This document outlines the payment items for a federal contract solicitation for maintenance dredging of Wellfleet Harbor in Massachusetts. The solicitation issued by the U.S. Army Corps of Engineers, New England District seeks bids for dredging approximately 162,000 cubic yards of sediments from the 10-foot entrance channel and anchorage of the Wellfleet Harbor Federal Navigation Project to authorized depths, transporting the material via scow to the Cape Cod Bay Disposal Site approximately 15 nautical miles away, and removing derelict moorings. Payment will be made for line items including mobilization and demobilization, dredging of specific areas to depths between -8 to -10 feet MLLW, and potential additional dredging under additive items. Bids are due by the date specified in the solicitation, which is only available electronically through beta.SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Maintenance Dredging, Wellfleet Harbor, Wellfleet, MA

Section 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

Quantity Surveys

Submit originals of all field notes and all other records relating to the quantity surveys.

1.2 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

Submit originals of all field notes and all other records relating to Quantity Surveys.

1.4 BIDDING SCHEDULE - PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed job or unit price item most closely associated with the work involved.

Section 01 22 00 Page 2

BASE BID ITEMS

A. Item Number 0001, "Mobilization and Demobilization for Dredging and Disposal".

Payment will be made for costs associated with mobilization and demobilization for dredging operations and disposal operations as defined in Special Contract Requirements clause "PAYMENT FOR

MOBILIZATION AND DEMOBILIZATION".

Unit of measure: Job.

B. Item Number 0002, "Maintenance Dredging of 10-Foot Anchorage to -8ft MLLW with Disposal at Cape Cod Bay Disposal Site (CCBDS)".

C. Item Number 0003, "Maintenance Dredging of 10-Foot Channel to -10ft MLLW with Disposal at Cape Cod Bay Disposal Site (CCBDS)".

The contract price per cubic yard for Payment Item Numbers 0002 and 0003 shall include all costs for the removal of shoaled materials encountered from dredging the Federal Navigation Project (FNP) anchorage and channel, respectively, to the specified depths, and the transportation to and disposal of the dredged material at the Cape Cod Bay Disposal Site (CCBDS), as specified in Section 35 20 23 MECHANICAL

DREDGING.

The total amount of material removed, transported and placed in CCBDS and paid for under the contract for this Item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of an after-dredge survey made as soon as practicable after the removal of the material.

Dredged material will be included that is within the limits of the side slopes and specified overdepths as described in Section 35 20 23 MECHANICAL DREDGING, paragraph "Dredging Limits", less any deductions that may be required for misplaced material described in subparagraph "Non-Designated Disposal Sites".

The contract drawings are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error. Refer to Special Contract Requirements, subpart "Contract Drawings and Specifications" for additional information and requirements regarding contract drawings.

Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the after dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.

Unit of measure: Cubic Yard (CD).

Section 01 22 00 Page 3

ADDITIVE ITEM

Item Number 0004 "Maintenance Dredging of 10-Foot Anchorage from -8ft to -9ft MLLW with Disposal at Cape Cod Bay Disposal Site (CCBDS)”,and Item Number 0005, "Maintenance Dredging of 10-Foot Anchorage from -9ft to -10ft MLLW with Disposal at Cape Cod Bay Disposal Site (CCBDS)”

The contract price per cubic yard for Payment Item Numbers 0004 and 0005 shall include all costs for the removal of an additional 1 foot depth of shoaled material encountered from dredging the Federal Navigation Project (FNP) anchorage between the specified depths respective to Item Number 0004 and Item Number 0005 as shown in the Bidding Schedule, to include the transportation to and disposal of the dredged material at the Cape Cod Bay Disposal Site (CCBDS), as specified in Section 35 20 23 MECHANICAL DREDGING.

The total amount of material removed, transported and placed in CCBDS and paid for under the contract for this Item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of an after-dredge survey made as soon as practicable after the removal of the material.

Dredged material will be included that is within the limits of the side slopes and specified overdepths as described in Section 35 20 23 MECHANICAL DREDGING, paragraph "Dredging Limits", less any deductions that may be required for misplaced material described in subparagraph "Non-Designated Disposal Sites".

The contract drawings are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error. Refer to Special Contract Requirements, subpart "Contract Drawings and Specifications" for additional information and requirements regarding contract drawings.

Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the after dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.

Unit of Measure: Cubic Yard (CD).

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Section 01 22 00 Page 4

-- End of Section --

PART 1 GENERAL
1.1 SUBMITTALS
1.2 JOB PAYMENT ITEMS
1.3 UNIT PRICE PAYMENT ITEMS
1.4 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS
PART 3 EXECUTION