W912PF-17-R-0018

0011017462

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See page 2 for details

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jun-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF-17-R-0018

X 9B. DATED (SEE ITEM 11)

31-May-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jun-2017

CODE

414TH CSB RCO ITALY SUBOFFICE LIVORNO

VIA AURELIA, EDIFICIO 5131

ZONA DEPOSITO

56128 TIRRENIA (PISA)

W912PF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

The purpose of this amendment is as follow:

a) to add attached Addendum 0001 to Scope of Work to Scope of Work / Performance Work Schedule, Project ED 00161-6 "General Repair Laundrette Bldg. 724 Camp Darby", consisting of 1 page dated 13 June 2017.

b) ) to provide the following material related to the equipment which will be potentially installed:

- Dryer T13 - DOCUMENT 1

- Dryer T13 - DOCUMENT 1

- Extractor (big washer) SCU030JCFXU - DOCUMENT 1

- Extractor (big washer) SCU030JCFXU - DOCUMENT 2

- Extractor (big washer) SCU030JCFXU - DOCUMENT 3

- Top load washer SWT911WN3022 - DOCUMENT 1

- Top load washer SWT911WN3022 - DOCUMENT 2

- Top load washer SWT911WN3022 - DOCUMENT 3

c) to correct the description of Attachment #1 indicated in Section J

d) to revise Section J

e) to revise Section L

f) to revise Section M

g) to provide answer to the following Request for Information:

Is it possible to participate in A.T.I. (Associazione Temporanea di Impresa) with a company having SOA OG1?

No, A.T.I. is not allowed for this requirement.

h) to provide all prospective contractors with a sample of Bid Guarantee (English & Italian version) and of Performance Bond (English version). The forms are suggested but no mandatory.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

SECTION J

The following documents are incorporated in the solicitation:

Attachment #1 - Statement of Work / Performance Work Schedule, Project ED 00161-6 "General Repair Laundrette Bldg. 724 Camp Darby", consising of 21 pages and 3 enclosures dated 03 April 2017

Attachment #2 - Technical Specifications consisting of 132 pages

Attachment #3 - Design Past Experience Questionnaire consisting of 1 page

Attachment #4 - Construction Past Experience Questionnaire consisting of 1 page

Attachment #5 - Past Performance Questionnaire consisting of 1 page

Attachment #6 - Dichiarazione del possesso dei requisiti generali (Statement of Possession of General Requirements) consisting of 2 pages

Attachment #7 - Dichiarazione del possesso dei requisiti generali BIS (Statement of Possession of General Requirements - Additional Information) consisting of 1 page

Attachment #8 - Drawings as listed below:

- 893-FS-A02.pdf, dated June 2007 (available also in CAD format)

- 893-FS-E02.pdf, dated June 2007 (available also in CAD format)

- 893-FS-E04.pdf, dated June 2007 (available also in CAD format)

- 893-FS-C02.pdf, dated June 2007 (available also in CAD format)

- 893-FS-M02.pdf, dated June 2007 (available also in CAD format)

- 893-FS-M04.pdf, dated June 2007 (available also in CAD format)

- 893-FS-M05.pdf, dated June 2007 (available also in CAD format)

- livorno_5_0034_0003.tif, dated July 1996 (only tiff available)

- livorno_5_0034_0004.tif, dated July 1996 (only tiff available)

- livorno_5_0034_0005.tif, dated July 1997 (only tiff available)

- livorno_5_0034_0006.tif, dated July 1997 (only tiff available)

- livorno_5_0034_0007.tif, dated July 1997 (only tiff available)

- livorno_5_0034_0008.tif, dated July 1997 (only tiff available)

- livorno_5_0034_0011.tif, dated April 1953 (only tiff available)

- livorno_5_0034_0015.tif, dated April 1053 (only tiff available)

- livorno_5-0034_0018.tif, dated April 1953 (only tiff available)

Attachment #9 - Addendum 0001 to the Scope of Work / Performance Work Schedule, Project ED 00161-6 "General Repair Laundrette Bldg 724 Camp Darby", consisting of 1 page dated 13 June 2017.

