This solicitation package includes specifications and pricing schedules for the renovation of the Vehicle Mobility Research Building on the USACE CRREL Hanover, New Hampshire campus. The project scope involves installing insulation in the upper and lower walls, procuring and installing a new heating system, replacing the overhead and pedestrian doors, and optional upgrades to the ceiling insulation and electrical system. Offerors must submit pricing for the base work using the CLIN schedule by November 17th, with the Government reserving the right to exercise ceiling and electrical upgrades within 20 days of award. The specifications provide submittal requirements for items like shop drawings, product data and samples to support the insulation, doors and heating system. The amendment changes the response date to November 17th and includes revisions to the CLIN schedule and submittal procedures section.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment No. 0001 W9128F

CRREL Mobility Laboratory Improvements, Hanover, New Hampshire

See attached documentation for content of the revisions to the solicitation

Date for receipt of proposals is 17 November 2022 at 1400 hours CST

Government Point of Contact: William Rawe,Contract Specialist, William.T.Rawe@usace.army.mil

ERDC CONTRACTING OFFICE

HANOVER OFFICE

72 LYME ROAD

HANOVER, NH 03755-1290

See Item 6

W913E5-23-R-0001

1 2

10/19/2022

10/18/2022

Am #0001 - 2

(Continuation SF 30)

19 October 2022

Solicitation No. W913E5-23-R-0001

Date of Issue: 18 Oct 2022

New Date of Receiving Proposals: 17 Nov 2022

SUBJECT: Amendment No. 0001 to Request for Proposal Solicitation Package for Construction of CRREL Mobility Lab Upgrades and Renovation.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.) NONE

b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified with highlighting, all portions of the revised specification pages apply regardless of whether changes are shown with highlighting.

Pages or Sections Deleted Pages or Sections Substituted or Added

Submittal Register 00 10 00

01 33 00

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposals. Revised proposals will be received until 2:00 p.m., CDT, 17 NOV 2022. Provide revised proposals by emailing it to Bill Rawe

(William.T.Rawe@usace.army.mil).

Attachments:

Section 00 10 00 – CLIN Pricing Schedule

Specification Pages listed in 1.b., above

ERDC CONTRACTING OFFICE

HANOVER OFFICE

72 LYME ROAD

HANOVER, NH 03755-1290

mailto:William.T.Rawe@usace.army.mil

Page 1 Section 00 10 01

CONTRACT LINE ITEM (CLIN) PRICING SCHEDULE

ITEM

NO.

DESCRIPTION QTY UNIT UNIT

PRICE

AMOUNT

BASIC ITEMS

0001 Entire work complete to fully insulate upper level walls.

Job

XXX

0002 Entire work complete to fully insulate lower level walls.

0003 Entire work complete to procure and install heating system excluding any electrical work identified in the options below.

0004 Entire work complete to procure and install garage doors and pedestrian doors.

TOTAL BASIC AMOUNT $_____________________________

OPTION ITEMS

[Option]

Entire work complete to fully insulate ceiling with spray polyurethane foam insulation in lieu of rolled plastic faced insulation.

[Option]

Entire work complete to fully insulate ceiling with rolled plastic faced insulation in lieu of polyurethane foam insulation.

[Option]

Entire work complete to upgrade all existing electrical components and electrical panels required to support the proposed heating system.

[ONLY PRICE THIS ITEM IF

NECESSARY TO SUPPORT THE

PROPOSED HEATING SYSTEM]

TOTAL AMOUNT (BASIC PLUS OPTIONS) $___________________________

OFFEROR'S NAME: ____________________________

NOTES:

1. See 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO OFFERORS for evaluation of options.

The Government reserves the right to exercise any of the options within 20 calendar days after issuance of

Notice to Proceed. An exercise of an option will not automatically result in an extension to the contract completion date.

2. Only one of the option CLINs 0005 or 0006 may be exercised. At no time will both options be exercised.

CLIN 0007 will be exercised if required to support the heating system.

Page 1 Section 00 10 01

3. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. In case of variation between the lump-sum prices and the total amount, the lump-sum prices will be considered the price submitted.

