Specifications.pdf
PDF 6 MB Posted
- Attached to
- Thomaston Dam – Gate Cylinders Repair
- Solicitation number
- W912WJ21B0019
About this file
This solicitation is for gate cylinder repairs at Thomaston Dam in Thomaston, Connecticut. The work includes repairs to the components of both gates, as well as other gate system operation components. Only one gate may be worked on at a time to ensure both gates are never out of service simultaneously. The contractor must follow all applicable safety requirements and coordinate work to avoid placing the gates out of service between December 1, 2021 and April 30, 2022. The solicitation includes specifications, drawings, and requirements for submittals, project scheduling, site access and storage, safety plans, as-built drawings, and more. The contractor will be selected based on a single lump-sum bid for all work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract Final.pdf | ||
| Amendment W912WJ21B0019 - 0004.pdf | ||
| Amendment W912WJ21B0019 - 0003.pdf | ||
| Amendment W912WJ21B0019 - 0002.pdf | ||
| Amendment W912WJ21B0019 - 0001.pdf | ||
| Drawings.pdf | ||
| W912WJ21B0019.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number:
W912WJ21B0019
Gate Cylinder Repairs
Thomaston Dam Thomaston, Connecticut
Construction Solicitation and Specifications
July 2021
Gate Cylinder Repairs, Thomaston Dam, Thomaston, CT
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 05 40.14 HYDRAULIC POWER SYSTEMS FOR CIVIL WORKS STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT BACKGROUND AND WORK COVERED BY CONTRACT DOCUMENTS
1.2 REFERENCES
1.3 PHOTOGRAPHS
1.4 SUBMITTALS
1.5 SUPERINTENDENCE BY THE CONTRACTOR
1.6 WORK SEQUENCE AND SCHEDULING
1.6.1 Hours of Operations
1.6.1.1 Periods When Service Gates are Not Out of Service
1.6.1.2 All Other Time Periods
1.6.2 Work Sequence
1.6.2.1 General
1.6.2.2 Two-Week Schedule of Work Activities
1.6.2.3 Initial Project Schedule
1.6.2.4 Periodic Schedule Updates
1.6.3 Organization at the Site
1.6.3.1 General
1.6.3.2 Rate of Progress
1.7 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Access to the Site and Storage/Staging Areas
1.8.2 Temporary Facilities and Utilities, and Storage Areas
1.8.3 Work Limits
1.8.4 Protection and Security
1.8.5 Work By Other Contractors
1.8.6 Emergency Contacts
1.8.7 Damaged Property
1.8.8 Contractor's Receipt of Supplies
1.8.9 Daily Clean Up
1.8.10 Government Sanitary Facilities
1.9 QUALITY ASSURANCE
1.10 GENERAL SAFETY REQUIREMENTS
1.10.1 General
1.10.2 Contractor's Project Superintendent
1.11 ENVIRONMENTAL PROTECTION
1.12 PRECONSTRUCTION CONFERENCE
1.13 AS-BUILT DRAWINGS
1.13.1 Preparation of As-Built Drawings
1.14 RECORD DRAWINGS
1.14.1 Final Record Drawing Annotation
1.14.2 Preparation and Submission of Record Drawings
1.14.3 Record Drawing Re-Submission Requirements
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT BACKGROUND AND WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
Thomaston Dam is the largest reservoir in the Naugatuck River basin and its operation is coordinated with other Corps flood control reservoirs in the basin to reduce flooding in Thomaston, CT and other downstream communities along the Naugatuck River on the main stem of the Housatonic River. While the Thomaston Dam and its reservoir are not influenced by the outflows from nearby USACE dams, the release from Thomaston Dam is regulated to maintain safe channel capacity.
The intake structure gatehouse, conduit, and outlet structure are located near the center of the dam. A gate operating house was constructed directly above the intake tower. The discharge from the outlet works is controlled by two 5 ft-8 in by 10 ft hydraulic slide gates, which are mechanically operated (hydraulic cylinders) from the operating house at the top of the intake tower.
The work of this project shall include repairs to the components of both gates (1 & 2), as well repairs and upgrade to other gate system operation components. The Contractor shall note that only one gate a time may be worked on to ensure that both gates are never out of service at the same time.