Attachment #10 - Material related to the equipment which will be potentially installed:

- Dryer T13 - DOCUMENT 1

- Dryer T13 - DOCUMENT 2

- Extractor (big washer) SCU030JCFXU - DOCUMENT 1

- Extractor (big washer) SCU030JCFXU - DOCUMENT 2

- Extractor (big washer) SCU030JCFXU - DOCUMENT 3

- Top load wahser SWT911WN3022 - DOCUMENT 1

- Top load wahser SWT911WN3022 - DOCUMENT 2

- Top load wahser SWT911WN3022 - DOCUMENT 3

Attachment #11 - Sample of Bid Guarantee (English and Italian version)

Attachment #12 - Sample of Performmance Bond (English version)

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

SECTION L

A. Each offeror shall provide a lump sum price in Euro currency and without IVA tax for all contract line item(s) in the bid schedule.

B. An authorized official of the firm shall sign:

- The SF 1442:

C. To be awarded a government contract you MUST have DUNS (Dun & Bradstreet) (http://fedgov.dnb.com/webform ) and NCAGE (www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in SAM Registration ((https://www.sam.gov).

D. Proposal Copies: One electronic (CD-R or DVD-R) copy of the proposal shall be submitted. The CD-ROM or DVD shall be “Read only” and all documents shall be submitted in Microsoft Office (version 2007 compatible) formats or Adobe Acrobat (PDF). No e-mail submissions will be accepted. One electronic copy only for the technical factors and non price factor shall be submitted.

I. DOCUMENTATION REQUIRED FOR THE EVALUATION

1. Failure to address all the mandatory requirements may cause the proposal to be disqualified from further consideration.

2. The offeror is responsible for submitting a well-written proposal, with adequately detailed information, which clearly demonstrates compliance with the solicitation requirements.

FACTOR:

TECHNICAL FACTOR I – DESIGN EXPERIENCE

The offeror shall demonstrate recent and relevant experience in scope, complexity and price. The Government will evaluate the information concerning at least two (2) projects provided by the offeror on the Past Experience Questionnaire (Attachment#3) (in English). In order to be considered relevant the value of each project shall be not less than Euro 80,000 ($88,987.76). In addition, each project shall be of similar scope, size and complexity i.e. each project shall contain the following works: Repair and / or upgrade of existing facilities, buildings, other than residential type. Work should include the modification / replacement of a set of utilities systems in addition to other various architectural type works. These two (2) projectss must have been perforemd by the design firm signing the letter of intent as required by this section. In order to be considered recent the past contracts must have been completed within five (5) years from the date of this solicitation as identified on Page 1, Block 3.

A letter of intent signed by an authorized agent of the Architect and Engineering firm that will be performing the design portion of this project must be included. If the design work will be performed "in-house" by the prime contractor a letter must be submitted stating this fact.

TECHNICAL FACTOR II – CONSTRUCTION EXPERIENCE

The offeror shall demonstrate recent and relevant experience in scope, complexity and price. The Government will evaluate the information concerning at least two (2) projects provided by the offeror on the Past Experience Questionnaire (Attachment#4) (in English). In order to be considered relevant the value of each project shall be not less than Euro 80,000 ($88,987.76). In addition, each project shall be of similar scope, size and complexity i.e. each project shall contain the following works: Repair and / or upgrade of existing facilities, buildings, other than residentail type. Work should include the modification / replacement of a set of utilities systems in addition to other various architectural type works. In order to be considered recent the past contracts must have been completed within five (5) years from the date of this solicitation as identified on Page 1, Block 3.

