 to 60 Hz
2200W at peak load
20A breaker for 200 V to 240 V
For more information, see Peak Power by Dock State (on page 14)
Power Load
1200W for operations above 32°F (0°C)
15A breaker for 100V-120V
Input/Output 2x PoE (30 W, 48 V)
1x USB 3.0 (5 W, 5 V)
Onboard Storage 512 GB (Non-removable, for media sync purposes only)
Service Life 5 years with regular service conducted annually
WARNING:
Ice accumulation when operating below 32°F (0°C) without a 200V-240V power supply. When operating below 32°F (0°C) without a 200V-240V power supply, Dock Heater functionality will be unavailable. Ice accumulation can result in degraded performance, crashes, or loss of the aircraft. For operation below 32°F (0°C), a 200V-240V power supply from a dedicated 20A breaker must be provided to enable Dock Heater functionality. Provide a 100V-120V power supply from a dedicated 15A breaker for operation in temperatures from 32°F (0°C) to 122°F (50°C).
Skydio Dock for X10 Site Readiness Manual | Page 5
Operating Limits
Category Specification / Requirement
Launch / Land Winds Up to 12 m/s (28 mph / 45 km/h)
Standby Wind Rating Bolted to Permanent Structure: Up to 160 mph (257 km/h)
Note:
For bolting guidance information, see Dock Installation Requirements (on page 22)
Skydio Dock Feet Installed: 80 mph (128 km/h)
Non-Bolted: 40 mph (64.4 km/h)
Operational Temperature
-4° to 122° F (-20° to 50° C)
Standby/Storage Temperature
-40° to 140° F (-40° to 60° C)
Ingress Protection (Roof Open)
IPX5
Ingress Protection (Roof Closed)
IPX6
Corrosion Resistance Designed to operate in humid environments, outside of direct saltwater splash zones.
Rain and Snow Limitations
Operational Capability*:
• 0.25 in/hr (light-moderate)
• Standby: 4.0 in/hr (Heavy)
*Limited by Dock for X10.
Skydio Dock for X10 Site Readiness Manual | Page 6
Weights and Dimensions
Weights
Category Specification / Requirement
Dock Roof 36 lb (16.3 kg)
Dock Base 143 lb (64.9 kg)
Dock Stand 53 lb (24.0 kg)
Fully Assembled 240 lb (108.9 kg)
Total Shipping Weight 300 lb (136.1 kg)
WARNING:
Transportation pallet tip hazard. Do not remove the Dock from its shipping pallet until it has reached the designated final installation location. While operating lift equipment, wear appropriate PPE.
Dimensions
Category Specification / Requirement
Height (Front View - Closed Roof) 55.5 in (141.0 cm)
Height (Front View - Open Roof Maximum)
37.6 in (95.5 cm)
Height (Side View - Dock Base) 31.3 in (79.5 cm)
Height (Side View - Dock Stand) 24.1 in (61.2 cm)
Width (Front View - Closed Roof) 37.7 in (95.8 cm)
Width (Front View - Open Roof) 40.5 in (102.9 cm)
Depth (Side View – Closed Roof) 34.1 in (86.6 cm)
Depth (Side View – Open Roof) 45.9 in (116.6 cm)
Depth (Side View - Maximum) 48.9 in (124.2 cm)
Doorway (Minimum) 29.7 in (75.4 cm)
Skydio Dock for X10 Site Readiness Manual | Page 7
Height / Width Depth / Base Height / Stand Height
Entryway Minimum Width - Roof Open
Depth - Roof Open Maximum Depth / Height - Roof Open
Skydio Dock for X10 Site Readiness Manual | Page 8
Materials
The Dock for X10 is composed of the following materials:
• Exterior Plastic: UL F1 rated* coating meets AAMA 2604 compliance for UV Resistance.
• Exterior Metals: Coated with Tiger Drylac Series 138* coating.
Note:
This coating is AAMA 2604 compliant for UV Resistance
*All materials and components are subject to change
Skydio Dock for X10 Site Readiness Manual | Page 9
External Radio Specifications
Technical Specifications WNC Radio Antenna
Type Specification / Requirement
Low Voltage Power Nominal: 11 to 13 W
USB-C: 5 V / 3 A, 9 V / 3 A, 12 V / 3 A, 15 V / 3 A, 20 V / 3 A
PoE: IEEE 802.3af
Power Input PoE from Skydio Dock or by Customer network.
Minimum: IEEE 802.3af
Power Load 11 to 13 W
Power draw will increase with increasing cable lengths
Input/Output 1x Ethernet, 1x USB-C 3.0
Operating Frequency Connect SL: 2400 to 2483.5 MHz and 5150 to 5850 MHz
Service Life 5 years of continual service with Dock
2 years when human-carried
ADS-B In Included
Skydio Dock for X10 Site Readiness Manual | Page 10
Type Specification / Requirement
GNSS GPS + Galileo + GLONASS + BeiDou
Operating Limits
Type Specification / Requirement
Wind Resistance* Up to 130 mph (209 km/h)
Operational Temperature -4° to 122°F (-20° to 50°C)
Storage Temperature -40° to 176°F (-40° to 80°C)
Ingress Protection IP55
Corrosion Resistance Designed to operate in humid environments, outside of direct saltwater splash zone
* Measures the wind speed at which the External Radio and bracket will remain on the pole they are mounted to.