Section 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

The Contractor is responsible for total management of his work including approval, scheduling, control, certification of all submittals and compliance with all applicable Buy-American Act and Trade Agreement Act clauses. The submittal management system provided in these specifications is intended to be a complete system for the Contractor to use to control the quality of materials, equipment and workmanship provided by manufacturers, fabricators, suppliers and subcontractors. Review each submittal for contract compliance. This review is based on the construction specifications.

No construction or installation activities are to be performed until required approvals and Government compliance reviews of applicable submittals have been made. Check to assure that all materials and/or equipment have been tested, submitted and approved during the preparatory phase of quality control inspections.

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal; and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including

(but not limited to) catalog cuts, diagrams, operating charts or curves;

test reports; test cylinders; samples; O&M manuals (including parts list);

certifications; warranties; and other such required submittals.

This section includes administrative and procedural requirements for construction submittals presented by the Contractor after the construction set plans and specifications have been accepted by the government.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, Section 01 33 00 Page 2 features, or other pertinent information regarding products, materials, equipment, or components to be used in the work. Unless otherwise designated, the submittals listed below will be handled as Administrative Submittals.

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction Progress Schedule

Work plan

Quality Control(QC) plan

Permits

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

Data sheets on the doors, insulation, and heating that will be installed prior to construction beginning.

Electrical diagrams and plans outlining what contractor will need to do to modify or replace existing panels to accommodate the required changes for this work, prior to electrical changes being made. This needs to be approved by CRREL before work starts.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-05 Design Data

Design submittals, design substantiation submittals and extensions of design submittals.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that

Section 01 33 00 Page 3 product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Factory test reports.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment.

This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract.

For example, Record Drawings, special warranties, posted operating instructions, training plan and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-

01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 ELECTRONIC SUBMITTALS

Electronic format will be utilized for submission of construction submittal items required by the specifications.

1.3.1 File Format

Electronic submittals may be submitted by any means readily accessible to the Government including, but not limited to, the following:

E-mails with text and all attachments less than or equal to 14MB in size. The Government IT system does not currently support e-mail transmissions of greater than 14MB. Should this e-mail transmission

Section 01 33 00 Page 4 size limitation change during the course of the Contract, larger e-mail transmissions may become acceptable, but no time extensions will be granted for transmission errors resulting from oversized email attachments.

Means of transfer must provide documents freely accessible to the

Government. If the means of transfer is by e-mail, FTP repository, or similar, files shall be capable of being downloaded without errors or disruption. Regardless of the method of transfer, the files shall be able to be archived on Government IT systems without error or restriction.

Once provided, all submittal documents shall become Government property.

ZIP-file or similar archives requiring a password for access to the archive are permissible provided the password for the archive is static, permanent, not use-limited, and provided to the Government at the time of transmission.

Any individual files provided electronically to the Government in 'SECURED' format, password-protected, or utilizing any other such method of file restriction shall be deemed defective and returned to the Contractor for correction. Regardless of errors encountered during the electronic submittal process the Contractor shall be responsible for delays resulting from the inadequacy of media delivery method, file-formatting, or file restriction issues. No time extensions will be granted for delays resulting from improper file formatting, file restrictions, or inadequate file transfer methods.

Discussion and decisions on a consistent Means of transfer throughout the duration of the project will be made at the pre-construction conference. The format of electronic submittals is Adobe Acrobat Portable Document Format

(PDF), compatible with Adobe X, unless agreed to and directed otherwise by the Contacting Officer's Representative.

1.3.2 Digital File Naming

Label and name electronic files delivered to the Government in a manner that is logical and consistent throughout the duration of the project. A file naming convention that clearly indicates the transmittal number, component of submittal, and revision number associated with the submittal will be discussed and confirmed at the pre-construction kickoff conference.

1.3.3 Content

Submit one (1) set of readily copied and legible electronic documents and associated matching ENG Form 4025 Transmittal Form. Duplicate copies of electronic submittals are not desired. Content and format of the electronic submittal shall conform to all requirements listed herein. Delivery methods of both electronic and hard-copy submittals shall remain consistent throughout the duration of the Contract, in compliance with Contract specifications.

