USAG BENELUX

ENGINEERING DIVISION

HANGAR # 6 - CHIEVRES AIR BASE

HAINAUT - BELGIUM

SPECIFICATIONS FOR

PROJECT

R-CH- O2-16029-16 & Q3-15273-15 & 8T-16172-16

LOCATION

Chievres Air Base

TITLE

Replace exterior metallic doors

DATE

June 2016

PERFORMANCE PERIOD

120 calendar days

INDEX

CHAPTER I : GENERAL

CHAPTER II : TECHNICAL PROVISIONS

SECTION 1 : Work site preparation, dismounting work and cleaning

SECTION 2 : New exterior metallic doors

CHAPTER I

GENERAL

G-01 :

SCOPE OF WORK

A) General work description The purpose of this project is to replace exterior metallic doors of electrical substations, and 2 blast resistant exit doors at the Lodge and the Barracks.

The site of work is located:

Chievres Air Base Bldg 20015, 20016, 20017, 20018, 20019, 20042, 20182, 20191 and 70026

7950 Chievres

B) Principal features

Principal items to be performed to accomplish the work consist of the following:

1) See various sections on previous page.

The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawing.

G-02 :

DRAWINGS AND STANDARDS

A) Drawings

All work under this contract shall be carried out in strict conformity with the following drawing, which forms a part of these specifications.

DRAWINGS (

TITLE

DATE

R-CH-O2-16029-16-1

Substation 20015

June 16

R-CH-O2-16029-16-2

Substation 20016

R-CH-O2-16029-16-3

Substation 20017

R-CH-O2-16029-16-4

Substation 20018

R-CH-O2-16029-16-5

Substation 20019

R-CH-O2-16029-16-6

Substation 20042

R-CH-O2-16029-16-7

Substation 70026

R-CH-Q3-15273-15

&8T-16172-16

Buildings 20182 and 20191

B) Specific applicable standards

All Belgian norms and regulations (NBN (Bureau de Normalisation), EN (European Norm), etc. ) in force concerning the performance of this project shall be applicable.

All regulations in matter of environmental, safety and health will be applicable

· General Regulations for Work Protection (RGPT) and Code on the welfare of workers on the work place

· General Regulations for Electrical Installations (RGIE)

Not limited to those above.

G-03 :

GUARANTEE, WORKMANSHIP AND MATERIALS

A) Workmanship and materials

All work done by the contractor will be in strict conformance with the best practices of the trades involved.

The contractor will employ workmen who are skilled in their particular trades.

In particular, all works with potential risk of refrigerants release to the atmosphere should be conducted under the direct supervision or by a person with a category I certificate as specified in the EU regulation (EC) 303/2008 and valid for the Walloon Region area.

For safety purposes, during the execution of the work, the contractor’s workers will have to speak French or English.

All materials will be brand new.

The contractor will in no way use asbestos containing materials for the performance of his work.

The paints will be lead free.

All hazardous products brought on site by the contractor must be documented on an inventory list with safety data sheet.

B) Guarantee

The contractor will guarantee his workmanship and materials for a minimum period of 1 year after the date of final acceptance or for the period as specified by pertinent Belgian laws for the workmanship or materials in question, whichever is longer.

G-04 :

SCHEDULING OF WORK

Prior to starting any work, the contractor will furnish the contracting officer, for approval, a detailed schedule showing the successive phases of the work. All interruptions or disturbance in normal functioning of US Government organizations will also be indicated (road closure, water or utility cuts).

G-05 :

AS-BUILT DRAWINGS

The contractor will submit detailed as-built drawings after completion of the project and before submitting the final bill. As-built drawings will be precise and accurate. They will be drawn on BENTLEY MICROSTATION v8 system or any other 100% compatible system. The CD-Rom of the basic project will be given to the contractor for correction at his request.

The planning of the work must be set up, discussed and approved by the contractor, the building manager and the Government Point of Contact GPOC before the start of the work. A close coordination with the management and authorities of the base, i.e. Fire Department, is mandatory.

G-06 :

DIGGING PERMIT, UNDERGROUND PIPES AND CABLES

Before starting the earthwork, the contractor will submit a written Digging Permit Request to the GPOC. He will provide minimum 15 days before starting the earthwork the situation drawings with the earthwork that will be performed, when the work will be performed, and all utilities near the earthwork site. Drawings must be of sufficient scale to clearly show the proposed work. The drawing of existing utilities will be provided to the contractor during contract award. No digging shall occur until written approval is provided by Chief Engineering, Plans and Services Division (CEPSD), Technical Director of Public Works (TDPW) or Director of Public Works (DPW).