A 10-ton electric wire rope hoist is located above the generator floor and may be used by the Contractor after being load tested and certified. The Contractor shall be responsible for obtaining the load test and getting the hoist certified.
Lead containing paint is present on the existing equipment and structures to be removed. In addition, the gate cylinders are located in an area designated by the U.S. Army Corps of Engineers, New England District (NAE) as a Confined Space. Both of these hazards require the Contractor to have appropriately trained and competent persons for the execution of this work.
This project involves fall hazards which will require a competent person for fall protection. See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.
See Section 35 05 40.14 HYDRAULIC POWER SYSTEMS FOR CIVIL WORKS STRUCTURES, Subpart SUMMARY for a detailed description of the work.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 01 11 00 Page 3
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard, Release 6.0
1.3 PHOTOGRAPHS
Attached at the end of the specification document are photographs taken at the project site during a recent site visit. The photographs are intended to show the conditions existing at the site. Items shown are not generally shown in their entirety. The Government does not guarantee that the conditions shown in the photographs will exist at the time of the performance of the work, and the Contractor is advised to make his own investigation of existing conditions.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G, RO
In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.
Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks).
SD-07 Certificates
Periodic Schedule Updates; G, RO
Request Application; G, RO
Request Application to work outside the hours of operation.
SD-11 Closeout Submittals
As-Built Drawings; G, DO
SECTION 01 11 00 Page 4
As-built drawings, which are paper mark-ups and scanned PDF's of the paper mark-ups, showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart AS-BUILT DRAWINGS for record keeping and submittal requirements.
Record Drawings; G, DO
Record drawings, which are CAD files showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart RECORD DRAWINGS for record keeping and submittal requirements.
1.5 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.
c. The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
d. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings.
e. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
f. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
SECTION 01 11 00 Page 5
1.6 WORK SEQUENCE AND SCHEDULING
1.6.1 Hours of Operations
1.6.1.1 Periods When Service Gates are Not Out of Service
During the time period of 1 December 2021 and 30 April 2022, inclusive, the Contractor shall not place the existing service gates out of service.
1.6.1.2 All Other Time Periods
Work hours are from 7:00 a.m. through 3:30 p.m., Monday through Friday.
The Contractor will not be permitted to work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer. The exclusion of work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:
January 1st Third Monday in January Third Monday in February Last Monday of May June 19th July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December
When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.6.2 Work Sequence
1.6.2.1 General
There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled SCHEDULES FOR CONSTRUCTION CONTRACTS. Variations shall be approved by the Contracting Officer prior to implementation.
SECTION 01 11 00 Page 6
1.6.2.2 Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in this section, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks). The schedule of work activities shall be updated and submitted by the Contractor to the Contracting Officer on a weekly basis, by noon on every Thursday during the prosecution of work period.
1.6.2.3 Initial Project Schedule
The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation pursuant to FAR Clause 52.236-15 "Schedules for Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The scheduling of the entire project is required. Provide a schedule that is a forward planning as well as a project monitoring tool.
The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart.
Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider as appropriate to the work, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
1. Activity Durations
2. Design and Permit Activities
3. Procurement Activities
4. Mandatory Tasks
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion and submission, review and acceptance of design packages.
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of installed equipment lists.
h. Submission and approval of test data, and reports
SECTION 01 11 00 Page 7
i. Show Government and other agency activities that could impact progress. These activities include, but are not limited to:
approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE), etc.
This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included in the schedule.
Submit the Initial Project Schedule for approval within 30 calendar days after notice to proceed is issued. No payment will be made for work items not fully detailed in the Project Schedule.
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
1.6.2.4 Periodic Schedule Updates
An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.
1.6.3 Organization at the Site
1.6.3.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause
COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.
1.6.3.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
1.7 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
The Contractor shall be responsible for the following:
(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.
(2) Complying with all local, State, and Federal regulations and
SECTION 01 11 00 Page 8 restrictions when using any facilities or hauling routes.
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Access to the Site and Storage/Staging Areas
Access to the project site is available for construction traffic. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.
Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as shown on the contract drawings.
1.8.2 Temporary Facilities and Utilities, and Storage Areas
The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
1.8.3 Work Limits
Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.