This specification does not indicate the wind resistance of the pole itself.
Skydio Dock for X10 Site Readiness Manual | Page 11
Weights and Dimensions
Weights
Category Specification / Requirement
Total Weight 2.65 lbs (1.2 kg)
Dimensions
Category Specification / Requirement
Height (Antenna to Antenna) 19.7 in (50.0 cm)
Width (Pine Dual Band) 9.4 in (23.9 cm)
Depth (Pine Dual Band to Rear Bracket) 9.3 in (23.6 cm)
Skydio Dock for X10 Site Readiness Manual | Page 12
Site Preparation
Dock Power Requirements
Power Connection Options
The Dock for X10 may be powered with either a 100V-120V connection or a 200V-240V connection. To ensure the Dock is able to operate in below freezing conditions, use a 200V-240V connection.
WARNING:
Ice accumulation when operating below 32°F (0°C) without a 200V-240V power supply. When operating below 32°F (0°C) without a 200V-240V power supply, Dock Heater functionality will be unavailable. Ice accumulation can result in degraded performance, crashes, or loss of the aircraft. For operation below 32°F (0°C), a 200V-240V power supply from a dedicated 20A breaker must be provided to enable Dock Heater functionality. Provide a 100V-120V power supply from a dedicated 15A breaker for operation in temperatures from 32°F (0°C) to 122°F (50°C).
Disconnect Accessibility:
Provide a local switched disconnect on the roof, accessible to both Skydio and Customer personnel.
DANGER:
Electrical hazard. Exposure to energized components can result in serious injury or death. Follow local/site specific lockout/tagout procedures for de-energizing the Dock and removing electrical hazards. Ensure the work area is clear of unnecessary personnel. If necessary, restrict access to the area.
Before performing service on the unit, do the following:
• Engage the Dock E-Stop button.
• Turn the Dock OFF.
• Disconnect the Dock from the AC power supply.
• Disconnect all external data and power cables from the Dock.
• Complete required lockout/tagout procedures per site requirements.
Surge Protection:
To better protect the dock, it is recommended to use surge protection rated 40 kA or 4 kV.
Skydio Dock for X10 Site Readiness Manual | Page 13
Power for Each Dock Type Specification / Requirement
Power Input 100 V to 240 V (200 V to 240 V required below 32°F (0°C)).
50 to 60 Hz
2200W at peak load
20A breaker for 200 V to 240 V
Power Load
1200W for operations above 32°F (0°C)
15A breaker for 100V-120V
Input/Output 2x PoE (30 W, 48 V)
1x USB 3.0 (5 W, 5 V)
Skydio Dock for X10 Site Readiness Manual | Page 14
Peak Power by Dock State Hot Room Temperature Cold Peak Voltage
(VAC): 100 V
Cold Peak Voltage
(VAC): 240 V
Device / Status
140 °F / 60 °C 75 °F / 23.8 °C -4° F / -20 °C -4° F /-20 °C
Dock - Not Charging 550 W 400 W 1300 W 1300 W
Dock - Charging 850 W 700 W 1430 W 1600 W
Dock - Super Charging 1000 W 850 W 1430 W 1750 W
Dock - Moving 1200 W 1000 W 1120 W 1300 W
External Radio Power Requirements Type Specification / Requirement
Power Nominal: 11 to 13 W
USB-C: 5 V / 3 A, 9 V / 3 A, 12 V / 3 A, 15 V / 3 A, 20 V / 3 A
PoE: IEEE 802.3af
Power Input PoE from Skydio Dock or by Customer network.
Minimum: IEEE 802.3af
Power Load 11 to 13 W
Power draw will increase with increasing cable lengths
Skydio Dock for X10 Site Readiness Manual | Page 15
Wiring Configuration
Hardwired and Conduit Requirements
DANGER:
Electrical hazard. Exposure to energized components can result in serious injury or death. Follow local/site specific lockout/tagout procedures for de-energizing the Dock and removing electrical hazards. Ensure the work area is clear of unnecessary personnel. If necessary, restrict access to the area.
Before performing service on the unit, do the following:
• Engage the Dock E-Stop button.
• Turn the Dock OFF.
• Disconnect the Dock from the AC power supply.
• Disconnect all external data and power cables from the Dock.
• Complete required lockout/tagout procedures per site requirements.