Additional information (drawings, etc...) about underground pipes and cables can be obtained at the Engineer Division - Hangar ( 6 - Chievres Air Base.

However, this information is only given as an indication and does not in any way commit the responsibility of the U.S. Government. The contractor will thus be responsible for carrying out the required soundings to verify their exactitude.

The contractor will ensure that no underground pipes or cables of any kind and their accessories will be damaged during the performance of the work. Any repair is done at the contractor’s expense and to the same standard as before the damage.

G-07 :

HOT WORK PERMIT

All security measures as stated in the General Work Safety Regulations (“Règlement Général sur la Protection du Travail” “RGPT”) will be complied with. Prior to starting the work, the contractor will ask a Hot Work Permit (for welding, cutting work, etc...) to the GPOC. This permit will be delivered by the U.S. Army Fire Officer.

In addition, no open fires or burning of trash will be allowed within the confines of the USAG Benelux (NSSG) Community.

Contractors, concessionaires or vendors performing work or conducting business on or in facilities under the jurisdiction of the USAG Benelux Military Community Commander Area of Responsibility will conform to this regulation. The GPOC will ensure that a copy of the French or Dutch translation of this regulation is handed to contractors at pre-construction conferences and that all requirements therein are adhered to. Specific requirements and limitations are as follows:

1. Smoking will be prohibited in the vicinity of hazardous operations and locations.

2. Waste material and rubbish will not be stored or allowed to accumulate within the building or in the immediate vicinity, but will be removed from the site at least daily. Rubbish will not be burned on the site.

3. Contractor materials and equipment will not be stored in a location or manner which will create a fire exposure to facilities adjacent to the project site.

4. The contractor will provide fire extinguishers at all locations where work is carried out.

5. In every building operation where a shed, storage, or other shanty is placed, or room or space is used for storage or workshop, the contractor will provide at least one approved portable fire extinguisher in an accessible location.

6. Flammable liquids and other hazardous materials such as paints, paint thinner, gasoline, asphalt, and tar will be stored in small detached structure or out in the open and not inside main buildings. Low flash point liquid used within buildings will be handled only in approved safety cans.

7. Adequate ventilation will be provided for paint spraying and operations involving the application of materials using adhesives containing flammable solvents. Such operations will be conducted remote from any potential source of ignition.

8. Asphalt and tar kettles will be located in a safe place outside of the building. Such kettles will not be placed on roofs or porches. Continuous supervision will be maintained while kettles are in operation. Metal covers will be provided for all kettles to smother flames in case of fire.

9. Electrical wiring and equipment for lighting, heating, and power purposes will be installed in compliance with current US and Host Nation Electrical Regulation requirements.

10. Cutting and welding will not be permitted unless:

a. A valid Hot Work Permit (welding permit) is available.

b. Combustibles have been safely covered or moved away.

c. A fire guard with a serviceable fire extinguisher is posted for the duration of the work and 30 minutes thereafter to assure that sparks or drops of hot material do not start fires.

11. Fire hydrants will only be used for fire fighting and training of the local fire and Emergency Services. Water can only be taken from hydrants with the permission of the Community Fire and Emergency Services Office. Parking within 2.5 m (8 feet) of a hydrant is not permitted.

12. Vehicles and other equipment with fuel driven motors, with mounted and filled fuel tanks will be equipped with 2,5 kg or larger carbon dioxide or dry chemical fire extinguishers.

13. Gasoline, oil and grease shall not be disposed into drainage systems or public water systems. Oil contaminated areas will be covered with an absorbent material and removed in accordance with the Spill Contingency plan. Any POL spillage will be reported immediately to the DES Fire and Emergency Services Office, DSN 361-5401/5347.

14. Construction offices, huts, construction vehicles, trailers and supplies will be located at least 10 m from all adjacent buildings.

15. Access for fire fighting vehicles will be provided to the immediate job site at the start of construction and maintained until all construction is completed. Vehicle parking control measures will be established.

16. Free access from the street to fire hydrants and to outside connections for standpipes or other firefighting equipment, whether permanent or temporary, will be provided and maintained at all times. No materials or constructions will be placed within 10 feet of such hydrants or connections, or between fire hydrants and the center line of the street.

17. Scaffolding materials or equipment will not block fire escape routes or access routes during performance of projects in occupied buildings.

18. In all buildings over 30 feet in height at least one stairway will be provided in a usable condition at all times.

19. Notification and actions to be taken in case of a fire:

a. Persons who discover a fire shall immediately alarm all personnel in the area, and shall report the fire to the Community Military Police using the nearest telephone. Military telephone dial 117.

b. The fire shall be reported using the building number. If the fire is outside of a building, the nearest building number shall be given. Stay on the phone until the operator on duty has completely understood and does not have any further questions. After the notification you should immediately ensure all windows and doors are closed and that all personnel have left the area. The responding fire department must be informed if any special dangers exists; example: If gas and pressurized containers, or paint and other flammable material are within the range of the fire. Not only acute fires, but also fires which have been extinguished and did not cause any damage must be reported.

c. To ensure smooth notification and fire fighting procedures, it is essential to show all employees the location of the nearest telephone, make sure they are familiar with the building number in which they are employed, and inform them of the locations of the fire extinguishers.

Also, for fire safety reasons, hot work permit will not be issued to perform cutting or welding operations before or after USAG BENELUX AOR regular duty hours.

G-08 : ENVIRONMENTAL STEWARDSHIP

All measures will be taken to prevent occurrence of spills during works. When a leak is detected (i.e. fuel leak on field works vehicles or company vans), the contractor will proceed to the immediate clean-up of the spill. Should the spill characteristics exceed the contractors response capacities, the contractor will immediately contact:

1) The GPOCThe Chievres Air Base Fire Department (068/ 27 54 01).

2) The USAG Benelux Environmental Division (068 27 5704)

3) The Spill Response Coordinator (068 27 5906)

The contractor must comply with all European, Belgian and regional environmental laws and regulations as well as regulations specified within the Belgian Final Governing Standards (BFGS). The BFGS is available on request through the Government Point of Contact GPOC). BFGS requirements that should be followed include, but are not limited to, the following:

BFGS Requirements

Air:

Any work that may potentially result in the release/recovery/recycling of a refrigerant requires the supervision of a trained refrigerant technician. (C.2.3.6.1.)

The use of the following Ozone Depleting Substances is prohibited: CFC’s, other fully halogenated chlorofluorocarbons, Halons, Carbon tetrachloride, 1.1.1.trichloro-ethane, Carbon tetrachloride, Hydrobromoflurorocarbones, bromochloromethane. (C.2.3.6.5.1)

The following use of Hydrochlorofluorocarbons (HCFC)s is prohibited: aerosol, solvents, and refrigerants. (C2.3.6.5.2)

Drinking Water:

Only lead-free pipe, solder, flus and fittings can be used to repair water systems and plumbing systems for drinking water. (C.3.3.1.11)

Waste Water:

Best Management Practices (Table C4.T1)

Protect fueling areas from rain and store spill response equipment nearby.

Construct sediment dams/silt fences around construction sites.

Perform corrosion control activities inside.

Store product drums/materials inside or under cover.

Capture sandblasting media, any paint waste and clean up materials (thinners, rinsates) for proper disposal.

Hazardous Materials (HMs):

HM containers and storage areas must be properly maintained. (C5.3.2)

Dispensing and storage areas for flammable liquids must have secondary containments. (C5.3.2)

All HMs must be labeled correctly. (C5.3.9)

All persons who use, handle or store HMs must be appropriately trained. (C5.3.10)

HMs must be in a locked cabinet/compartment when not in daily use. (C5.3.13.7 and C5.3.13.8.6.1)

Non-fixed liquid petroleum gas (LPG) containers must be stored outdoors. (C5.3.13.1)

Each HM must have a readily available Material Safety Data Sheet (MSDS) in English OR the predominant language. (C5.2.15)

Hazardous Waste (HW):

HW generated by the contractor will not be stored on Base, even temporarily, and must be disposed of at the cost of the contractor and by the contractor to an authorized facility outside of USAG Benelux.

HW should be segregated by the different hazardous characteristics (corrosive / flammable etc). (C6.3.2.1)

All HW containers must be closed, in good condition and with no traces of corrosion, leaks or spills. (BFGS C6.3.4 -> C5.3.2)

HW containers must be labeled correctly. (C6.3.4 ->C5.2.8)

Solid Waste:

Solid Waste must be disposed of at the cost of the contractor and by the contractor to an authorized facility outside USAG Benelux installations. It is recommended that the waste is recycled to the maximum extent possible.

Petroleum, Oil and Lubricants (POL):

At a minimum, all personnel handling (POL) shall be trained annually in the operation and maintenance of equipment to prevent discharges; discharge procedure protocols; general facility operations and the USAG Benelux (Belgian installations) Red Plan (updated regularly). (C9.3.6)

If the fueling of vehicles/machines is required on an installation it must take place on an impervious surface that drains to an oil-water separated. (C9.3.8.1.4.2)

Noise:

The contractor shall not cause sound levels in surrounding public place to exceed an established maximum level of 90dB (C10.3.1.)

Breaking and sieving activities shall neither be performed between 1900 and 0700 nor on Saturdays, Sundays or holidays. (C10.3.5.2.1)

Historic and Cultural Resources:

Any discovery of archeological resources shall be reported to the project GPOC within three business days. (C12.3.8.1)

Asbestos:

There are buildings and structures throughout USAG Benelux that contain asbestos. In particular asbestos can be found in cement piping, cement roofing, boiler gaskets, cement panels, cement chimney inspection holes and thermal system insulations. The identification of asbestos within a building and/or structure will be made within the work specific Environmental Review. Any asbestos that is removed due to work under this contract must be disposed of correctly, at the cost of the contractor, by the contractor and to an authorized facility outside of USAG Benelux.

Spill:

When using and/or storing HMs or POLs the contractor must have the ‘Red Plan’ readily available, in English AND the predominant working language. The Red Plan is different for the Walloon and Brussels regions and is updated regularly.

Work-Specific Environmental Reviews the contractor will receive an Environmental Review that is specific to the requested work The contractor must also respect and apply all environmental measures defined in the Environmental Review as it will mention site specific precautions that are not mentioned within this review. The review will be written by the USAG Benelux Environmental Division and communicated to the contractor through the GPOC.

The USAG Benelux Environmental Management System (EMS)

USAG Benelux Environmental Management System (EMS):

USAG Benelux implemented EMS IAW EO13423, ISO 14001:2004(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. USAG Benelux and EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause a real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities, and authorities while supporting the Garrison’s mission. Contractors and their personnel are required to be aware of, and comply with, the Garrison EMS policy and legal and other requirements when performing work at an installation.

The Garrison EMS is explained during the contractor pre-performance meeting and/or in the EMS manual, which may be requested from the Environmental Division. The USAG Commander’s Environmental Policy may be viewed on line at:

http://www.usagbenelux.eur.army.mil/documents/Policies/BNL_PL17(PWE)EnvironmenalMgt%20System(EMS).pdf G-09 :

SITE MAINTENANCE AND FINAL CLEANING

During performance of works, all measures should be taken to avoid improper temporary storage of waste generated by works. In particular, emphasis will be put on POL(Petroleum, Oil and Lubricants) containing equipment or soiled waste/hazardous waste (scrap metal, contaminated soil)

As soon as the work is finished, the contractor shall remove all his equipment, excess materials, debris, etc. generated by his work and will evacuate them outside US Government installations.

G-10 : COORDINATION IN MATTER OF SAFETY AND HEALTH

1.

The law of 04 August 1996 related to the welfare of workers during the execution of their work and the royal decree of 25 January 2001 concerning temporary or mobile work sites are applicable for this project.

In accordance with article 71, §3, of above mentioned royal decree, a project-coordination as foreseen in section III, 1st sub section, of this royal decree has been set up during the elaboration of this project. Therefore, there is a safety and health plan related to this project for these specifications.

The contractor will comply with the recommendations of this safety and health plan (available upon request to the “Engineering Plans and Services Division”, Hangar # 6, Chievres Air Base (David Diricq, EPS Division, tel.068/27.54.46). These recommendations are part of this project.

In application of the same article 71, §3, an execution-coordinator will be designated by the GPOC for the coordination in matter of safety and health during the execution of this project.

Within 15 days after contract award, the contractor will submit at least 4 proposals of execution-coordinator to the GPOC’s approval with:

· the necessary documents for the verification of the compliance with the conditions to exercise the coordinator function (art. 56 to 64 of R.D. dated 25.01.2001 completed by the royal decree of 19.12.2001)

No proposal may emanate from a coordinator working for the awarding firm or for an office on which the contractor has a supervisory position.

The GPOC has 10 calendar days to choose the execution-coordinator.

The coordinator’s fee is at the contractor’s charge.

2.

The contractor has 15 days from the selection of the coordinator to make up and transmit to the C.O.R. and to the execution-coordinator a document with all the complementary elements to his bid that could be claimed by the coordinator.

3.

The execution-coordinator does not act as a substitute for the GPOC. He plays the role of an advisor of the awarding party. His mission is the following:

3.1.

General obligations from the law of 04 August 1996 and royal decree of 25 January 2001

1. to coordinate the implementation of the general prevention principles described at article 5 of the law of 04 August 1996, during the technical or planning selections, in order to schedule the various simultaneous or consecutive works or phases of work, as well as during the expectation of the duration of these various works or phases of work;

2. to coordinate the implementation of relevant provisions in order to ensure that the contractors properly implement the general prevention principles and execution principles described at articles 4, 5 and 15 of the law of 04 August 1996;

3. to draw up a coordination logbook comprising the elements described at article 33 of the royal decree of 25 January 2001, except for elements dealing with the design of the project, and to update it;

4. to write down the deficiencies of the various parties in the logbook and to notify the GPOC;

5. to write down contractors’ remarks in the coordination logbook and leave them for information to the parties concerned;

6. to call and be the chairman of the coordination structure when such a structure has to be set up in accordance with article 37 of the royal decree of 25 January 2001;

7. to draw up an ulterior performance file whose content conforms with article 36 of the royal decree of 25 January 2001;

8. to organize the cooperation and coordination of activities between contractors, including those who follow one another, in order to ensure the protection of workers and the prevention of accidents and professional health hazards, as well as their mutual information;

9. to coordinate the supervision of the proper application of work procedures;

10. to take all necessary precautions so that only authorized people have access to the work site.

11. at the provisional acceptance of the work, to hand over the updated logbook and the ulterior performance file to the GPOC, and to notify this delivery in a record attached to the ulterior performance file.

3.2.

Special obligations within the scope of this project

1. to read and understand these specifications related to the work to be executed, especially the article concerning the safety and health measures to be implemented on the work site in application of the law of 4 August 1996 about the welfare of workers during the execution of their work, and of R.D. of 25 January 2001 about temporary or mobile work sites;

2. to give advice to the GPOC and to make proposals in due time concerning the implementation and adaptations of the document described at item 2 of above mentioned article, during the previous phase described in that item 2 as well as during the execution of the work;

3. to participate in any meeting to which he is invited by the GPOC, and to set up himself any useful meeting with the GPOC, the contractor or any intervening party on the work site, for the execution of his mission;

4. to control the application of the hazards prevention measures described at item 3 of the above mentioned additional article;

5. to write down the contractor’s obligations deficiencies as foreseen in above mentioned item 3 in the logbook.

4.

The contractor applies the hazards prevention measures foreseen in the document described at item 2, adapted if necessary. He has the sections of this document applied by the possible subcontractors if they apply to them.

5.

During the execution of the work, the contractor updates the document described at item 2, either on his own initiative, when the progress of the work, the identification of unforeseen or insufficiently known hazards, the incoming or outgoing of some parties, or any modification brought to the project or the work justifies, or at the GPOC’s request. If some update occurs on his own initiative, he informs the awarding party and the execution-coordinator. He takes into account any possible remark expressed by the GPOC.

In particular, he also provides the following information to the GPOC with a copy to the execution-coordinator:

· name of the subcontractor(s), the nature and cost of the work they are responsible for, the expected starting date and duration;

· traffic rules and road signs for the work site, for the public traffic area (automobiles, bicycles, handicapped people…) and for the area reserved for the work and workers, and the access rules;

· storage procedures and evacuation of materials and debris;

· work planning.

6.

The contractor must cooperate to the coordination as described above. To that purpose, he will give to the execution-coordinator, spontaneously or at his request, any information that is indispensable for the good execution of his mission. He will invite him at any meeting where his presence is necessary for the accomplishment of his task. He will participate in meetings where he is invited by the GPOC or the coordinator.

The contractor will have the obligations of previous paragraph applied by possible subcontractors.

7.

The compliance with the obligations described in items 2, 5 and 6 above is an integral part of this project.

