Addendum 04 W91364-18-R-8000 MSAR

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM 04 TO

W91364-18-R-8000 FOR Modular Small Arms Range

AT 180TH FIGHTER WING

Responses to: Bristol Companies, received 21 December 2017:

MSAR Bristol 3RD set of questions / Questions set #9:

1: Please clarify the review process and timing to be employed for this project. Who will perform the government reviews of design/ engineering documents and submittals? What is the anticipated duration for the review periods?

Answer: The design working group shall conduct reviews. A properly prepared and complete design submittal package will require 7 calendar days to review.

2: Will the Toledo Airport be involved in any design reviews/approvals?

Answer: Not at this time.

3: How many design reviews are anticipated?

Answer: The SOO requires two. If submissions are rejected then additional reviews may be required, with no extension to the performance period.

4: Will the National Guard accept and review the submittal for the modular/ prefabricated gun range building prior to the completion of the balance of the design documents i.e. civil/site engineering design? The Modular building is a long lead item

Answer: Follow the requirements of the SOO for design and submittals.

5: Does the Base have a Design Standard that is to be adhered to? If so please provide.

Answer: Exterior wall colors should match Centria Surry Beige or approved equal. Finish roofing color should be white. Exterior, louvers, openings and frames shall be dark bronze or approved equal.

Interior colors per the SOO and ETL.

6: Will the project be limited to using Federally Approved Colors for the building finishes? Colors listed in the Federal Standard may not be standard manufacturer colors requiring a custom color.

Answer: Exterior wall colors should match Centria Surry Beige or approved equal. Finish roofing color should be white. Exterior, louvers, openings and frames shall be dark bronze or approved equal.

Interior colors per the SOO and ETL.