WARNING:
Ice accumulation when operating below 32°F (0°C) without a 200V-240V power supply. When operating below 32°F (0°C) without a 200V-240V power supply, Dock Heater functionality will be unavailable. Ice accumulation can result in degraded performance, crashes, or loss of the aircraft. For operation below 32°F (0°C), a 200V-240V power supply from a dedicated 20A breaker must be provided to enable Dock Heater functionality. Provide a 100V-120V power supply from a dedicated 15A breaker for operation in temperatures from 32°F (0°C) to 122°F (50°C).
The following applies from the perspective of the Drone:
• Low voltage data is routed to the left side of the Dock.
• High Voltage AC power is routed to the right side of the Dock.
Skydio Dock for X10 Site Readiness Manual | Page 16
The following hardwire and conduit requirements apply to Dock installation:
• There must be 1x circuit per Dock.
• A manual disconnect must be accessible to a Skydio Authorized Technician and placed within line of sight of the Skydio Dock.
• For 200 V to 240 V: 12 AWG setup required for cold weather (L1, L2, G)
• For 100 V to 120 V: 12 AWG setup (L, N, G)
• Hard conduit is run between the circuit breaker box to the flex conduit beside the Dock.
• The Knockout on both sides of the Dock is sized for 1.0" EMT conduit or equivalent to a 2.54 cm diameter hole.
Note:
Located 6.5" (16.5 cm) above ground level.
• To ensure there is enough conduit wiring to the terminal connections inside the Dock, provide an additional 4.0 ft (1.2 m) wire beyond each Dock's knockout location.
• Hardwired power connects to Wago connectors located inside of the Dock.
Conduit Wago Connectors
Skydio Dock for X10 Site Readiness Manual | Page 17
Ethernet Cable Requirements Skydio Device X10 Dock Cable External Radio
Connection X10 Dock to PoE Switch External Radio to X10 Dock or PoE Switch
Conductors 23 AWG Solid Bare Copper 23 AWG Solid Bare Copper
Shielding Aluminum Foil Overall (F/UTP) Aluminum Foil Overall (F/UTP)
Outer Diameter (OD) No Restriction 5.3mm - 6.5mm (Restricted to ensure gland fits)
Jacket CMX rated
Outdoor rated, UV-resistance in compliance with UL444, Withstands temps -40 to 90C (not necessarily direct-burial rated)
CMX rated
Outdoor rated, UV-resistance in compliance with UL444, Withstands temps -40 to 90C (not necessarily direct-burial rated)
Bandwidth Up to 550 MHz Up to 550 MHz
PoE Support Up to 100W (IEEE 802.3af/at/bt, 4PPoE) Up to 100W (IEEE 802.3af/at/bt, 4PPoE)
Certification ANSI/TIA‑568.2 ‑D, cETLus, RoHS ‑3, Fluke tested
ANSI/TIA‑568.2 ‑D, cETLus, RoHS ‑3, Fluke tested
Connectors CAT6 Shielded 23AWG RJ45 Connector CAT6 Shielded 23AWG RJ45 Connector
Strain Relief Strain relief is mandatory on dock side to prevent long term damage.
[Note there is a significant ~30 deg bend when plugged into the dock making the strain relief critical]
No Strain relief on waterproof gland on the External Radio-side.
Strain Relief required if the other side is plugged into the dock. Else optional.
To prevent signal loss for network installations, CAT6A cabling offers higher performance specifications compared to standard CAT6. Ensure cable length is less than 328 ft (100.0 m).
CAT6 cable with solid copper and double shielding is more than sufficient for nearly all installations. CAT6A is not required for Skydio systems as our operations do not utilize the higher throughput speeds it supports.
CAUTION:
Improper installation, routing, or excessive length of Cat6 network cables. Improper cabling may result in degraded data transfer rates and reduced communication reliability. Do not exceed recommended cable length limit. Avoid kinking, sharp bends, or placing excess weight on Cat6 network cables.
When to Consider CAT6A
For installations with long cable runs or environments with significant electrical interference, CAT6A may provide additional protection against signal loss or errors. These are edge scenarios, however, and in the vast majority of deployments, CAT6 will perform reliably without issue.
Skydio Dock for X10 Site Readiness Manual | Page 18
Computer System Requirements
Remote Flight Deck/DFR Command System Requirements
For optimal performance with Remote Flight Deck, and DFR Command, ensure the computers used with the Dock for X10 Flight System meet the requirements below.
For information about network setup and configuration, see: Skydio Dock for X10 Networking Guide.
Note:
Skydio does not support accessing Remote Flight Deck from Virtual Desktop Infrastructure (VDI). Remote Flight Deck must be flown on a local machine.
