addendum31 34(2).docx
DOCX document 227 KB Posted
- Attached to
- REPLACE WINDOWS IN BLDG 31
- Solicitation number
- W912PQ-10-R-0026
About this file
Question and answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| addendum31 34.docx | DOCX document | |
| site visit attend b31 34.pdf | ||
| ADDENDUM31.docx | DOCX document | |
| H-1.pdf | ||
| image.pdf | ||
| W912PQ-10-R-0026.doc | DOC document | |
| W912PQ-10-R-0026-U0001.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEW YORK AIR NATIONAL GUARD
109TH AIRLIFT WING
BASE CONTRACTING OFFICE
1 AIR NATIONAL GUARD ROAD
SCOTIA, NY 12302-9752
20 May 2010
MEMORANDUM FOR: Contractors
FROM: 109 MSG/MSC
SUBJECT: Addendum for Projects “Replace Windows, Buildings 31 & 34”
The Proposal Response date will not be extended.
The following is the listing of questions asked in reference to the subject projects, and the respective answers.
QUESTIONS AND ANSWERS – BLDGs 31 & 34
Question:
Do we need to allow for extra units for testing?
Answer:
No, contractor submits window design/specifications for approval
Question:
Insulated or single pane windows?
Answer:
Insulated windows
Question:
Glass only or do you need metal doors/window frames?
Answer:
The identified door frames that are being replaced should be replaced in kind, window frames have to meet the strength specifications in the statement of work
| //Signed// |
| WANDA D. YARBOR, MSGT, NYANG |
| CONTRACTING SPECIALIST |