1ST TATICAL THEATER SIGNAL BRIGADE

Facility/Site Power Coordinator Evaluation Report for S242 HMP TCF ADN Camp

Humphreys, South Korea

14 June 2018 – 15 June 2018

Prepared by:

1TTSB/S4 Engineering Brigade Power Coordinator

Unclassified/FOUO

MEMORANDUM FOR THE COMMANDER 22 June 2018

SUBJECT: Facility/Site Power Coordinator Evaluation Report for HMP TCF ADN

Camp Humphreys, South Korea

Reference: (a) NETCOM Regulation 420-1 Facility Engineering Site Power

Coordinator Program, 27 September 2010

1 Overview

The Brigade Power Coordinator Evaluation Team from 1TTSB/S4 Engineering conducted an evaluation of HMP TCF ADN S242 Camp Humphreys. This facility is operated and maintained by personnel of the 501st Signal Company, 41st Signal Battalion, 1st Tactical Theater Signal Brigade. This evaluation was conducted in accordance with reference (a) to determine the facility's readiness in sustaining its mission. This is accomplished by identifying deficiencies, items, and comments that affect current and future operations of the facility. The evaluation was conducted at HMP TCF ADN, 14 June - 15 June 2018.

1.1 Site Overview

Figure 1: Building Layout

Figure 2: TCG Rm2 and Battery Rm Floor Layout

Figure 3: TCG Rm3 Floor Layout

1.2 These categories are defined below:

1.2.1 Deficiencies: Problems that have resulted or will result in an operational impact to the mission and require immediate corrective action. May be beyond the capability of the site or facility to correct.

1.2.2 Item: An item that was documented during a subsequent audit and still exists without sufficient action.

1.2.3 Comments: Observations, either favorable or unfavorable, that warrant mentioning. Recommendations to improve the facility.

2 Site Power Coordinator Program

2.1 Deficiencies: (3)

2.1.1 Site Power Coordinator not appointed. The 41st needs to nominate a replacement for SSG Radouane Moukraj, IAW NETCOM 420-1 9. Estimated time to complete: 15 days.

2.1.2 Replacement needs to be trained in Electrical Safety (S4 to offer monthly electrical safety beginning in July) and emergency response (unit responsibility), NETCOM 420-1 11. Estimated time to complete: 60 days.

2.1.3 Site Power Coordinator Program mandates SOP be present onsite to deal with emergencies IAW NETCOM 420-1 18.a. If site power fails and DC batteries run out of energy (concurrent failure), then it would take an emergency work order to DPW to bring the site’s power back online. This could leave the site without power for an indeterminate time. This is not in line with service level agreements and mission. Estimated time to complete: 180 days.

2.2 Items: (0)

2.2.1 None Noted.

2.3 Observations & Comments: (3)

2.3.1 None Noted

3 Primary Power & Auxiliary Power Systems

This facility is energized the power from exterior pad mounted 225KVA transformer via 800A rating CUMMINS ATS. The ATS is connected to 250 KVA CUMMINS generators via another CUMMINS ATS. The facility also has a DC SAGEON power inverter with batteries which is supplying the DC power to the transport equipment.

The 2 x 250 KVA Cummins generators are installed to supply as an emergency power source. If normal power fails or the supply voltage drops below acceptable level, both generators run. When one of generators reach an acceptable voltage and frequency, that generator is selected by ATS1, installed between two generators. This generator will supply emergency power to the facility through ATS2 which is installed between ATS1 and main enclosure circuit breaker. These generators are connected to a 550 gallon fuel tank filled with approximately 400 gallons.

Figure 4: Cummins 250KVA Generators

3.1 Deficiencies: (1)

3.1.1 No regular generator exercising/testing. The site’s generators have not be serviced since takeover. This is a simple DPW work order to be completed by facility manager. NETCOM 420-1 9.d.(1). The Site NCOIC or Site Power Coordinator to submit FEWR to Building Manager and track DPW Maintenance.

DPW should perform the maintenance. Estimated time to complete: 30 days.

3.2 Items: (0)

3.2.1 None Noted.

3.3 Observations & Comments: (1)

3.3.1 The BPC team didn’t performed a generator readiness test on both generators, the test should be performed following maintenance.

4 Power Distribution

There are several electrical panel boards receiving electrical power from ATS2 via Power Distribute Block in the ATS. The power system for transport racks is configured to send SAGEON DC converter (50 Amps x 20/24EA rating) via panel board “MP.”

Some equipment is configured to receive AC power from rack mounted converter or building AC system. There are 4 rows of racks consuming less than AC 100 amps.

There are 5 deficiencies and 3 comments.