System Performance Requirements
Category Minimum Recommended
CPU Intel Core i5-8400 or AMD Ryzen 5 2600 Intel Core i7-12700 or AMD Ryzen 7 7700X
RAM 32 GB DDR4 32 GB DDR4 or greater
GPU
Desktop: NVIDIA GTX 1060 or AMD RX
Laptop: NVIDIA GTX 1060 Mobile or AMD
RX 5500M
Desktop: NVIDIA RTX 2070 or AMD Radeon RX 6600 XT
Laptop: NVIDIA RTX 2070 Mobile or AMD Radeon RX 6700M
Network 100 Mbps sustained with latency under 50 ms
1 Gbps Ethernet preferred, or Wi-Fi 6 with minimum 300 Mbps sustained with Latency under 30 ms
Display
Category Minimum Recommended
Resolution 1920 × 1080 (Full HD) 2560 × 1440 on a 30-inch Ultrawide Display
Screen width 1200 pixels 1600 pixels
Screen height 1024 pixels Not Specified
Operating System and Browser Support
Note:
Keep supported browsers up to date.
A 64-bit Operating System is required.
Supported Not Supported
Windows 10 or later, macOS 10.12 or later Linux
Google Chrome, Microsoft Edge Apple Safari, Mozilla Firefox, Microsoft Edge (not based on Chromium), Microsoft Internet Explorer https://support.skydio.com/hc/article_attachments/49656765459867
Skydio Dock for X10 Site Readiness Manual | Page 19
DFR Command Operator Suggested Equipment List
For a DFR Command Operator, Skydio suggests the following equipment:
• A PC meeting all system requirements
• Monitor
• Monitor Stand
• Lighting
• Temp Keyboard
• Chairs
• Desk
Optional Accessories
• Desk Phone
• Walkie Talkie
© 2026 Skydio, Inc. All rights reserved. Proprietary. Printed copies are uncontrolled.
https://www.amazon.com/dp/B0C48D7Q22?ref=fed_asin_title&th=1 https://www.amazon.com/Govee-H6047-Controller-Specially-Assistant/dp/B0B6CQ2LQ2/ref=asc_df_B0B6CQ2LQ2?mcid=49072767fdb533f2b1afc326d6063bef&hvocijid=14498694276282458603-B0B6CQ2LQ2-&hvexpln=73&tag=hyprod-20&linkCode=df0&hvadid=721245378154&hvpos=&hvnetw=g&hvrand=14498694276282458603&hvpone=&hvptwo=&hvqmt=&hvdev=c&hvdvcmdl=&hvlocint=&hvlocphy=9208144&hvtargid=pla-2281435180218&th=1 https://a.co/d/coYFG4e https://secretlab.co/pages/titan-evo-2022-series https://www.amazon.com/AT-ML17929-2-Line-Corded-Telephone/dp/B007P8DKZ2/ref=sr_1_6?dib=eyJ2IjoiMSJ9.PO3QgZeDUJpWsOx4QLKp9OdffW8Bz12QF31jzye7HspcraoQIHTROjsRYM1Not7XIhU8tKFbsXK_kDBzdOW8Lbig7vydCkOFBu20q2aFHoU9VE1MpNNAILy5apNzhrGWfDQWJ1v162h-Aox5SSHCj6LBThlYzO8z0qAic51Uhbxq4UPYsdyDXZarnGHONo5k4thMlj5lcvkE8TpCpV3uGePZgJAo1ZYbUlvIVV5UacA.4yHRSjE-iSzsZR1wWRwHo-mkIk3e2gnVjVRMb4cUxYg&dib_tag=se&keywords=Desk%2Bphone&qid=1741905502&sr=8-6&th=1 https://www.amazon.com/pxton-Rechargeable-400-470Mhz-Transceiver-Flashlight/dp/B08HK5SXH1/ref=sr_1_7?crid=ULCPBOWPJTW2&dib=eyJ2IjoiMSJ9.ooLFMotY_bQATsTClabi9Vpd-8g3H4qFoNcGd5ATkRvAUw6vbYx-0DtoB92NtmVxqrUrLUAuxALM-xyIKS3ohuM-hhAIFHvcipj-MOxTHVwPJdkyx_5O9JWHGh7YzRvaXzhxcKGl1LEyOpN6xHqRQr4g9Bpo5QMfJjA_kC7uUulIrrreBx7vUt89bCSJk-uGMtPcEG9klYiZhUseboyJqt0XJUeyrZ7IhC-ZttCt-JQX_vy1-61oZfhPLuWiSCOT0u3PHzEIxm5vSZWJ5ZDbrih6VwpgjmtRvfqSwdmzcM7tVsjKFmoJsLp1x9SjfLYCENQm6-0cSK6K_G1CrBnSOtXPG8Jx3mr5JBEfM7aTkhw.PsvRvOw6hD1wGxMdhaagcnzL95jA4v9zWBN5XLkdMxU&dib_tag=se&keywords=walkie+talkie+radio+with+stand&qid=1741905971&s=electronics&sprefix=walkie+talkie+radio+with+stan%2Celectronics%2C192&sr=1-7
Skydio Dock for X10 Site Readiness Manual | Page 20
Installation Requirements
DANGER:
Improper installation or configuration of the Dock for X10. Improper installation or configuration of the Dock for X10 will result in equipment damage, serious injury, or death. For every Dock for X10 installation location, including connectivity and Radio Frequency (RF) mapping, final placement and installation requirements must be determined through a Skydio Site Survey.
