This statement of work describes a renovation project for the Vehicle Mobility Research Building on the Cold Regions Research and Engineering Laboratory campus. The project includes installing spray foam insulation on the walls and ceiling, installing an electric heating system, and replacing all pedestrian and garage doors. The building consists of three zones totaling 34,138 cubic feet that must be heated to 60 degrees Fahrenheit at an exterior temperature of negative 10 degrees Fahrenheit. Insulation options include spray foam or rolled insulation for the ceiling. The statement of work provides specifications for the type and locations of insulation, heating system requirements by zone, and dimensions and quantities of doors to be replaced. It also outlines submittal requirements, conduct of work rules, safety and environmental compliance standards, and existing utility information to assist contractors in preparing bids for the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bidder Inquiries_W913E5-23-R-0004.pdf | ||
| VSB Power Panel 1.jpg | JPG image | |
| VSB Power Panel 2.jpg | JPG image | |
| VSB Power Panel 3.jpg | JPG image | |
| Am-0001_W913E5-23-R-0004.pdf | ||
| ATTACHMENT 2 - PPQ.pdf | ||
| ATTACHMENT 1 - Specialized Experience.pdf | ||
| W913E523R0004.pdf | ||
| ATTACHMENT 3 - Proposal Data Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01 81 00 Page 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 81 00
STATEMENT OF WORK
1.1 DESCRIPTION OF PROJECT:
This Statement of Work is for the complete winterization of the
Vehicle Mobility Research Building (VMB) on the CRREL Hanover, New Hampshire campus utilizing the attached specifications and drawings to install insulation, a heating system, and replace the doors.
1.2 PROJECT SCOPE:
Contractor shall furnish all labor, equipment, supplies and materials, and perform all operations necessary to install the insulation, heating system, and doors following in accordance with the "Statement of Work" and Enclosures and attachments.
1.2.1 Fully Installed Insulation in the Mobility Building (Task 1):
Insulation shall be applied to the walls and ceiling of the building. Spray polyurethane foam insulation is required for the walls. Either spray polyurethane foam insulation or rolled insulation may be used for the ceiling – options are requested for both.
Part A. Insulation of the Walls
• Upstairs Walls: Spray polyurethane foam insulation shall be applied to all the upstairs walls. The insulation shall cover the walls fully but shall not protrude beyond the face of the window support frame on all walls. This amounts to approximately 3 inches of insulation over an area of approximately 2238 square feet. Insulation shall be 2# closed cell polyurethane spray foam insulation resulting in a vapor barrier. The materials used must be the non-flammable variety of polyurethane spray foam insulation.
• Downstairs Walls: Spray polyurethane foam insulation shall be applied to the downstairs walls. Insulation shall be applied to downstairs walls above the doors in the south two bays and any other parts of steel sided wall in the south two bays. This amounts to approximately 6 inches of insulation over an area of approximately 95 square feet.
• Sealed Vapor Barrier: All corners, gaps, and seams should be sealed with the insulation resulting in a fully sealed vapor barrier around the walls, to include any seams adjoining the walls to the ceiling (roof).
• Shave Excess: The contractor shall shave excess spray foam insulation (as needed) to ensure the insulation layer does not exceed the face of the beams and face of the window support frame on all walls. The resulting end product
Section 01 81 00 Page 2 should be sufficient to install wall paneling flush against the beams and insulation.
• R-Value Handout and Card: Upon completion of wall insulation, the contractors shall provide a printed handout that explains the insulation performance (the R-value) of the installed product. The insulation card shall also be provided after the job is completed. The card typically includes information such as the manufacturer of the insulation, the R-value of the product, the date of installation, and the contractor’s certification that the installation has been performed in accordance with local code requirements. The card is required to be posted in a prominent location, such as near the electrical panels.