1.3.4 Delivery

Delivery of submittals will be similar to those described in the "SUBMITTAL

ITEM PROCEDURES" paragraph below. Notifications of file transfers will be sent to the Government recipients listed below. The means of contact and notification by mail or email will be coordinated and confirmed at the pre-construction conference.

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

Section 01 33 00 Page 5

Unless directed otherwise, the words "Government Approval" associated with

"G" designated submittals are interpreted in the context of the below defined submittal types. Submittal Reviewers include the following:

COR – Contracting Officers Representative

CR - Government Conformance Review

1.4.1 Government Approved (G)

Government approval is required for any deviations from the Solicitation or

Accepted Proposal and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled, "Specifications and

Drawings for Construction," they are considered to be "shop drawings."

1.4.2 Government Conformance Review (CR)

1.4.3.1 Substitutions

Unless prohibited or provided for otherwise elsewhere in the Contract, where the accepted contract proposal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, and the Contractor desires to substitute manufacturer or model after award, submit a requested substitution for

Government concurrence. Include substantiation, identifying information and the DOR's approval, as meeting the contract requirements and that it is equal in function, performance, quality and salient features to that in the accepted contract proposal. If the Contract otherwise prohibits substitutions of equal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, the request is considered a "variation" to the contract.

Variations are discussed below in paragraphs: "Designer of Record

Approved/Government Approved" and "VARIATIONS"

1.4.3.2 Construction Submittals

Government's concurrence are required for those submittals as directed by the Government. These submittals are to be reviewed and approved by the

Contractor's Quality Control Representative and the Contractor's Designer prior to submittal to the Government. Conformance review only checks for compliance with the RFP solicitation requirements. Conformance review of submittals or lack thereof by the Government does not relieve the Contractor of its responsibility for the design and construction. Typical submittals are listed below.

• All Testing, Adjusting, and Balancing (TAB) submittals

• All System type testing procedures and acceptance reports (e.g., Fire

Detection, Fire Protection, Security/Communication Systems, etc.)

• All O&M Manuals

• Other final operational type submittals such as Spare Parts Data, Framed

Instructions, Warranty Information, etc.

1.4.4 Government Approved (GA)

In addition to the above stated requirements for proposed deviations to the accepted design, Government Approval and, where applicable, a contract modification are required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract (the solicitation and/or the accepted proposal), which constitutes a change to the contract terms. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are

Section 01 33 00 Page 6 considered to be "shop drawings." The Government reserves the right to accept or reject any such proposed deviation at its discretion.

1.5 PREPARATION

1.6 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The

Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the

Government in those instances where the technical specifications so prescribe. For design-build construction the Government will retain 2 copies of information only submittals.

1.7 VARIATIONS

Variations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.7.3 Considering Variations

Discussion with Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal

(VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the

Government.

1.7.4 Proposing Variations

When proposing variation, deliver written request to the Contracting

Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the

DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

If revisions to the accepted design become necessary, submit a supplemental design package using the "Supplemental Design Certification and Transmittal

Form" The revisions will be considered a "Variation" and the list of deviations from the accepted design shall be outlined on the Design

Certification form. Variations from the Construction Set must be approved

Section 01 33 00 Page 7 by the Contractor's Designer, and Contractor's Quality Control

Representative and accepted by the Contracting Officer. The supplemental design submittal must include drawings, specifications, design analysis and calculations necessary to establish that the proposed revision satisfies the contract requirements.

1.7.5 Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor, including its

Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.7.6 Review Schedule Is Modified

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.8 SUBMITTAL ITEM PROCEDURES

1.8.3 Government Reviewed Design Construction Submittals

Except as noted below, all Government reviewed design construction hard copy submittals are to be submitted in three (3) copies. All three (3) copies are to be mailed directly to the addressee shown below using the transmittal form. Additionally, submit one (1) copy of the transmittal form to the COR (as directed). See paragraph: ELECTRONIC SUBMITTALS for submittal items being transmitted electronically.

Technical Reviewers

Contracting Officer Representative (COR) (Contact info provided at award)

Engineer (Contact info provided at award)

CRREL Campus Manager (Contact info provided at award) mailto:andrew.p.bernier@usace.army.mil mailto:michael.w.parker@erdc.dren.mil

Section 01 33 00 Page 8

CRREL Director of Public Works (Contact info provided at award)

Electronic Submittals and e-mail notifications of Electronic Submittals posted to the emails listed above for each of the personnel listed.

Items not to be submitted in multiples, such as samples and test cylinders, are to be submitted to the COR (as directed), accompanied by one (1) copy of the transmittal form.

All hard copy submittals must be presented such that they fit into a standard size (letter) cabinet file drawer. Larger drawings must be folded to fit and not rolled. See paragraph: ELECTRONIC SUBMITTALS above for electronic submittals.

Catalog cuts and other descriptive data which have more than one model, size, or type or which shows optional equipment must be clearly marked to show the model, size, or type and all optional equipment which is provided.

Submittals on component items forming a system or that are interrelated are to be submitted at one time as a single submittal in order to demonstrate that the items have been properly coordinated and will function as a unit.

1.8.4 Government Reviewed Construction, Government Approved (G-AO/G-RO) and FIO Submittals

Except as noted below, data for all Government Reviewed Construction and

Government Approved submittal items are to be submitted in one (2) copy

(hard copy submittals) to the COR (as directed). Copies are to be submitted using the transmittal form.

Except as noted below, data for all items listed as "FIO" Submittals in the various sections are to be submitted in three (3) copies (hard copy submittals). All three (3) copies are to be submitted to the COR (as directed) using the transmittal form.

All hard copy submittals must be presented such that they fit into a standard size (letter) cabinet file drawer. Larger drawings must be folded to fit and not rolled. See paragraph: ELECTRONIC SUBMITTALS above for electronic submittals.

All submittals must be reviewed and approved by the Contractor's Quality

Control Representative and Contractor's Designer prior to submittal to the

Government. A completed Government conformance review is required on all

Government Reviewed Construction submittals, prior to construction of the related items.

The Government has the option to review any For Information Only submittals.

1.8.5 Certificates of Compliance

mailto:Bartlett.harwood@usace.army.mil mailto:Edward.J.Coleman@usace.army.mil

Section 01 33 00 Page 9

Each certificate must be signed by an official authorized to certify in behalf of the manufacturing company and contain the name and address of the

Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification is not to be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.8.6 Operation and Maintenance Data/Manuals

Where required by various technical sections, operations and maintenance data/manuals are to be provided by the Contractor in one (1) hard copy and three (3) separate electronic copies (three (3) CD-ROM copies), unless directed otherwise. Provide legible hard copies of the operations and maintenance data that are assembled in three-ring binders with index and tabbed section dividers and having a cover indicating the contents by equipment or system name and include the project title and location.

The legible electronic copies of the operation and maintenance data on the

CD-ROMs are to be in a Adobe Acrobat .PDF format (Version 9.0) and be organized using bookmarks that define the contents by equipment or system name and includes Project Name and Location, unless directed otherwise by the Contracting Officer. Include the same information on the CD-ROM cover.

Operation and maintenance data for mechanical and electrical systems are to be submitted for approval to the Contracting Officer 90 days prior to final tests of these systems, unless otherwise specified. Each operation and maintenance manual must contain a copy of all warranties and a list of local service representatives required by Section 01 78 36.00 24 WARRANTY OF

CONSTRUCTION AND DESIGN. If field testing requires these copies to be revised, they are to be updated and resubmitted for approval within 10 calendar days after completion of tests.

1.9 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. All copies of the approved submittal will be retained by the Contracting Officer. For electronic submittals, see paragraph: ELECTRONIC SUBMITTALS above. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above.

1.10 DISAPPROVED OR REJECTED SUBMITTALS

Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned

Section 01 33 00 Page 10 submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.

Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.11 APPROVED/ACCEPTED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor

Quality Control (CQC) requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.12 WITHHOLDING OF PAYMENT

No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted

Proposal.

Am-0001_W913E5-23-R-0001
Am-0011_W913E5-23-R-0001_Narrative
Section 00 10 01 - CLIN Schedule
SECTION 01 33 00 - Submittal Procedures

File details come from the government source that posted it. Updated .