Transport and Delivery
Customer Transportation Responsibilities
The Customer is responsible for transporting the Skydio Dock from the shipment destination to the final installation site. Transport may require lifting or craning the pallet to a rooftop or elevated location, depending on site conditions.
WARNING:
Transportation pallet tip hazard. Do not remove the Dock from its shipping pallet until it has reached the designated final installation location. While operating lift equipment, wear appropriate PPE.
To transport, do the following:
• Lift of hoist the Dock in the packaging by crane or telescopic handler.
• If a crane or forklift are not available, separate the Dock into 3x major assemblies for other logistical solutions.
Shipping Information
Type Specification / Requirement
Shipping Dimensions 40 in x 48 in x 58 in (101.6 cm x 121.9 cm x 147.3 cm) Pallet
Total Shipping Weight ~300 to 360 lbs (136.1 to 163.3 kg)
Skydio Dock for X10 Site Readiness Manual | Page 21
Skydio Installation and Validation
Note:
Skydio Authorized Technicians and Field Services teams will perform system assembly and installation, validation testing, RF analysis, connectivity mapping, and system activation.
Skydio Dock for X10 Site Readiness Manual | Page 22
Dock Installation Requirements
DANGER:
Improper installation or configuration of the Dock for X10. Improper installation or configuration of the Dock for X10 will result in equipment damage, serious injury, or death. For every Dock for X10 installation location, including connectivity and Radio Frequency (RF) mapping, final placement and installation requirements must be determined through a Skydio Site Survey.
Layout and Clearance
Obstacle Clearance
The Dock requires an open field of view to the sky within a 15 ft (4.6 m) radius of the dock center point. Inside this zone, any obstacle taller than the dock (ex. fence, wall, building, light pole, or overhanging tree) must be positioned so that its horizontal distance from the dock is at least 1.2 x the obstacle's height (H). Obstacles beyond the 15 ft radius are not restricted. GPS-transparent objects (ex. thin bridges, poles, or towers that do not block the sky view) are exempt.
To support Drone operation and unobstructed approach paths, maintain the following clearances:
• Ensure no tall obstacles are present within a 15 ft (4.6 m) radius surrounding each Dock set.
• Maintain a clear line of sight above and around each Dock.
Obstacle Height 1.2 x H Field Minimum Distance
3.0 ft (0.9 m) 3.6 ft (1.1 m) 4.0 ft (1.2 m)
4.0 ft (1.2 m) 4.8 ft (1.5 m) 5.0 ft (1.5 m)
5.0 ft (1.5 m) 6.0 ft (1.8 m) 6.0 ft (1.8 m)
6.0 ft (1.8 m) 7.2 ft (2.2 m) 8.0 ft (2.4 m)
7.0 ft (2.1 m) 8.4 ft (2.6 m) 9.0 ft (2.7 m)
8.0 ft (2.4 m) 9.6 ft (2.9 m) 10.0 ft (3.0 m)
9.0 ft (2.7 m) 10.8 ft (3.3 m) 11.0 ft (3.4 m)
10.0 ft (3.0 m) 12.0 ft (3.7 m) 12.0 ft (3.7 m)
11.0 ft (3.4 m) 13.2 ft (4.0 m) 14.0 ft (4.3 m)
12.0 ft (3.7 m) 14.4 ft (4.4 m) 15.0 ft (4.6 m)
For Dock Hive information, see: Multiple Docks (Hive) (on page 31)
GNSS Considerations
For the Global Navigation Satellite System (GNSS), note the following:
• Transparent objects are permissible (ex., poles, trees, nets, or items which usually do not fully block GNSS signals). To avoid these violations, users should ensure to set a return height.
• For non-transparent objects, Skydio uses a GPS Survey Tool and may need to consult with internal engineers to determine if the item is permissible to mitigate risk of reduced landing reliability.
Skydio Dock for X10 Site Readiness Manual | Page 23
Approach and Landing
When a Drone is approaching or landing at a Dock, the following conditions apply:
• To detect a Dock during descent, the Drone must descend within 12 ft (3.7 m) above the Dock.
Note:
Obstacle Avoidance (OA) may be deactivated.
• Drone GPS may be inaccurate by a few meters.
• A clear line of sight to the Dock must be maintained.
Note:
This clearance accounts for potential wind, gusts, estimation errors, or control deviations.
Roof Rotation and Space Considerations
To prevent obstruction or damage during roof movement, observe the following:
• For Roof rotation, allow adequate space behind each Skydio Dock.
• The Roof rotates 6.0 in (15.2 cm) above the base of the Dock; ensure no obstructions exist within this rotation zone.
Mounting and Structural Requirements
Note:
Dock for X10 may be freestanding or bolted onto a permanent structure. It is the Customer's sole responsibility to provide permanent mounting of the Dock System and External Radio.
Skydio Dock for X10 Site Readiness Manual | Page 24
Mounting Method
The following mounting methods explain how to secure the Skydio Dock to an installation surface:
Recommended: Secure the Skydio Dock by bolting it to an accessible permanent structure, such as a concrete pad when installing on the ground. The Dock for X10 is approximately 3.1 ft x 2.8 ft and requires a minimum pad size of 4 ft. x 4 ft. x 6 in. (1.2 m x 1.2 m x 15.24 cm).
Note:
Refer to the bolting layout diagram for specific bolt placement.
Pad Dimensions
Alternative Options:
• For installations where bolting is not feasible, the Dock may be mounted using four leveling feet (non-bolted configuration).
• For a roof constructed with soft or non-structural materials, construct a standing platform with the following minimum dimensions: 40 in x 36 in x 4 in (101.6 cm x 91.4 cm x 10.2 cm).
Note:
To ensure proper stability and load distribution, mount the Dock to the standing platform.
Leveling and Surface Requirements
The following requirements apply to leveling and surface preparation:
Skydio Dock for X10 Site Readiness Manual | Page 25
• To ensure proper Dock operation and aircraft landing accuracy, the landing surface must be maintained within ±3° of level.
• Verify level alignment after installation and during periodic maintenance checks.
Dock Feet Guidance
If Dock Feet are required, see the following information:
Category Specification / Requirement
Material Steel (painted, holes for paint/hanging only)
Weight (per "foot") ~18 lbs (8.2 kg)
Total Added Weight ~72 lbs (32.7 kg) Across All 4x Dock Feet
Surface Grip Dock Feet Underside Use Grip Tape Placed on a Rubber Utility Mat Adhered With Tape
Survival Wind Rating • Without Dock Feet (Un-anchored Dock): ~40 mph (54.7 to 64.3 km/h)
• With Dock Feet + Utility Mat: ~80 mph (128.7 km/h)
• Bolted Dock: > 80 mph (128.7 km/h) Up to 160 mph (257 km/h)
Anchor Bolt and Thread Specifications
WARNING:
Improper structural installation or inadequate anchoring. Structural failure under wind loading may result in equipment damage, falling components, or serious injury. For higher wind exposures (C/D) or other elevated load conditions, use engineered mounts or increase anchoring in accordance with applicable code requirements. Validate installation with a licensed structural engineer.
The following specifications apply to all bolt and thread installations:
Mounting Category Fastener
Concrete Pad Steel Wedge Anchor for Concrete
3/8 in -16 x 3 in (M10-1.5 x 75 mm) (McMaster: 91578A823)
Other Structures High-Strength Grade 8 Steel Hex Head Screws
3/8 in -16 x 2 in (M10-1.5 x 75 mm) (McMaster: 97753A137)
Ensure thread exposure above grade meets the following limits:
• Minimum: 1.0 in (25 mm)
• Maximum: 2-3/8 in (6.0 mm)
Use the following diagram for the following:
• Anchor bolt location requirements
• Precise hole spacing
• Bolting pattern
Skydio Dock for X10 Site Readiness Manual | Page 26
Dock Grounding Requirements
The Dock for X10 is grounded via the electrical system and power supply connections during installation.
Skydio Dock for X10 Site Readiness Manual | Page 27
External Radio Installation Requirements For the External Radio, note the following:
• Failure to provide dedicated External Radios may cause communication loss between Docks and the network.
• Each Dock requires 1x External Radio to maintain reliable connectivity and full system performance.
• To avoid any signal loss, ensure the maximum distance between the Dock and External Radio is 100 m.
Distance Between External Radio and Dock / Multiple Radios
Skydio Dock for X10 Site Readiness Manual | Page 28
Mounting Options
WARNING:
Improper structural installation or inadequate anchoring. Structural failure under wind loading may result in equipment damage, falling components, or serious injury. For higher wind exposures (C/D) or other elevated load conditions, use engineered mounts or increase anchoring in accordance with applicable code requirements. Validate installation with a licensed structural engineer.
Improper mounting may result in movement, instability, or loss of communication during operation.
The External Radio may be mounted using one of the following options:
• A Customer-provided pole
• A Freestanding Mount provided by Skydio
Note:
To prevent shifting or tipping when using the Skydio Freestanding Mount, the Customer must secure it with sandbags or 8x cinder blocks 4" x 8" x 16" blocks (~256 lbs).
Mount Type Pole OD Antenna Set Ballast (Cinder Blocks)
Target Wind Rating
Assumptions
Banda-clamped to engineered pole
2 to 4 in Patch or Yagi pair
0 130 mph (209 km/h)
Retention on pole only; pole and anchors engineered to site wind
(ASCE 7)
Non-penetrating ballasted stand
2 to 3 in Patch or Yagi pair
8 80 mph (128 km/h)
Exposure B; standard 4" x 8" x 16" blocks; correct clamp install
External Radio Grounding Requirements
WARNING:
Electrical hazard. Improper grounding can result in electric shock, fire, equipment damage, serious injury, or death. All grounding work must be performed by a qualified electrician in accordance with local codes.