NON-PRICE FACTOR III - PAST PERFORMANCE

The Government will evaluate the information provided on the Past Performance Questionnaire (Attachment # 5) (in English). In order to be considered relevant the value of each project shall be not less than Euro 80,000 ($88,987.76). In addition, each project shall be of similar scope, size and complexity . Each project shall contain the following works: Repair and / or upgrade of existing facilities, buildings, other than residential type. Work should include the modification / replacement of a set of utilities systems in addition to other various architectrual type works. In order to be considered recent the past contracts must have been completed within five

(5) years from the date of this solicitation as identified on Page 1, Block 3.

The offeror is encouraged to submit past performance information with evidence of customer satisfaction such as performance evaluation, special commendation, recognition , letters of appreciation, “ certificato di regolare esecuzione” o “collaudo finale” photographs of the projects , etc.

FACTOR IV : PRICE

Offerors are required to fill in the lump sum prices for CLIN 0001

II. DOCUMENTATION REQUIRED BY THE SOLICITATION

A. BID GUARANTEE: The offeror shall submit the bid guarantee in the amount of 20% of the bid. The bid guarantee shall be released by a bank.

B. PERFORMANCE BOND: The offeror shall provide the performance bond in the amount of 30% of the contract amount within 15 calendar days from the award date. The performance bond shall be released by a bank.

C. SOA CERTIFICATION: The applicable SOA(s) for this project is / are as follows:

Applicable SOA Category and Classification: SOA OG1, Classification I (or higher). Sub-contracting is allowed up to 50%. However, prime contractor must possess the required SOA. The name of the prime contractor shall be indicated in the SOA.

D. ANTI-MAFIA LAW REQUIREMENTS

1. Pre-Award Effect of Anti-Mafia Procedure: Inasmuch as the work of this solicitation is to be performed on land owned by the Italian State, the prospective contractor will be subject to Italian Law No. 646, of 13 September 1982, and subsequent integration and amendments. The solicitation data will be made available only to firms that meet the submittal requirements described in paragraph below. As much, in the event that prior to award any disciplinary actions or proceedings for Mafia related matters exist against the apparent low bidder, no award will be made to said low bidder.

2. Termination Under Italian Law No. 646 (Anti-Mafia): If during the life of this contract, any proceeding or disciplinary actions contemplated by Italian Law No. 646 of 13 September 1982 (and subsequent amendments and integration) is undertaken against any component of the Contractor or any Subcontractor, the Government can consider this a failure to execute the work and terminate the Contractor’s right to proceed with the work under the "DEFAULT" clause of this contract.

3. Application of Italian Law No. 646 (Anti-Mafia) To Subcontractors: In addition to the requirement in the "Subcontractors" clause if applicable to this contract, before the Contracting Officer can consent to any Subcontractors, the Contractor will be required to certify to the Contracting Officer that no disciplinary actions or proceedings for Mafia related matters exist against such Subcontractors.

4. Submittal Requirements: The offerors are required to submit the following:

a. An original copy, un-expired and not older than two months at the time of bid opening, of the Chamber of Commerce Certificate of Membership (Certificato di Iscrizione alla Camera di Commercio). The Certificate must include the statement transcribed below, required by art. 9 and of the D.P.R. no. 252 dated 3 June 1998: "Nulla osta ai fini dell’articolo 10 della Legge 31 Maggio 1965 n. 575, e successive modificazioni. La presente certificazione e’ emessa dalla CCIAA utilizzando il collegamento telematico con il sistema informativo utilizzato dalla Prefettura di Roma."

b. Original copies, un-expired and not older than one month at the time of the bid opening, of the Family Status and Residency Certificates of each and every member of the firm, as listed in the Chamber of Commerce Certificate of Membership (per Decreto Legislativo no. 490 of 8 Aug. 1994, published in the Gazzetta Ufficiale no. 186 of Aug.

10 1994).

ADDENDUM to ANTI-MAFIA LAW REQUIREMENTS

1. Regarding 4. (a) above: As it is no longer possible to include the statement “Nulla osta….” we request that you send us the Chamber of Commerce Certificate of Membership without the statement.

2. Therefore, we require that you also submit an Anti-Mafia Self-Certification document including the following:

“Che nulla osta ai fini dell’art. 10 della Legge 575/1965 e successive modificazioni” (NULLA OSTA – in accordance with art.10, Law no. 575, 31 May 1965 and subsequent modifications).

a. Company Name and Fiscal Code

b. Name of every member of the firm, as listed in the Chamber of Commerce Certificate of Membership (per Decreto Legislativo no. 490 of 8 Aug. 1994, published in the Gazzetta Ufficiale no. 186 of Aug. 10 1994). Include:

first and last name; sex; and date & place where they were born.

c. “Che non risulta iscritta nel registro delle Imprese, per la posizione anagrafica in oggetto, alcuna dichiarazione di procedura consorsuale, ai sensi della normativa vigente in materia.”

d. “Che non risulta iscritta nel registro delle Imprese, per la posizione anagrafica in oggetto, alcuna procedura consorsuale, ai sensi della normativa vigente in materia.”

E. POOL OF FIRMS (CONSORZIO STABILE): Any Permanent Pool of Firms (Consorzio Stabile) shall provide with the proposal the here below listed required document/certificate otherwise its proposal will be rejected as not in compliance with the requirement of the solicitation, if a determination is made to award the contract based on initial proposals without discussion.

A copy certified of the notarized legal document that established the Permanent Pool of Firms (Consorzio Stabile).

The name and addresses of all the associated firms. The associated firms are NOT allowed to submit their individual proposals under this solicitation otherwise the proposal of the Permanent Pool of Firms (Consorzio Stabile) and the proposal of any associated firm will be rejected. The names and the addresses of the associated firms proposed to perform the work.

III. DOCUMENTATION REQUIRED FOR THE DETERMINATION OF RESPONSIBILITY

The U.S. Government requires the offeror to submit the following documentation/certification to be satisfied that a prospective contractor currently meets the applicable standards in Federal Acquisition Regulation 9.104 – Standards.

A. DOCUMENTO UNICO DI REGOLARITĄ CONTRIBUTIVA (DURC)

The offeror shall provide with the proposal a copy certified and NOT older than ninety (90) days at the time set forth for the receipt of the offer of the DURC. (Documento Unico di Regolaritą Contributiva). Self certifications are NOT allowed. However, if the offeror has submitted a certified DURC to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may submit a copy of the previously certified DURC. The document MUST include the following statement otherwise the proposal will be rejected. “Con il presente documento si dichiara che l’impresa RISULTA REGOLARE ai fini del DURC”.

B. CERTIFICATE OF THE CHAMBER OF COMMERCE (CERTIFICATO DI ISCRIZIONE ALLA CAMERA

DI COMMERCIO) (ORDINARIO)

The offeror shall provide with the proposal a copy certified and NOT older than two (2) months at the time set forth for the receipt of the offer of the Chamber of Commerce Certificate of Membership (Certificato di Iscrizione alla Camera di Commercio). Self-certifications are NOT allowed. However, if the offeror has submitted a certified Chamber of Commerce Certificate of Membership to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may submit a copy of the previously certified Chamber of Commerce Certificate of Membership. The certificate must include the following statement otherwise the proposal will be rejected. "NULLA OSTA ai fini dell’articolo 10 della Legge 31 Maggio 1965, n. 575 e successive modificazioni. La presente certificazione e’ emessa dalla C.C.I.A.A. utilizzando il collegamento telematico con il sistema informativo utilizzato dalla Prefettura di Roma."

C. DICHIARAZIONE DEL POSSESSO DEI REQUISITI GENERALI (Statement of Possession of Mandatory Requirements): The offeror shall provide with the proposal a self-certification to the effect that the offeror has all the necessary qualifications in accordance with Article 17 of the Italian Decree of the President of the Republic (D.P.R.)

dated 25 January 2000 number 34 using the Attachment #6 titled “DICHIARAZIONE DEL POSSESSO DEI REQUISITI GENERALI”. Each self-certification shall be accompanied by a copy of a valid unexpired identity card of the individual making the self-certification.

D. DICHIARAZIONE DEL POSSESSO DEI REQUISITI GENERALI BIS (Statement of Possession of Mandatory Requirements-Additional Information): The offeror shall provide with the proposal a self certification to the effect that the offeror has all the necessary qualifications in accordance with Article 17 of the Italian Decree of the President of the Republic (D.P.R.) dated 25 January 2000 number 34 using the Attachment #7 titled “DICHIARAZIONE DEL POSSESSO DEI REQUISITI GENERALI BIS”. Each self-certification shall be accompanied by a copy of a valid unexpired identity card of the individual making the self-certification.

E. EXTRACT OF THE REGISTRATION BOOK (ISTITUZIONE DEL LIBRO UNICO): The offeror shall provide with the proposal a copy or a photocopy of the Extract Registration Book (ISTITUZIONE DEL LIBRO UNICO) listing the employees presently employed by the offeror.

F. EQUIPMENT LIST: The offeror shall provide with the proposal a list of all the major equipment presently in its possession.

G. BANK REFERENCE: The offeror shall provide a bank reference that discusses whether or not the offeror has an adequate financial resource to successfully complete the resultant contract.

H. PROFESSIONAL TECHNICAL CAPABILITY IN ACCORDANCE WITH DLGS NO. 81/2008

ATTACHMENT XVII (SAFETY LAW).

In order to verify compliance with the Italian DLGS No. 81/2008, Enclosure XVII (Safety Law), the offeror shall provide the below required documentation/certification. If the offeror has submitted the below information to the issuing office (RCO Sub Office Livorno) within 90 days from the due date of this proposal, then the offeror may reference that submission instead of submitting duplicate information. In its proposal, the offeror must reference the request for proposal number for which the information was previously submitted.

1. Photocopy of the Chamber of commerce, industry or craftsmanship certificate showing the company’s business trade related to the typology of the contract;

2. Evaluation of risks document as in Art. 17, Para. 1, Sub-Para. a), or self-certification as in Art. 29, Para. 5, of the same DLGS;

3. Specific documentation showing that machinery, equipment and provisional clauses are in conformance with what required by the DLGS;

4. List/s of individual safety/protective equipment issued to employees;

5. Appointment of a safety manager responsible for the implementation of preventive and protective safety measures;

of the individuals responsible for the fire prevention and fire-fighting measures, the evacuation procedures, for the management of emergencies, and qualified medical physician (doctor) when required;

6. Name/s of the employee’s safety representative/s;

7. Qualification certificates of the above mentioned individuals and employees as prescribed by the DLGS;

8. List of employees as they appear in the offeror’s Istituzione del Libro Unico and relative health records attesting they are medically fit, as required by the DLGS;

9. Photocopy of the record of social security contributions (DURC), as prescribed in D.M. 24 Oct 2007; and

10. Statement that no interim orders, negative administrative provisions or suspensions exists as specified in the Art. 14 of the DLGS no. 81/2008

SECTION M - EVALUATION FACTORS FOR AWARD

BASIS OF AWARD

BASIS OF AWARD

A. The award will be made to the lowest priced technically acceptable proposal. Proposals will be evaluated for technical acceptability (including past performance), but will not be ranked using the non-price factors. In order for an Offeror to be considered for award, the proposal must receive an “Acceptable” rating in every non-price factor. A proposal receiving a rating of “Unacceptability” in any non-price factor will not be eligible for award.

B. FACTORS

The solicitation provides for the following non-price factors: Technical Factor I - Design Past Experience Technical Factor II – Construction Past Experience Non-Price Factor III – Past Performance Factor IV – Price

C. EVALUATION OF THE NON-PRICE FACTORS

Phase One. The Contract Specialist will screen each proposal for completeness to ensure that all mandatory requirements for this solicitation have been addressed. This level of evaluation does not include an in-depth reading of the proposal’s content, but it is conducted solely to ensure that a complete proposal has been received and that meets the requirements of the solicitation. Failure to address all the mandatory requirements may be grounds to disqualify the proposal from further review.

Phase Two. In this phase, the evaluation team, comprised of experts appointed by the SSA, evaluates the technical factor.

TECHNICAL FACTOR I – DESIGN EXPERIENCE

The offeror shall demonstrate recent and relevant Experience in scope, complexity and price. The Government will evaluate the information concerning at least two (2) relevant design for projects provided by the offeror on the Attachment #3 entitled “Design Experience Questionnaire (in English).

The technical factor will be rated on an acceptable/unacceptable basis using the following ratings: “

Acceptable Proposal clearly meets the minimum requirements of the solicitation

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation

TECHNICAL FACTOR II – CONSTRUCTION EXPERIENCE

The offeror shall demonstrate recent and relevant Experience in scope, complexity and price. The Government will evaluate the information concerning at least two (2) relevant projects provided by the offeror on the Attachment # 4 entitled “Construction Experience Questionnaire (in English)”.

The technical factor will be rated on an acceptable/unacceptable basis using the following ratings:”

Acceptable Proposal clearly meets the minimum requirements of the solicitation

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation

NON-PRICE FACTOR III — PAST PERFORMANCE

This factor will be rated acceptable or unacceptable based on whether the past performance submitted for consideration is relevant and demonstrates successful past performance by the offeror, such as no terminations for default, no ratings less than satisfactory by its customers/references, whether the quality of its work was satisfactory and completed in a timely manner and whether the offeror demonstrated reasonableness and cooperation during performance of the contracts. Past failure to apply sufficient tenacity and perseverance to perform acceptably is strong evidence of unacceptable past performance. In addition, failure to meet the quality requirements of a contract is a significant factor to consider in determining unsatisfactory performance. Offerors may be asked to clarify some issues regarding the aforementioned factors to enhance U.S. Government understanding. Such clarifications shall not be used to cure proposal deficiencies or material omissions, and/or otherwise revise the proposal.

Past Performance Evaluation Ratings

Rating Descriptions:

Acceptable Based on the offeror’s performance record, the

Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.

Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a) (2) (IV).

Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”

For Past Performance to be considered relevant, the offeror shall submit information about at least two (2) projects that contain the following works: Repair and/or upgrade of existing facilities, buildings, other than residential type.

Work should include the modification/replacement of a set of utilities systems in addition to other various architectural type works.

The magnitude must be not less than Euro 80,000 ($88,987.76) per individual project. To be considered recent, the project must be completed in the last five years from the date of this solicitation (date shows at Block no. 3 of SF 1442).

The offeror is encourage to submit past performance information with evidence of customer satisfaction such as performance evaluation, special commendation, recognition, letters of appreciation, “ certificato di regolare esecuzione” o “collaudo finale” photographs of the projects, etc.

The Past Performance is considered not relevant if it is not similar in work and the magnitude is less than Euro 80,000 ($88,987.76) per individual project.

It will be considered not recent if it is not completed in the last five years from the date of this solicitation (date shows at Block no. 3 of SF 1442).

The Government will conduct a past performance assessment on all contracts, at least three, submitted by the offeror on the Past Performance Questionnaire (Attachment #5). The Government will consider the recency and relevance of the information, source of the information, context of the data, and general trends in Contractor’s performance.

The Government will consider the Past Performance Questionnaire information, as well as information obtained from any other sources.

FACTOR IV - EVALUATION OF THE PRICE

A contract will be awarded to the Lowest Priced Technically Acceptable Offeror (LPTA). The total price indicated at CLIN 0001 will be evaluated for fair and reasonableness and for unbalanced pricing.

Unrealistic, unbalanced or unreasonable pricing may cause a proposal to be determined unacceptable.

Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(End of Summary of Changes)