1.8.4 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.8.5 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors.
1.8.6 Emergency Contacts
The Contractor shall provide a list of emergency contacts to be used in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.8.7 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair
SECTION 01 11 00 Page 9 such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.8.8 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.8.9 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.8.10 Government Sanitary Facilities
Toilet facilities are not available on site for the Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
1.9 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
SECTION 01 11 00 Page 10
1.10 GENERAL SAFETY REQUIREMENTS
1.10.1 General
The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.10.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.11 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.12 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.
1.13 AS-BUILT DRAWINGS
Maintain at the jobsite one set of paper full-size contract drawings marked to show all deviations that have been made from the contract drawings, including buried or concealed construction and utility features revealed during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings.
These drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, submit the original marked set of prints to the Contracting Officer for approval. Also, provide PDFs of the current working redlines and/or markups complying with the as-built drawings and markup requirements. Requests for partial payments will not be approved if the marked prints and PDF files are not current, and request for final payment will not be approved until the marked prints and PDF files are submitted to and approved by the Contracting Officer.
SECTION 01 11 00 Page 11
1.13.1 Preparation of As-Built Drawings
The entries shall be made in the jobsite set of prints at the time field changes are made, pertinent information collected, or need for corrections established, as a continuing process during the life of the contract. As revised drawings are issued by the Contracting Officer, revised prints shall be introduced into the set to replace the superseded drawings and all applicable notations previously made on the superseded drawings transferred to the current prints. Carefully prepared sketches, not less than 8-1/2" x 11", may be used to depict changes or added information in lieu of notations on the actual prints. Staple sketches to the prints affected by the change. All plan views, sections, elevations, profiles, diagrams, details, or schedules affected by a change shall be marked up as required to reflect the change. All notations or changes made on the prints shall be in sufficient detail to clearly depict the change. Colored pens or pencils shall be used to make notations on the record prints as follows:
Red pen or pencil shall be employed to indicate added or corrected work or information.
Green pen or pencil shall be used to show the deleted or incorrectly depicted work or information.
Blue or black pen or pencil shall be used to show information not to be recorded on the drawings but included on the marked-up prints for explanatory or clarification purposes for the benefit of the Contracting Officer.
1.14 RECORD DRAWINGS
The record drawings are the final compilation of actual conditions reflected in the as-built drawings. The record drawings are CAD files produced from the source drawing files and marked-up as-built drawings.
The Contractor shall request the full set of electronic drawings, in the source CAD format, for Record Drawing preparation, after award and at least 30 days prior to required use. The Government will provide one set of "as-designed" electronic CAD files in AutoCAD Version 2019. The CAD files are provided to enable preparation of record drawings. If discrepancies exist between the CAD files and the contract PDF drawings, correct the CAD files to show the contract PDF drawings. The Government has no responsibility to modify any GFM due to changes in the design that occur after award.
The Contractor shall prepare the CAD drawing files in AutoCAD Version 2019 or later format.
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings, ERDC/ITL TR-12-6 and ERDC/ITL TR-12-1. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6, "Adding a Drawing Sheet", and ERDC/ITL TR-12-1, "Adding or Deleting Drawing Sheets and Index Sheet Procedures".
Provide electronic PDF files of all CAD contract drawings sheets associated
SECTION 01 11 00 Page 12 with the record drawing submittal. Compile and organize the PDF set to match the contract drawings.
1.14.1 Final Record Drawing Annotation
When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Show the wording "RECORD DRAWING AS-BUILTS" in the revision block of each drawing.
1.14.2 Preparation and Submission of Record Drawings
Within 30 days after Government approval of all of the working as-built drawings, prepare the final CAD record drawings and submit CAD and PDF drawing files. Also submit all external references (x-refs), plot style files, and all other required CAD resource files. The Government will promptly return one set of prints annotated with any necessary corrections. Within 7 calendar days revise the CAD files accordingly at no additional cost and submit one set of final CAD files and PDF files to the Government. Drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record drawings as specified will be cause for withholding any payment due under this contract. Approval and acceptance of final record drawings must be accomplished before final payment is made.