To ensure electrical safety and system stability, the following grounding requirements apply:
• Utility Use Cases: Grounding is recommended using grounding straps or cables attached to the Dock and External Radio.
• All Other Use Cases: Grounding is recommended for improved electrical safety and system stability.
Skydio Authorized Technicians will install a grounding strap between the external radio and the mounting pole.
If using the provided non-penetrating sled, provisions must be made to ground the sled using a conductive fastener or securing the grounding wire between one of the fasteners in the assembly. If using a non-conductive pole, provisions must be made to connect a grounding wire to the lug of the grounding strap fastened to the pole.
Placement and Line of Sight
Poor placement may reduce signal quality and interrupt Drone-to-Dock communication.
Follow these placement guidelines:
Skydio Dock for X10 Site Readiness Manual | Page 29
• For optimal line-of-sight, install the External Radio at the highest point of the roof.
• To maintain clear line of sight in all directions, if no elevated location is available, ensure the mounting pole extends at least 10 ft (3.0 m) above all roof structures.
Mounting Hardware and Stability
Using undersized or unstable supports may cause mount failure in severe weather.
To ensure long-term structural integrity:
• Use a steel mounting pipe with an outer diameter between 2 in to 6 in (5.1 to 15.2 cm).
• Permanently fix the pipe to a structural surface capable of withstanding environmental loads.
• Confirm the assembly remains stable under all expected weather conditions.
Network Cabling
CAUTION:
Improper installation, routing, or excessive length of Cat6 network cables. Improper cabling may result in degraded data transfer rates and reduced communication reliability. Do not exceed recommended cable length limit. Avoid kinking, sharp bends, or placing excess weight on Cat6 network cables.
Meet the following requirements for cabling:
• Use a Customer-provided shielded Cat6 or Cat6A Ethernet cable from the base of the External Radio to the Dock accessory port (or to open internet).
• The cable must be outdoor-rated and shielded, and should be encased in conduit where possible.
• Limit total cable length to less than 328 ft (100.0 m) between the External Radio and Dock.
Final Position Verification
Unverified locations may result in poor RF performance or obstruction interference. All final radio and dock locations must be verified through the Skydio Pre-Site Survey before installation.
Category Specification / Requirement
Horizontal distance between External Radio and Dock Minimum: 17 ft (5.2 m)
Horizontal distance between two or more External Radios Minimum: 17 ft (5.2 m)
Vertical distance between two External Radios mounted to the same pole (from tip-to-tip of the antennas)
Minimum: 18 in (45.7 cm)
Recommended: 36 in (91.4 cm)
Skydio Dock for X10 Site Readiness Manual | Page 30
Category Specification / Requirement
Mounting height and location Loss of signal or reduced range will occur if the external radio's line of sight is obstructed.
To maintain full communication range, observe the following requirements:
• Obstructions will limit the range of Skydio Connect SL in the direction of the blockage.
• The External Radio must maintain an unobstructed line of sight (with added margin for wave spread-out) to the horizon in all directions.
• To prevent interference with the Drone's line-of-sight, he External Radio must be installed at least 5.0 ft (1.5 m) above any walls or roof obstructions.
Skydio Dock for X10 Site Readiness Manual | Page 31
Multiple Docks (Hive)
WARNING:
Improper installation or operation of multiple Skydio Dock for X10 units. Improper installation or operation may result in significant equipment or property damage, severe injury, or death. Follow all safety, electrical, and operational requirements for the installation and operation of multiple Skydio Dock for X10 units.
Hive Layout and Clearance
A Hive is a group of 2 to 6 Docks installed in the same location. When installing a Hive, ensure the following:
• Maintain a minimum of 5.0 ft (1.5 m) between each Dock, side-by-side.
• Maintain a minimum of 15 ft (4.6 m) of clearance around each set of Docks for safe operation and flight maneuvering.
• Provide a 4 ft x 4 ft (1.22 m × 1.22 m) square space nearby as an alternative safe landing zone.
• Final locations to be determined during Skydio Site Survey.
Skydio Dock for X10 Site Readiness Manual | Page 32
Appendixes
Corrosion Guidance Dock for X10 is designed and tested to operate in coastal regions, outside of direct saltwater splash zones.
With the standard Maintenance and Repair package for Dock, Skydio Service Representatives will conduct maintenance and repair visits in order to keep Dock for X10 operational.
Corrosive environments will cause cosmetic degradation and may also result in functional degradation.
Functional degradation can be corrected by replacing corroded components, which is covered under the Dock for X10 Maintenance and Repair package, so long as the deployment is not in an area of direct saltwater exposure. Cosmetic degradation is, however, not covered under the Maintenance and Repair package.
To reduce the likelihood of functional and cosmetic degradation due to corrosion, Skydio recommends that the Dock for X10 be installed at least 200 m from coastline. Deployments inside of 200 m but outside of saltwater splash zones will not void the warranty.
Installation in direct saltwater splash-zones will void the 1-Year Limited Warranty and may result in repairs that are not covered under the Dock for X10 Maintenance and Repair package.
Safety Information
DANGER:
Improper installation or configuration of the Dock for X10. Improper installation or configuration of the Dock for X10 will result in equipment damage, serious injury, or death. For every Dock for X10 installation location, including connectivity and Radio Frequency (RF) mapping, final placement and installation requirements must be determined through a Skydio Site Survey.
DANGER:
Electrical hazard. Exposure to energized components can result in serious injury or death. Follow local/site specific lockout/tagout procedures for de-energizing the Dock and removing electrical hazards. Ensure the work area is clear of unnecessary personnel. If necessary, restrict access to the area.
Before performing service on the unit, do the following:
• Engage the Dock E-Stop button.
• Turn the Dock OFF.
• Disconnect the Dock from the AC power supply.
• Disconnect all external data and power cables from the Dock.
• Complete required lockout/tagout procedures per site requirements.
WARNING:
Ice accumulation when operating below 32°F (0°C) without a 200V-240V power supply. When operating below 32°F (0°C) without a 200V-240V power supply, Dock Heater functionality will be unavailable. Ice accumulation can result in degraded performance, crashes, or loss of the aircraft. For operation below 32°F (0°C), a 200V-240V power supply from a dedicated 20A breaker must be provided to enable Dock Heater functionality. Provide a 100V-120V power supply from a dedicated 15A breaker for operation in temperatures from 32°F (0°C) to 122°F (50°C).
Skydio Dock for X10 Site Readiness Manual | Page 33
WARNING:
Improper installation or operation of multiple Skydio Dock for X10 units. Improper installation or operation may result in significant equipment or property damage, severe injury, or death. Follow all safety, electrical, and operational requirements for the installation and operation of multiple Skydio Dock for X10 units.
WARNING:
Improper structural installation or inadequate anchoring. Structural failure under wind loading may result in equipment damage, falling components, or serious injury. For higher wind exposures (C/D) or other elevated load conditions, use engineered mounts or increase anchoring in accordance with applicable code requirements. Validate installation with a licensed structural engineer.
WARNING:
Transportation pallet tip hazard. Do not remove the Dock from its shipping pallet until it has reached the designated final installation location. While operating lift equipment, wear appropriate PPE.
CAUTION:
Improper installation, routing, or excessive length of Cat6 network cables. Improper cabling may result in degraded data transfer rates and reduced communication reliability. Do not exceed recommended cable length limit. Avoid kinking, sharp bends, or placing excess weight on Cat6 network cables.
NOTICE:
Customer Responsibilities. Skydio will provide Skydio Dock for X10 and External Radio hardware only.
The Customer is solely responsible for providing all infrastructure required for operation, including but not limited to:
• Power
• Electrical work
• Networking
• Wiring between Docks
• Installing protective conduit to encase cable runs
• Mounting
• Site preparation
Skydio assumes no responsibility or liability for any Customer-performed or Customer-provided infrastructure.
Skydio Dock for X10 Site Readiness Manual | Page 34
Revision History
Revision Description Date
1 Initial Release May 7, 2026
2 Updated layout. Removed Operating Environment sections. May 8, 2026
Skydio Dock for X10 Site Readiness Manual
| Site Readiness Manual |
| Dock Specifications |
| Technical Specifications |
| Operating Limits |
| Weights and Dimensions |
| Weights |
| Dimensions |
| Materials |
| External Radio Specifications |
| Technical Specifications |
| Operating Limits |
| Weights and Dimensions |
| Weights |
| Dimensions |
| Site Preparation |
| Dock Power Requirements |
| Power Connection Options |
| External Radio Power Requirements |
| Wiring Configuration |
| Hardwired and Conduit Requirements |
| Ethernet Cable Requirements |
| When to Consider CAT6A |
| Computer System Requirements |
| Remote Flight Deck/DFR Command System Requirements |
| Installation Requirements |
| Transport and Delivery |
| Customer Transportation Responsibilities |
| Shipping Information |
| Skydio Installation and Validation |
| Dock Installation Requirements |
| Obstacle Clearance |
| GNSS Considerations |
| Approach and Landing |
| Roof Rotation and Space Considerations |
| Mounting Method |
| Leveling and Surface Requirements |
| Dock Feet Guidance |
| Anchor Bolt and Thread Specifications |
| Dock Grounding Requirements |
| External Radio Installation Requirements |
| Mounting Options |
| External Radio Grounding Requirements |
| Placement and Line of Sight |
| Mounting Hardware and Stability |
| Network Cabling |
| Final Position Verification |
| Multiple Docks (Hive) |
| Hive Layout and Clearance |
| Appendixes |
| Corrosion Guidance |
| Safety Information |
Revision History
File details come from the government source that posted it. Updated .