addendum31 34(2).docx

DOCX document 227 KB Posted

Attached to
REPLACE WINDOWS IN BLDG 31
Solicitation number
W912PQ-10-R-0026
Issued by

About this file

Question and answers

View the file

Other files

File Type Posted
addendum31 34.docx DOCX document
site visit attend b31 34.pdf PDF
ADDENDUM31.docx DOCX document
H-1.pdf PDF
image.pdf PDF
W912PQ-10-R-0026.doc DOC document
W912PQ-10-R-0026-U0001.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW YORK AIR NATIONAL GUARD

109TH AIRLIFT WING

BASE CONTRACTING OFFICE

1 AIR NATIONAL GUARD ROAD

SCOTIA, NY 12302-9752

20 May 2010

MEMORANDUM FOR: Contractors

FROM: 109 MSG/MSC

SUBJECT: Addendum for Projects “Replace Windows, Buildings 31 & 34”

The Proposal Response date will not be extended.

The following is the listing of questions asked in reference to the subject projects, and the respective answers.

QUESTIONS AND ANSWERS – BLDGs 31 & 34

Question:

Do we need to allow for extra units for testing?

Answer:

No, contractor submits window design/specifications for approval

Question:

Insulated or single pane windows?

Answer:

Insulated windows

Question:

Glass only or do you need metal doors/window frames?

Answer:

The identified door frames that are being replaced should be replaced in kind, window frames have to meet the strength specifications in the statement of work

//Signed//
WANDA D. YARBOR, MSGT, NYANG
CONTRACTING SPECIALIST