• Cleaning: The contractor is responsible for the area being free of debris, equipment, and other materials used or generated during the contract prior to close-out of the contract. The mobility lab shall be returned to the state of cleanliness found upon arrival. No insulation residue (dust, debris, chunks, etc.) shall be on the floors or in other areas of the workspace. Fiber dust resulting from cutting or installing insulation shall be cleaned from all surfaces exposed.
Part B. Insulation of the Ceiling
• Thickness: The ceiling shall be insulated with an insulation thickness shall not exceed the face of the beams.
This amounts to approximately 9 inches of insulation over an area of approximately 2160 square feet.
• Baffles and the Damper: Install a baffle/damper over the existing vent locations (3 total as outlined in photos).
Insulation shall be applied to the outside of the baffles and the damper on the gable vent to keep heat from escaping.
Insulation shall not cover (clog / close) the required baffle openings or vent openings because this would stop the proper functionality of the ventilation system, but rather the insulation shall seal the baffle structures and damper to reduce heat loss.
• Foam vs Rolled Insulation Options: For the ceiling insulation, please provide two quotes for our consideration:
polyurethane spray foam insulation and rolled insulation.
o Part B-1 (Option): For spray polyurethane foam insulation, we require that 2# closed cell insulation is quoted to provide a vapor barrier. The materials used must be the non-flammable variety of polyurethane spray foam insulation. If urethane spray foam insulation is used, the contractor shall shave excess spray foam insulation (as needed) to ensure the insulation layer does not exceed the face of the beams and face of the window support frame on all walls. In the quote, please indicate the assumed R value for the ceiling after application of this insulation.
Insulation shall be 2# closed cell polyurethane spray foam insulation resulting in a vapor barrier. The
Section 01 81 00 Page 3 materials used must be the non-flammable variety of polyurethane spray foam insulation.
o Part B-2 (Option): For rolled plastic faced insulation, we require that all corners, gaps, and seams should be sealed with the insulation resulting in a fully sealed lid and vapor barrier, to include any seams adjoining the walls to the ceiling. Your bid must also explain how you would secure this insulation to prevent it from sagging or falling over time. Your bid should include the brand and specific type of insulation you plan to use. In the quote, please indicate the assumed R value for the ceiling after application of this insulation.
• Shave Excess: If spray polyurethane foam insulation is selected, the contractor shall shave excess spray foam insulation (as needed) to ensure the insulation layer does not exceed the face of the beams and face of the window support frame on all walls. The resulting end product should be sufficient to install paneling flush against the beams and insulation.
• R-Value Handout and Card: Upon completion of wall insulation, the contractors shall provide a printed handout that explains the insulation performance (the R-value) of the installed product. The insulation card shall also be provided after the job is completed. The card typically includes information such as the manufacturer of the insulation, the R-value of the product, the date of installation, and the contractor’s certification that the installation has been performed in accordance with local code requirements. The card is required to be posted in a prominent location, such as near the electrical panels.
• Cleaning: The contractor is responsible for the area being free of debris, equipment, and other materials used or generated during the contract prior to close-out of the contract. The mobility lab shall be returned to the state of cleanliness found upon arrival. No insulation residue (dust, debris, chunks, etc.) shall be on the floors or in other areas of the workspace. Fiber dust resulting from cutting or installing insulation shall be cleaned from all surfaces exposed.
Insulation Summary Table
Area Sub Area Approximate
Measurements
Mode
Walls Upstairs
Walls
3 inches of insulation over ~2238 square feet
Polyurethane
Spray Foam
Walls Downstairs
Walls
6 inches of insulation over ~95 square feet
Polyurethane
Spray Foam
Ceiling Option B1
~6 inches of insulation over ~2160
Polyurethane
Spray Foam
Section 01 81 00 Page 4 square feet
Ceiling Option B2
~9 inches of insulation over ~2160 square feet
Rolled Foam
Insulation
*Measurements provided above are approximate. Vendors will have the opportunity to visit the building this summer to verify measurements and site conditions prior to completing bids.
1.2.2 Fully Installed Heating System in the Mobility Building (Task 2):
A heating solution shall be installed in the building that meet the standards described below.
• Volume of Zones: The total volume of space that needs to be heated is 34,138 cubic feet as outlined in the Table below, and elaborated in the following text. The heating system serving theses spaces shall be sufficiently capable of heating these areas to sustain an interior temperature of 60 degrees F when exterior environmental conditions are negative 10 degrees F.
Heating System Summary Table
Zone Approximate Area Approximate
Volume
Zone 1
(Bay #1)
19 ft wide x 26 ft deep, and 10 ft tall at eves plus roof pitch
4,940 cubic feet
Zone 2
(Bays 2-4)
Bay 2: 42.5 ft wide x
26 ft deep and 10 ft tall at eves plus roof pitch
Bay 3-4: 18 ft wide x
26 ft deep and 10 ft tall at eves plus roof pitch
11,050 cubic feet + 4,680 cubic feet t =
15,730 cubic feet t
Zone 3
(Downstairs)
37 ft Wide x 26 ft Deep and 14 ft tall
13,468 cubic feet
TOTAL
34,138 cubic feet
*Measurements provided above are approximate. Vendors will have the opportunity to visit the building this
• Fuel Type: The heating system shall utilize this fuel type:
electric. The Contractor is responsible for providing a solution that works with the existing electrical panel and system, or if the Contractor proposes a system that requires
Section 01 81 00 Page 5 upgrading the feed to the panel and any other electrical upgrade requirements then those costs need to be included in the Contractor’s proposal
• Thermostats: CRREL will accept either: (a) multiple heating systems for each zone described, or (b) one primary centralized heating system for all the zones. If one system for all the zones is proposed by the Contractor, then each zone shall have a sperate thermostat to allow CRREL to control temperatures separately for each zone, and turn off certain zones as desired. Specifically, a thermostat will be required in Bay 1, another thermostat for the zone of Bay 2-
4, and another thermostat for the zone of the downstairs space. If separate systems for each zone are proposed, it is assumed that each zone will logically have a separate thermostat
• Heat in ZONE 1: This zone includes the upstairs south Bay #1 and needs a heating solution. The heating system serving this area shall be sufficiently capable of heating this zone to sustain an interior temperature of 60 degrees F when exterior environmental conditions are negative 10 degrees F.
This area includes one pedestrian door, one garage door, and four windows approximately 44 inches wide by 33 inches tall.
This area is approximately 19 ft wide x 26 ft deep, and 10 ft tall at eves plus roof pitch
• Heat in ZONE 2: This zone includes Bays 2-4 and needs a heating solution. Current configuration, from the south end:
Bay #2 is walled off and includes one garage door. This area includes one garage door, and one window approximately 44 inches wide by 33 inches tall. Room size approximately 18 ft wide x 26 ft deep and 10 ft tall at eves plus roof pitch;
Bays #3 and #4 are one large space with a stairwell at the north end. This area includes one pedestrian door, two garage doors, and four windows approximately 44 inches wide by 33 inches tall. The room size is approximately 42.5 ft wide x 26 ft deep and 10 ft tall at eves plus roof pitch.
The heating system serving these areas shall be sufficiently capable of heating these zones to sustain an interior temperature of 60 degrees F when exterior environmental conditions are negative 10 degrees F
• Heat in ZONE 3: This zone includes the downstairs two southern bays and needs a heating solution. This zone consists of one large room with two garage doors and one side entry pedestrian door. The room is approximately 37 ft
Wide x 26 ft Deep and 14 ft tall. The heating system serving these areas shall be sufficiently capable of heating these zones to sustain an interior temperature of 60 degrees F when exterior environmental conditions are negative 10 degrees F.
1.2.3 Fully Installed Doors in the Mobility Building (Task 3):
Pedestrian and garage doors shall be installed in the mobility
Section 01 81 00 Page 6 building meeting the standards described below.
• Garage Doors Upstairs: Four (4) new insulated garage doors shall be installed upstairs replacing each of the 4 existing overhead doors. Each door shall be sufficient for a space that is approximately 14 ft 2 inches wide and 8 ft tall.