1.14.3 Record Drawing Re-Submission Requirements
If elements of a record drawing submittal are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:
A. Re-submit all CAD components, including updated content in response to Government comments.
B. Provide a copy of all Government review comments.
C. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 11 00 Page 13
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
1.2 JOB PAYMENT ITEM
1.3 BIDDING SCHEDULE - PAYMENT ITEM
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced item as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.2 JOB PAYMENT ITEM
The payment item for the work of this contract for which contract job payments will be made is listed in the BIDDING SCHEDULE and described below. The job price and payment made for the item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 BIDDING SCHEDULE - PAYMENT ITEM
a. Item Number 0001, "All Work".
All costs for labor, equipment, and materials for all work of this project, as shown on the contract drawings and in accordance with the specifications.
Unit of Measure: Job.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 2
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 MINIMUM INSURANCE REQUIREMENTS
1.2 SUPERVISION
1.3 PRECONSTRUCTION CONFERENCE
1.4 PARTNERING
1.4.1 Team-Led (Informal) Partnering
1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.2 SUPERVISION
See Section 01 11 00 SUMMARY OF WORK, Subpart SUPERINTENDENCE BY THE
CONTRACTOR.
1.3 PRECONSTRUCTION CONFERENCE
See Section 01 11 00 SUMMARY OF WORK, Subpart PRECONSTRUCTION CONFERENCE.
1.4 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the Government, Contractor, and key subcontractors are required to participate in the Partnering process.
1.4.1 Team-Led (Informal) Partnering
A. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
B. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room at the project site or at the Contractor's temporary trailer.
C. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
D. The Partners will determine the frequency of the follow-on sessions.
E. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
SECTION 01 30 00 Page 2
1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.1.2 Project Type
1.1.3 Submission of Submittals
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
1.4.1.1 Approval Codes
1.4.2 For Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
1.5.2.2 Format for SD-02 Shop Drawings
1.5.2.2.1 Drawing Identification
1.5.2.3 Format of SD-03 Product Data
1.5.2.3.1 Product Information
1.5.2.3.2 Standards
1.5.2.3.3 Data Submission
1.5.2.4 Format of SD-04 Samples
1.5.2.4.1 Sample Characteristics
1.5.2.4.2 Sample Incorporation
1.5.2.4.3 Comparison Sample
1.5.2.5 Format of SD-05 Design Data
1.5.2.6 Format of SD-06 Test Reports
1.5.2.7 Format of SD-07 Certificates
1.5.2.8 Format of SD-08 Manufacturer's Instructions
1.5.2.8.1 Standards
1.5.2.9 Format of SD-09 Manufacturer's Field Reports
1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)
1.5.2.11 Format of SD-11 Closeout Submittals
1.5.3 Source Drawings for Shop Drawings
1.5.3.1 Source Drawings
1.5.3.2 Terms and Conditions
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of SD-04 Samples
1.7 INFORMATION ONLY SUBMITTALS
1.8 PROJECT SUBMITTAL REGISTER
1.8.1 Submittal Management
1.8.2 Preconstruction Use of Submittal Register
SECTION 01 33 00 Page 1
1.8.3 Contractor Use of Submittal Register
1.8.4 Approving Authority Use of Submittal Register
1.8.5 Action Codes
1.8.5.1 Contractor Action Codes
1.8.6 Delivery of Copies
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting that Variations are Compatible
1.9.4 Review Schedule Extension
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
SECTION 01 33 00 Page 3
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Initial Project Schedule
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after
SECTION 01 33 00 Page 4 installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.
Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
Data incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
SECTION 01 33 00 Page 5
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, RO
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Government approval is required for any variations from the Solicitation or the Accepted Proposal and for other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.1.1 Approval Codes
a. Construction Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction Division. Send all such submittals to the project Resident or Area Engineer, as applicable.
b. Engineering Division {"DO" (District Office) Reviewer): A "DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.
c. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
d. Government acceptance is required for submittals with a "G, A" designation.
SECTION 01 33 00 Page 6
1.4.2 For Information Only
Submittals not requiring Government approval will be for information only.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are attached at the end of this section and are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.2.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format.
1.5.2.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title
SECTION 01 33 00 Page 7 block, for each drawing.
Reserve a blank space on the right-hand side of each sheet for the Government disposition stamp.
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section as a complete, bound volume. Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.2.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.
State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically.