AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0003 w ill provide questions and answ ers from the Aberdeen Test Center (ATC) site visit held 06 January 2021 - see items highlighted in yellow .
The Period of Performance for this follow -on contract is also being changed to 01 May 2021 - 30 April 2024.
Furthermore, the due date for proposals is herby extended through 20 January 2021 at 1000 EST.
1. CONTRACT ID CODE PAGE OF PAGES
Y 1 19
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91CRB21T0002
X 9B. DATED (SEE ITEM 11)
22-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0003
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Jan-2021
CODE
ACC - APG - W91CRB
BLDG 4310
6515 INTEGRITY COURT
ABERDEEN PROVING GROUND MD 21005-3013
W91CRB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91CRB21T0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 15-Jan-2021 10:00 AM to 20-Jan-2021 10:00 AM.
SUPPLIES OR SERVICES AND PRICES
CLIN 0007
The CLIN description has changed from Contractor Manpower Reporting to REMOVED Contractor Manpower Reporting.
The CLIN extended description has changed from:
To include all Manpower Reporting for Option Year 2Months 25 through 36NOT SEPARATELY PRICEDAccounting for Contract ServicesContractor is required to provide data on contractor manpower (includingsubcontractor manpower) for performance of this contract. Instructions, including the Contractor and Subcontractor User Guides, are available at the CMRA (Contractor Manpower Reporting Application) website at https://cmra.army.mil. For further assistance, email the CMRA Help Desk atcontractormanpower@hqda.army.mil.
To:
This CLIN will NOT BE INCLUDED in the contract award. No longer applicable. Please disregard. Accounting for Contract ServicesContractor is required to provide data on contractor manpower (includingsubcontractor manpower) for performance of this contract. Instructions, including the Contractor and Subcontractor User Guides, are available at the CMRA (Contractor Manpower Reporting Application) website at https://cmra.army.mil. For further assistance, email the CMRA Help Desk atcontractormanpower@hqda.army.mil.
CLIN 0011
The CLIN description has changed from Contractor Manpower Reporting to REMOVED: Contractor Manpower Reporting.
The CLIN extended description has changed from:
To include all Manpower Reporting for Option Year 2Months 25 through 36NOT SEPARATELY PRICEDAccounting for Contract ServicesContractor is required to provide data on contractor manpower (includingsubcontractor manpower) for performance of this contract. Instructions, including the Contractor and Subcontractor User Guides, are available at the CMRA (Contractor Manpower Reporting Application) website at https://cmra.army.mil. For further assistance, email the CMRA Help Desk atcontractormanpower@hqda.army.mil.
This CLIN will NOT BE INCLUDED in the contract award. No longer applicable. Please disregard.
DELIVERIES AND PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 01-FEB-2021 TO
31-JAN-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265 FOB: Destination
W81C5M
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 01-MAY-2021 TO
30-APR-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0002 has been changed from:
CAGE
POP 01-FEB-2021 TO
31-JAN-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2021 TO
30-APR-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0004 has been changed from:
CAGE
POP 01-FEB-2021 TO
31-JAN-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2021 TO
30-APR-2022
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0005 has been changed from:
CAGE
POP 01-FEB-2022 TO
31-JAN-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2022 TO
30-APR-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0006 has been changed from:
CAGE
POP 01-FEB-2022 TO
31-JAN-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2022 TO
30-APR-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0008 has been changed from:
CAGE
POP 01-FEB-2022 TO
31-JAN-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2022 TO
30-APR-2023
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0009 has been changed from:
CAGE
POP 01-FEB-2023 TO
31-JAN-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2023 TO
30-APR-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0010 has been changed from:
CAGE
POP 01-FEB-2023 TO
31-JAN-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2023 TO
30-APR-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following Delivery Schedule item for CLIN 0012 has been changed from:
CAGE
POP 01-FEB-2023 TO
31-JAN-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
CAGE
POP 01-MAY-2023 TO
30-APR-2024
N/A US ARMY ABERDEEN TEST CTR -
W81C5M
PETER TURNEY
US ARMY ABERDEEN TEST CENTER
400 COLLERAN ROAD
ABERDEEN PROVING GROUND MD
21005-5059 410-278-3265
The following have been added by full text:
INSTRUCTIONS - RFP SUBMISSION
Instructions for the Submission of the Proposal The Offeror shall submit documentation illustrating their approach for satisfying the requirements of this solicitation. The NAICS code is 811310 (Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance), and the FSC is J042 (Maintenance/Rebuild of Equipment - Fire Fighting/Prevention). The resultant contract is expected to be a Firm Fixed Price (FFP) type for the quarterly maintenance CLIN and a Time and Materials (T&M) type CLIN for the emergency on-call repair services. All maintenance and repair will be performed on Aberdeen Proving Ground (APG), MD. Proposals must be clear, coherent, and prepared in sufficient detail for effective evaluation of the Offeror’s technical ability to perform the requirements of the solicitation. Unnecessarily elaborate brochures or other presentations beyond those sufficient to present a complete effective response to the solicitation are not desired.
The proposal, subject to FAR 52.212-1, Instruction to Offerors – Commercial Items, shall be submitted with the minimum information suggested. All information necessary for the review and evaluation of a proposal must be contained in the proposal volumes set forth below:
Volume I – Technical Volume II – Past Performance Volume III – Cost/Price
All questions in regards to the solicitation are to be sent directly to the Contract Specialist, Alyssa R. Grice at alyssa.r.grice.civ@mail.mil, no later than January 13, 2021 at 1000 EST. Questions received after the specified time will not be addressed. The Government reserves the right to respond to follow-on questions if it is in the Governments best interest to respond and by doing so results in a better acquisition outcome.
Offers in response to this RFP must be submitted for all of the requirements identified in the RFP. Offers submitted for less than all of the requirements called for by this RFP will not be considered for award. The Government will not consider Alternate Proposals. The proposal must meet the requirements of the Performance Work Statement.
As stated in FAR 52.212-1(g), the Government intends to evaluate proposals and award a contract without discussions with Offerors. Therefore, the Offeror’s initial offer should contain the Offeror's best terms from a price and technical standpoint.
Every Offeror must submit a written proposal before the date and time specified in Block 8 of the Request for Proposal (RFP). The proposal shall remain valid for a minimum of one hundred twenty (120) days and shall not contain classified data/information. The proposal shall be accompanied by a cover letter (letter of transmittal) prepared on the company’s letterhead stationery. The cover letter (letter of transmittal) shall identify all enclosures being transmitted and shall be used only to transmit the proposal and shall include no other information.
Additionally, the Offeror’s CAGE code must be included on the first page of the proposal.
The Offeror’s proposal shall be submitted by electronic mail. Proposal submissions must clearly identify the RFP number and the date specified for receipt of offers on the subject line. Offerors are responsible for submitting proposals in a manner to be received by the appropriate Government office designated in the solicitation by the time specified in the solicitation. Any proposal that is received after the appointed date and time is “late” and may not be considered for award.
Proposals shall be submitted to the following electronic mail addresses with a return email confirming receipt:
Alyssa.r.grive.civ@mail.mil; Elizabeth.m.nordell.civ@mail.mil
Offerors are advised that there will be no use of non-government advisors in the source selection for this solicitation.
The following have been modified:
QUESTIONS FROM INDUSTRY
All questions in regards to the solicitation are to be sent directly to the Contract Specialist, Alyssa R. Grice at alyssa.r.grice.civ@mail.mil, no later than January 13, 2021 at 1000 EST. Questions received after the specified time will not be addressed. The Government reserves the right to respond to follow-on questions if it is in the Governments best interest to respond and by doing so results in a better acquisition outcome.
23 December 2020:
Question 1: Will there be a site visit for this solicitation?
Answer: The Aberdeen Test Center (ATC) has scheduled an optional site visit for 06 January 2021 at 1000 EST for those offerors that wish to attend. No other site visit will be offered prior to the close of this solicitation, due to test schedules and time constraints.
Please note the following:
(1) COVID-19 Precautions: Please follow all CDC guidance to include: not visiting if experiencing symptoms or are sick, 10 days isolation, and 24 hours without fever, etc.
A mask is required behing the gate, even outdoors, and please keep a 6ft space between others.
https://www.cdc.gov/coronavirus/2019-ncov/if-you-are-sick/end-home-isolation.html
(2) Directions to ATC are available from the contract specialist, Alyssa Grice. Please email Ms. Grice directly at alyssa.r.grice.civ@mail.mil for maps and also to RSVP with how many person(s), along with names, will be in your party for the site visit. Please note visitor(s) must first get pass from VISITOR CENTER at the Rt. 715 gate , then proceed to ATC VISITOR CONTROL (Bldg. 324) for escort.
(3) All visitors must be US citizens. No cameras allowed.
NOTE: No questions regarding the solicitation will be answered during the site visit and all questions are to be submitted in writing to Alyssa Grice at alyssa.r.grice.civ@mail.mil, after conclusion of the site visit for review, answer and amendment.
Question 2: Is an incumbent contractor currently performing these services, if similar services have been performed in the past, or if this is a new requirement. If this is a follow-on requirement, could you please provide the previous contract or task order number?
Answer: This is a follow-on requirement for fire suppression equipment support services. The incumbent contractor is DVF Corporation and the current contract number is W91CRB-18-P-0010.
Question and Answers (Q&A) from Site Visit 06 January 2020 - AA5 1000M Pad and Pump House at Aberdeen Test Center (ATC)
Question 3: What are the confined space work requirements in the valve vaults?
Answer: ATC referred visitors to the PWS and applicable OSHA regulations regarding confined space work.
Question 4: Do offerors need to include cost for personnel from up range control room(s) to speak to technician in the valve vault during quarterly inspections (so they’d know when valves were opened, closed, etc.).
Answer: ATC answer was “no.” ATC will put a technician in the control room to coordinate with the maintenance/inspection technician in the valve vault via radio.
Question 5: What is the typical duration to conduct quarterly inspection?
Answer: ATC stated at the site visit all of the ranges can typically be inspected in a day. All deficiencies noted. Any follow up work on deficiencies would of course take extra time. ATC later clarified with an email to ACC stating it would actually take longer. Corrected response was “When all ranges are properly inspected, it will - in all likelihood - require more than one day, to include C-field.”
Question 6: Are “single line documentation” (wiring diagrams) applicable?
Answer: ATC stated it was a work in progress because of ongoing upgrades. When upgrades are finished we expect to have applicable diagrams.
Question 7: What about coordinating control room functions for troubleshoot and maintenance efforts?
Answer: ATC will provide control room support (valve actuation, etc.)
Question 8: Will the winning contractor would be responsible for the FM200 fire suppression system for/in the downrange AA5 control room?
Answer: ATC responded that they are NOT responsible and it’s not part of this contract.
Question 9: What sort of pump testing will be required.
Answer: ATC responded that pressure, flow, VFD function, etc. is based on manufacturer guidance?
Question 10: How about the absence of a fire alarm panel in the AA5 pump house?
Answer: ATC responded that it’s not an NFPA20 fire pump.
A brief clarification discussion ensured for the benefit of all contractors because some contractors working primarily in environments and with technology governed by National Fire Protection Association (NFPA) standards and regulations for protection of personnel, were initially confused thinking that all components and equipment had to meet those standards, especially in the pump houses.
ATC clarified that it isn’t the case. Our fire suppression equipment is of a military unique application and is meant to protect materiel under test from undue damage from fire during testing – not to protect personnel. It was designed and installed with that in mind. That said, ensuring NFPA compliance for fire suppression systems is not required and is not the goal of the maintenance/repair contract. Inspections and maintenance is instead to be focused on maintenance of as-built/as-designed performance of the on-site systems.
Question 11: Will the up range controls also control the AA5 pump house?
Answer: ATC responded yes, JCI providing controls interface and Tigerflow HMI will be local and remote control.
Question 12: What it the rundown of test ranges included again?
Answer: ATC responded AA5, PIMF, PI12 all have foam/water/CO2 systems. C-Field has water and foam only. BTD has CO2 only. Pete also mentioned the diesel fire pump mentioned in the PWS is at C-Field only.
Question 13: How long does a CO2 tank last and who is responsible for refill.
Answer: The average fill lasts 6 months but it's all usage dependent. ATC refills the tanks – not the contractor.
(End of Summary of Changes)