Each door shall include one row of insulated glass (double pane) windows at eye level. Each door shall include installation of their own new garage door openers, with three buttons (open, close, stop) on a push button system.
Doors must have manual override to allow easy opening of the doors in case there is a loss of power. Each door shall include the ability to be locked with the locking mechanisms.
• Garage Doors Downstairs: Two (2) new insulated garage doors shall be installed downstairs (in the south two bays). Each door shall be sufficient for a space that is approximately
14 ft 2 inches wide and 12 ft 2 inches tall. Each door shall include one row of insulated glass (double pane) windows at eye level. Each door shall include installation of their own new garage door openers, with three buttons
(open, close, stop) on a push button system. Doors must have manual override to allow easy opening of the doors in case there is a loss of power. Each door shall include the ability to be locked with the locking mechanisms.
• Pedestrian Doors: Four (4) new, exterior, half-light, pedestrian (ped) doors shall be installed in the mobility building. Each door shall be sufficient for a space that is approximately 36 inches wide x 83.5 inches tall. Two (2) doors will be installed upstairs (one on each end of the building). Two (2) doors will be installed downstairs (one in the hallway and one on the south end). The doors shall include all hardware to result in a fully installed door
(mounting, doorknobs capable of taking “Best” brand keyed inserts). The doors shall be metal with internal insulation. The glass in the doors shall minimally be double pane.
Door Summary Table
Area Quantity Approximate Dimensions
Garage Doors
Upstairs
14 ft 2 inches wide and
8 ft tall
Garage Doors
Downstairs
14 ft 2 inches wide and
12 ft 2 inches tall
Pedestrian
Doors
36 inches wide x 83.5 inches tall
*Measurements provided above are approximate. Vendors will have the opportunity to visit the building this
Section 01 81 00 Page 7
1.3 PROJECT INFORMATION / REQUIREMENTS:
1.3.1 Period of Performance. See Section 00 72 00, FAR 52.211-10. Minor extensions may be granted on a case-by-case basis for issues deemed to be beyond the Contractor’s control.
1.3.2 Building in Full Use: The CRREL Vehicle Mobility Research Building will be in full use by CRREL engineers through the duration of the contract. The Contractor PM / Site Supervisor must coordinate closely with CRREL and plan in advance to ensure coordination of construction activities with CRREL research activities. It will be possible to coordinate days where CRREL staff are not present in the building for construction activities that require limited occupancy for safety reasons (e.g., spraying chemicals).
1.3.3 Hours of Operation. The laboratory is open for business from 0600 to
1800 Monday through Friday. If the Contractor requests access earlier or later access, this must be coordinated with and approved by the COR.
1.3.4 Location and Hours of Work: Accomplishment of the work in this SOW requires the work to be performed at the ERDC's Hanover, New Hampshire facility, located at: CRREL, 72 Lyme Road, Hanover, New Hampshire 03755.
1.3.5 Traffic Control. Traffic control measures and phasing shall allow for continuous access to all facilities and parking lots. Traffic Control: The contractor is responsible for establishing a traffic control plan in accordance with Manual on Uniform Traffic Control Devices (for streets and highways), and approved by the CRREL Director of Public Works (DPW) and CRREL Facilities
Manager. Traffic control is the sole responsibility of the contractor.
1.3.6 Modular Office Space. If a modular office space trailer is required, the Contractor shall coordinate with the modular office supplier to ensure appropriate location of utility connections. If needed, the Contractor Shall provide the site to receive and anchor modular office space trailers.
1.4 GENERAL
1.4.1 Kickoff Meeting: Contractor shall attend an onsite post award kick off meeting that will be arranged by the Government representative before any work on site commences. The purpose of the conference is to ensure all requirements for submittals are met, to discuss scheduling, to review safety, security, describe the plan for conducting the work, inform Contractor of Government lines of authority, and to address other subjects or questions that may be raised by either the Government or Contractor. CRREL will also conduct a “walk through” with the Contractor to locate key utilities and building / installation attributes.
• Work shall not commence on site until the kickoff meeting has taken place, all submittals have been approved, and there are no outstanding
Section 01 81 00 Page 8 issues.
• The Contractor Site Safety Officer (SSO) and the Contractor Primary POC must be present at this kickoff meeting.
• CRREL will discuss Safety Rules, Security Rules, other polices and site considerations.
• CRREL will also ensure the Contractor understands all the technical standards in the contract by reviewing the SOW to be sure no ambiguity exists, as well as the processes for acceptance and invoicing.
• All relevant and required Licenses and Certifications must be delivered to the COR at this meeting, along with proof of General Liability
Insurance.
• Safety Data Sheets (SDS): Because the creation of spray polyurethane foam products involves mixing and reacting of chemicals, the contractor shall provide to the COR the relevant Safety Data Sheets (SDS) which contain information about the chemicals including their use, storage, handling, emergency procedures, first-aid, and potential health effects.
• The Contractor shall bring a proposed schedule. The planned work scheduled will be discussed at the kickoff meeting. Work shall not commence until the work schedule has been approved by the COR. Once approved, the schedule shall be strictly followed. No changes can be made by the Contractor without prior approval of the COR.
• CRREL will be using parts of the MVB concurrently during construction and is aware that CRREL’s work cannot delay activities by the Contractor.
CRREL and the Contractor shall discuss a proposed schedule of activities at the kick-off meeting so that unobstructed access can be coordinated in advance.
1.4.2 Existing Conditions: Contractor shall field verify conditions prior to start of work to confirm plans match existing conditions.
1.4.3 Government Furnished Utilities: The Government will furnish to the
Contractor, in reasonable quantities, water and electricity in order to successfully complete this contract. Contractor may use the sanitary facilities in the Main Lab 1st Floor
1.4.4 Utility Outage/Connection Requests: The contractor shall develop and submit a memorandum to CRREL COR for any required for any required closures or utility outages. The form shall be submitted in accordance with Buckley Space
Force Base. Outages shall be coordinated by the contractor and contractor shall obtain all required signatures on the outage request. Forms shall be turned in to the Dig Permit Coordinator at building 1005 Base CE. The contractor shall coordinate with the COR and DPW prior to conducting any electrical work that connects to the CRREL electrical system (panel, grid). Review of work and possible engagement by CRREL electricians may be required.
Section 01 81 00 Page 9
1.4.5 Restoration to Original Conditions: The contractor shall limit construction activities to those areas within the limits of disturbance. Any disturbance beyond these limits shall be restored to original condition by the contractor at the contractor's expense.
1.4.6 Restrooms: Contractor shall provide portable restrooms for all personnel. Government facility restrooms are off limits.
1.4.7 Government’s Continuous Inspection and Quality Assurance: This contract is subject to inspections that may occur as often as daily and would be conducted prior to the close of business. A final Government inspection shall also occur upon completion of each task. Government inspections will, among other things, help ensure continuous quality assurance and quickly identify defects. Contractor shall repair defects as directed by the COR at
Contractor’s own expense.
1.4.8 Contractor’s Quality Control: The Contractor shall develop and maintain their own Quality Control Plan to ensure that all contract standards as successfully met. The Contractor shall be responsible for preventing and/or ensuring non-recurrence of defective services.
1.4.9 Contract Administration and Management: The following subsections specify requirements for contract, management, and personnel administration:
• Contractor Primary Point of Contact (POC). The Contractor shall designate a primary POC for work being performed during the execution of the contract. The Contractor primary POC shall keep the Contracting Officer’s
Representative (COR) informed of the work progress and be available to communicate with the COR regarding this contract work.
• US Citizens: All Contractors working on this contract must be US
Citizens and able to provide documentation to substantiate this status.
Background check verifications will be enforced.
• Work Execution: The Contractor shall furnish all labor, supervision, tools, materials, equipment, incidental engineering, transportation, and any other items and services necessary to perform the work outlined in the Scope of Work. The Contractor shall plan, program, administer, manage, execute and complete the work necessary to provide the specified services. The Contractor shall perform all administrative services, such as material procurement, quality control, financial control, and correspondence, and maintain accurate and complete records and files. The
Contractor shall manage the timeliness, completeness, and quality of the deliverables.
• Personnel Management: The Contractor shall provide all management and support as required. The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement. The Contractor shall have the responsibility for supervising their employees and subcontractors.
• Subcontract Management: The Contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor
Section 01 81 00 Page 10 performance on this requirement. The prime Contractor will manage work distribution to ensure there are no Organizational Conflicts of Interest
(OCI) considerations. Contractors may add subcontractors to their team after notification to the Contracting Officer (KO) and Contracting
Officer Representative (COR). Cross teaming may or may not be permitted.
• Travel / Temporary Duty (TDY): The Contractor is responsible for arranging all travel to execute the work outlined in the SOW including mobilization of necessary contractor employees to accomplish all tasks, or through management of subcontractors as directed by Contractor.
1.4.10 Licensing, Certifications, Insurance: The Contractor must provide copies of their personnel’s licenses and/or certifications that pertain to work under this project to the COR.
• HVAC Technicians: Contractor personnel performing the installation of the heating and air conditioning equipment shall have an HVAC Technicians license. It shall be provided either from a reciprocal state, NATE, or other equivalent recognized certification. HVAC technicians shall hold an EPA Universal Refrigerant License.
• Electrical – Contractor personnel accessing electrical system panels shall have NFPA 70E Compliant Arc Flash Safety training.
• Spray Foam Insulation Training Certification: Contractor personnel installing spray foam shall have proof of training certification.
• General Liability Insurance: The Contractor must provide proof of general liability insurance covering property damage and bodily injury losses.
1.4.11 Smoking Policy: Smoking shall comply with the CRREL Smoking Policy, which, in general, prohibits smoking on site except in a designated smoking area. Designated smoking areas will be discussed at the kickoff meeting.
1.4.12 Tools and Equipment: Tools and equipment used under this contract shall be owned solely by the contractor, maintained in good condition, and shall be used and stored using safe practices and procedures at all times in accordance with manufacturer’s instructions and recommendations. Tools and equipment shall be restricted to the immediate work area unless alternate arrangements are requested and approved through the COR. GFCI protection is required for portable tools and portable extension cords.
1.4.13 Damage: Installation of new materials shall not cause any damage to surrounding areas or items. The Contractor shall repair, at their own expense, all damages that occur due to their work, work areas, any surrounding areas, where damages are caused as a result of the performance of Contractor. All repairs shall be executed as directed by the Government.
1.4.14 Deliveries. The Contractor shall notify the COR minimally 24 hours prior to when a delivery of equipment and supplies is planned to occur. This will facilitate access on to the site.
1.5 SUBMITTALS
1.5.1 Required Submittals: The contractor shall provide all materials, equipment and information submittals required by the Government for approval
Section 01 81 00 Page 11 prior to the start of work. Material submittals shall be submitted for all major items of work.
1.5.2 As-Built Drawings: Refer to attached Construction Drawing Sets.
1.6 ENVIRONMENTAL AND SAFETY
1.6.1 These requirements shall be considered to be part of this Statement of
Work, and compliance with these requirements is the responsibility of the contractor.
1.6.2 Regulations and Requirements: This project is subject to all environmental regulations and requirements as enumerated by the CRREL
Facilities Manager and CRREL Department of Public Works. These requirements must be obtained by the offeror from the COR.
1.6.3 General Waste Management: Government policy is to apply sound environmental principles in the design, Design Build Construction and use of facilities. As part of the implementation of that policy: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. All construction and demolition waste shall be disposed of off post and/or site by the contractor.
1.6.4 Control of Waste: During performance of all work on site, the Contractor shall control waste and debris to ensure that it stays within the work area.
Contractor shall remove waste and debris from the site and properly dispose of it on a daily basis. Waste shall not be dumped in CRREL trash bins or dumpsters unless approved by the COR and Facilities Manager.
1.6.5 Disposition of Construction Debris: Unless otherwise noted, all construction debris, spoils, and removals shall become the property of the contractor and shall be disposed of off post.
1.6.6 Fire Hydrants: The contractor shall coordinate with the Government
Quality Assurance Representative and CRREL DPW prior to making any connections.
A backflow preventer with meter is required to be installed by contractor whenever a hydrant is used to supply water for construction.
1.6.7 Hot Work Permit: The contractor shall obtain hot work permits prior to conducting any type of hot work or work that may emit sparks such as cutting metal, welding, etc. Permits are required before work can commence and is the contractor's duty to obtain such permits from ERDC DPW. Points of contact will be provided at the preconstruction kick-off meeting.
1.6.8 Site Safety Officer (SSO): The Contractor shall designate one person to serve as the SSO. CRREL expects that safety standards and protocols are followed in accordance with the Corps of Engineers Safety and Health
Requirements Manual (EM 385-1-1) which is freely available for download on the internet. The Contractor shall submit the name of the SSO to the COR.
• The SSO shall be responsible for briefing and insuring correct training of all contractor and subcontractor personnel on the site.
• The SSO should be on-call at all times while Contractor and sub-
Contractor personnel are on the site.
Section 01 81 00 Page 12
1.6.9 Department of Defense Safety Policies: DoD safety protocols are enforced on the CRREL site. All Contractor personnel shall comply with the safety guidelines in effect before being allowed on the premises. This may include, but is not limited to, answering a health questionnaire and wearing personal protective equipment (PPE) while on site.
1.6.10 Safety Standards: This contract is subject to the requirements of and shall be in accordance with EM 385-1-1, U. S. Army Corps of Engineers Safety and Health Requirements Manual, OSHA 29 CFR 1910 regulations covering personnel protective equipment, the CRREL Safety Office, and to any other local, state, and federal regulations that apply to the work. All Contractor personnel shall maintain safe practices and procedures at all times while on the CRREL site.
1.6.11 Accident Prevention Plan (APP): Contractor personnel will verbally brief COR on an Accident Prevention Plan (APP) before commencing work.
1.6.12 Personal Protective Equipment (PPE): Contractor personnel performing work on site shall comply with OSHA PPE standards for protective equipment.
Each specific task will be assessed, and the appropriate PPE shall be used.
Examples include, but are not limited to: Gloves, glasses, hard hat, face shield, steel toed shoes, and Arc Flash clothing. Contractor is required to supply their employees with proper PPE.
1.6.13 Safety Data Sheets (SDS): Contractor shall submit to the COR for review at least 2 business days before bringing any chemicals onsite.
1.6.14 Trichloroethylene (TCE): On CRREL Campus, no products or equipment containing Trichloroethylene (TCE) or exposed to TCE may be used or brought on site.
1.6.15 Routes of Egress: The Contractor shall ensure work does not block egress routes in the case of an emergency.
1.6.16 Fall Protection: Fall protection threshold height is 4 feet. The Contractor shall comply with EM 385-1-1 Safety and Health Requirements Manual when accessing work areas at or above that threshold.
1.6.17 Equipment: Contractor equipment used to access work areas (i.e.
ladders, lifts, cranes) shall be current with manufacturer’s safety inspections and certificates. Inspection certificates must accompany any equipment used on site. Equipment shall be made available for inspection by the COR prior to start of work on site.
1.6.18 Barriers/Barricades and Signage: The Contractor shall provide barriers or barricades and signage as necessary to ensure unauthorized pedestrian or vehicle traffic cannot enter into work areas until safe to do so.
1.6.19 Portable Extension Cords: If it is necessary to use portable extension Cords, they shall be sized in accordance with manufacturer ratings for the tool to be powered and protected from damage. Portable extension cords shall be
GFCI and shall meet the requirements of NFPA 70, NFPA 70E and OSHA electrical standards.
1.6.20 Asbestos: If the Contractor encounters any material that could contain
Section 01 81 00 Page 13 asbestos, they shall immediately report finding to COR. The material shall not be disturbed until it has been investigated and identified
1.6.21 Re-occupancy Time: For the polyurethane installation, the contractor shall confirm to the COR what the product manufacturer’s guidance is with respect to when residents or occupants must vacate the building and when they may reoccupy the space (re-occupancy time) after job completion
1.7 ANTI-TERRORISM AND OPERATIONAL SECURITY (AT/OPSEC) REQUIREMENTS
1.7.1 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The
Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force
Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The
Contractor is responsible for meeting performance requirements during elevated
FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.7.2 Antiterrorism (AT) Level I Training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT
Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
1.7.3 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel
Section 01 81 00 Page 14 requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost
Marshal/Directorate of Emergency Services/Security Office using the National
Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as
“TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
1.7.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See
Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
1.7.5 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility
Verification and FAR Subpart 22.18 in using the E-Verify Program at
(https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility
Verification, and submit it to the Contracting Officer to become part of the official contract file.
1.7.6 Deliveries. The Contractor shall notify the COR minimally two days prior to when a delivery of equipment and supplies is planned to occur. This will facilitate access on to the site.
Section 01 81 00 Page 15
1.8 EXISTING UTILITIES
The information below provides a summary of the locations (map), type, and capacity of existing utilities. Contractor shall field verify all utilities prior to starting work.
1.9 CONSTRUCTION DRAWING SETS.
1.9.1 General Building Details. The following general information is provided to assist potential contractors to generate a bid. The building is approximately 26 ft wide by 80 ft long, and 26-28 feet tall at the tallest point along the ridge line, with two stories (upstairs and downstairs). The structure is a Butler built steel building on top of a concrete foundation. It is built into the hillside with the downstairs having all 4 walls constructed of concrete with the exposed wall having 1-2 ft of metal siding above the garage door before reaching the top story. The top floor is entirely metal sided and with a steel frame inside supporting the walls and shallow (2/12) pitch metal gabled roof. The building also includes a concrete-slab on both floors. Water is available in the building. The building includes 8 windows of approximately 44 inches x 33 inches each, with single pane glass. Windows will not be replaced at this time so use existing windows when calculating heat loss for sizing heat and AC. The building has a 120/208V service rated at 200A.
Discounting for continuous loads provides a useable capacity of 160A. Allowing for nominal existing loads reduces the unused capacity to about 140A, 208V, 3-
Phase, which will support an electric heating load of about 50kW. Photographs of the building are provided below, showing the exterior, roof, windows, interior, and subject doors.
1.9.2 Photographs of the Mobility Lab Building.
All labeled pedestrian and garage doors are to be replaced. Including new openers for the garage doors.
Mobility Building – Top Floor (South and East sides)
All four garage doors are to be replaced
Pedestrian Door
4 3 2 1
S o u t h
N o r t h
Section 01 81 00 Page 16
Mobility Building Top Floor (North and East Sides)
Mobility Building Bottom Floor (North and West Sides)
Vent will need damper system installed
Pedestrian Door
Pedestrian Door
Garage Doors that need to be replaced
Section 01 81 00 Page 17
Mobility Building Bottom Floor (South and West Sides)
Bay 1 – Remove blue board and discard, replace with new insulation as specified in section above. Room will be cleaned out prior to construction.
Vent will need damper system installed
Pedestrian Door
Section 01 81 00 Page 18
Bay 3 and 4 – Showing steel construction and stairwell. Room will be cleaned out prior to construction.
Downstairs Bays – showing garage doors, steel construction. Room will be cleaned out prior to construction.
--END OF STATEMENT OF WORK--