4.1 Deficiencies: (5)

4.1.1 The abandoned cables and unsecured wires were observed on the cable tray during the audit. The National Electrical Code is very directive concerning accessible abandon cabling and its impacts to LHS. Recommend the 41st installers secure these cables with proper materials or remove them and mark for future use. Anticipated completion 30 days from report acceptance.

Figure 5: Abandoned Cables and Unsecured wires

4.1.2 Some electrical panels were installed without regard for the working space requirements outlined in NEC Article 110.26. Recommend the relocation of existing obstacles in front of panel boards. The site NCOIC or Site Power Coordinator should coordinate with the site technical staff to remove or relocate items. Anticipated completion 90 days from report acceptance.

Abandoned cables

Unsecured wires

Figure 6: Narrow Working Space

4.1.3 The panel board “TPP-G” is energized the power from 3P 175AT/175AF circuit breaker in the MP panel board. However, the 3P 225AT/225AF main breaker size of PNL “TPP-G” is observed during the audit. IAW NEC 215.3 Overcurrent Protection or 240.4 Protection of Conductors. Conductors shall be protected against overcurrent in accordance with their ampacities specified in 310.15, unless permitted or required in 240.4 (A) through (G). Overcurrent protection sizing has 1) either not be done properly 2) been overlooked. This configuration potentially create unnecessary fire risks. Recommend DPW or 41st installation team correct the situation. The site NCOIC or Site Power Coordinator shall determine whether a FEWR or other means can remedy the situation.

Anticipated completion 180 days from report acceptance due to potential ASI.

Narrow Working Space

Figure 7: Large Size Downstream Circuit Breaker

4.1.4 Unnecessary bonding jumper in the “MP” panel board connected to the neutral was found during the audit. If left uncorrected, there is parallel path for neutral current creating LHS issues in the case of a potential fault. The neutral conductor shall not be connected to normally non-concurrent-carrying metal parts of equipment IAW NEC article 250.24(A) (5). Recommend DPW assess the situation and correct. The site NCOIC or Site Power Coordinator shall submit FEWR to building manager, track DPW maintenance, and maintain copies of results. Anticipated completion 90 days from report acceptance.

Figure 8: Unnecessary Bonding Jumper

MP TPP-G

4.1.5 Total 6 emergency lights and 1 exit lighting fixture are not operated properly. If left unrepair, this condition will increase risk to personnel in an emergency situation. Additionally, exit lighting fixtures are required IAW building S242 fire evacuation plan. Recommend DPW assess the situation and correct. The site NCOIC or Site Power Coordinator shall submit FEWR to building manager, track DPW maintenance, and maintain copies of actions. Anticipated completion 90 days from report acceptance.

Figure 9: Inoperable EXIT Light & EM lighting fixtures

Figure 10: Building Fire Evacuation Plan

4.2 Items: (0)

4.2.1 None noted.

4.3 Observations & Comments: (3)

4.3.1 Measured power consumption of building was documented. The site is using 35% of capacity. Generator load condition is acceptable.

Figure 11: Ampere Readout ATS #2

4.3.2 Measured power consumption of SAGEON board was documented.

Figure 12: Ampere Readout SAGEON

Figure 57: Battery Status

Figure 58: Battery Room Temperature

Figure 59: SAGEON Status

Figure 60: SAGEON Distribution List #1

Figure 61: SAGEON Distribution List #2

Figure 62: SAGEON Distribution List #3

6 HVAC

The TCF has 18 air conditioner supply in the facility. The condition of the ACUs are in an okay, but these equipment have 2 deficiencies, 1 comment.

Figure 63: A/C Unit Location

6.1 Deficiencies: (2)

6.1.1 The condensation water was observed from ceiling air diffuser. If left unrepaired, this condition could damage rack equipment and induce other significant issues.

Recommend DPW come determine if the situation needs to be corrected. The site NCOIC or Site Power Coordinator shall submit FEWR to building manager, track DPW maintenance, and maintain copies of results. Anticipated completion 90 days from report acceptance.

Figure 64: Temporary Protection from Condensation Water

6.1.2 The AC-18 outdoor unit was not operated properly showing signs of damaged flexible conduit. Recommend contractor come determine if the outdoor unit needs to be correct. The HVAC system should be operated and maintained IAW NETCOM 420-1 9. D. (2). Anticipated completion 90 days from report acceptance.

Temporary protection work from condensation water

Figure 65: Inoperable equipment & Damaged Flexible Conduit

6.2 Items: (0)

6.2.1 None noted.

6.3 Observations & Comments: (1)

6.3.1 Labeling of ACUs (indoor and outdoor) are inconsistent. Sticker does not match the contractor labeling and panel board labeling. Labeling shall be marked IAW NEC 110.22. Site NCOIC or Site power coordinator. Anticipated completion 30

7 Earth Grounding System & Bonding

Description: There are no damaged conductors in the ground test wells which are located at the adjacent of facility. The facility has one anticorrosive busbars. There are 3 deficiencies and 1 comment.

7.1 Deficiencies: (3)

7.1.1 No anticorrosive on Secondary Bonding Busbar (SBB). TIA-607C 7.2.1, 7.3.1 &

7.4.1, 1st paragraph. The busbar shall be cleaned and an anti-oxidant should be applied prior to fastening connectors to the busbar. Site NCOIC or Site Power Coordinator. Anticipated completion 90 days from report acceptance.

Figure 66: Bldg. SBB & Improper lugs and connector

7.1.2 One-hole lugs were observed on the SBB. According to TIA 607-C 7.2.3, the connection to the SBB should be used with two hole lugs. Site NCOIC or Site Power Coordinator. Anticipated completion 180 days from report acceptance.

One-hole lugs

Split bolt connector

SBB

7.1.3 Improper bonding conductor connection were observed on the various location.

The connections to the Telecommunication Equipment Bonding Conductor (TEBC) shall be made with listed irreversible compression connectors IAW TIA 607-C section 7.5.8.1. Anticipated completion 180 days from report acceptance.

7.2 Items: (0)

7.2.1 None noted.

7.3 Observations & Comments: (1)

7.3.1 No recent EGS or bonding testing available for viewing. S4 lacks the Megger to inspect resistances between bonds and coupling. NETCOM 420-1 23.a.(4).

Grounding systems installed in accordance with MIL-STD-l88-l24 and MIL- HDBK-4l9 are properly maintained. DPW should preform ground ring testing every 21 Months per NETCOM 420-1 (TM 5-690 Chapter 7 – testing should occur 24 mo.) and provide results to unit. The Site NCOIC or Site Power Coordinator shall submit FEWR to Building Manager, track DPW Maintenance, & maintain copies of tests. Anticipated completion 180 days from report acceptance.

8 Fire Suppression System (FSS)

Description: The condition of the fire suppression system are in an okay condition, but there are 3 deficiencies and 1 comment.

8.1 Deficiencies: (3)

8.1.1 An empty fire extinguisher point was observed. The fire extinguisher shall be located on the designated place for emergency situation. To prevent fire extinguishers from being moved or damaged, they should be mounted on brackets or in wall cabinets with the carrying handle placed 3-1/2 to 5 feet above the floor IAW NFPA 10 section 6.6. Site NCOIC or Site Power Coordinator should work with facility manager to correct. Anticipated completion 30 days from report acceptance.

Figure 67: Empty Fire Extinguisher

8.1.2 Improper wall penetration for telecommunication wires were observed on the various location. The telecommunication cables shall be secured with proper materials such as conduit or cable tray. Additionally, telecommunication room or space shall be separated from other occupancies within the building by fire-resistance-rated construction IAW NFPA 76 section 8.3. Site NCOIC or Site Power Coordinator request to 41st installation team. Anticipated completion 90

Figure 68: Improper Wall Penetration

8.1.3 Improper cable tray wall penetration for telecommunication wires were observed on the various location. The telecommunication room shall be separated from other occupancies within the building by fire-resistance-rated construction IAW NFPA 76 section 8.3. Recommend that follow the detail for wall penetration as below. Site NCOIC or Site Power Coordinator. Anticipated completion 90 days from report acceptance.

Figure 69: Improper Cable Tray Penetration

8.2 Items: (0)

8.2.1 None noted.

8.3 Observations & Comments: (1)

8.3.1 No recent testing available for viewing. NETCOM 420-1 25. Fire protection systems may vary from simple hand held fire extinguishers to sophisticated installed water or chemical extinguishing systems. All systems require periodic testing or inspection, usually on an annual basis or as stated below in table 1.

DPW is to preform FSS testing. Site NCOIC or Site Power Coordinator shall submit FEWR to Building Manager, track DPW maintenance, and maintain copies of tests.

9 Description: Facility/Site Power Coordinator Evaluation Team consisted of the following individuals:

Joe Dubinsky, Project Management Professional, NPFA 70E Qualified, 1TTSB Site Power Coordinator, Electrical/Facility Engineer

Mr. Chi Yong Chon, Project Management Professional, Certified Information Systems Security Professional, 1TTSB/S4 Engineering, Electronics Engineer

Mr. Jin Hur, Professional Engineer, 1TTSB Engineering, Electrical Engineer

The 1TTSB/S4 Engineering Team wish to express their gratitude for the assistance provided by the personnel of the Camp Humphreys.

JOSEPH G. DUBINSKY

Brigade Power Coordinator joseph.g.dubinsky.civ@mail.mil

DSN: 315-755-0882