The application of hazards prevention measures described at item 4 is also an integral part of the project, provided that these measures do not exceed the general obligations that the law of 4 August 1996 and the R.D. of 25 January 2001 impose to contractors, in particular articles 7 and 15 of the law, and section VI, sub section IV of the decree.

8.

The full text related to the coordination in matter of safety and health concerning this project can be consulted upon request to the “Engineering Division”, Hangar # 6, Chievres Air Base (David Diricq, tel.068/27.5446).

G-11 : ACCESS TO THE MILITARY INSTALLATION

See Clause 5152.225-4001 Installation Clearance Requirements in the administrative/contractual portion of this package.

G-12: ANTITERRORISM AND OPERATIONS SECURITY REQUIREMENT

Access and General Protection/Security Policy and Procedures.

1.

The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

2.

For Contract That Require Performance or Delivery in a Foreign Country.

DFARS 252.225-7043. The clause will be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and non-contingency support. The key AT requirement is for non-local national contractor personnel to comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor’s compliance with combatant commander and subordinate task-force commander policy and directives.

G-13: FINAL ACCEPTANCE OF WORKS

The final acceptance of the work will be done in the presence of the GPOC and the contractor.

CHAPTER II

TECHNICAL PROVISIONS

SECTION 1

PRELIMINARY WORK AND DISMOUNTING

TP-1-01: Appropriate equipment During the execution of the work, the contractor will provide scaffoldings, ladders, elevator,… and all necessary equipment and the workforce for a good execution of the work. He will not ask or borrow equipment from the U.S. Government (ladder, scaffolding, lift machines…).

TP-1-02: Preparation of the work site, protection means and particular conditions The contractor will firmly fix panels or plastic sheets in order to fix boundaries to the work site area and to limit the spread of dust in the room. Additional protective measures will be performed to protect the carpet, walls and false ceiling.

Any work will only be performed during accurate periods of time defined by the building manager. All necessary protections means (plastic films, canvas, etc…) will be put by the contractor in order to protect goods from dust and falling materials.

Any damage caused by the contractor will be at his cost.

The contractor will clean the work site at the end of the work. The cleaning includes the removal of debris and dust, cleaning with water of all surfaces and reinstalled equipment. The building manager will inspect and approve the site before reusing it.

TP-1-03:

Dismounting Dismounted and demolished items mentioned below include the removal and evacuation out of the military area of all debris resulting from the work. All debris will be evacuated to an authorized public dump at the contractor’s expense. All dismounted items become the property of the contractor, unless otherwise specified in these specifications or on the work site by the GPOC.

Any damage caused by the contractor’s personnel during the demolition work will be repaired at his cost.

All security protections as described in the "General Regulation of labor protection - RGPT" shall be respected.

Important Remark: The Building # 20182 and 20191 remains occupied during the construction! For this reason, a water and dust tight barrier will be installed to separate the working area and the occupied offices. This barrier will be submitted to the approval of the COR before installation.

The price for this barrier is included in the unit price of the item referring to these works.

Items to be removed:

· the removal of the exterior doors and windows has been summarized in section 2

· the dismounting of the door stop at building 20191

TP-1-04 :

Cleaning Cleaning during the work performance :

During the works the Contractor shall be responsible for the cleaning and the net appearance of the work site. The debris generated by the works shall be removed weekly.

The cost of the cleaning being included in the unit price of the item referring to these works.

SECTION 2

NEW METALLIC EXTERIOR DOORS

TP-2-01:

GENERAL

The exterior doors will be:

· Shop assembled

· stored, adjusted and installed on site (including all weatherproofing elements)

· provided with glazing and all necessary infill panels

· provided with all interior and exterior finishing

· provided with hinges, locks and all necessary opening devices and railing

Material description The work will comply with the following norms: STS 36, STS 52, STS 53 and NT 188 The window and door will be classified as:

· height: PV2: - deformation test P1= 1000

· pressure and depression , P2 = 750

· security test P3 = 2000

· wind resistance: PA3 : 6.6 m³/hm or 0.99 m³/hm² @ 600Pa (NBN B25-204)

· water tightness: PE2 : 150 Pa

They must have an ATG certification statement. This statement will be submitted before their installation.

Hardware

1) Hanging elements:

- Each leaf of door shall be hung on 4 rustfree hinges.

- Butt Hinges: Use 5 knuckle type

- Pivots and Pin hinges: Use 13mm diameter hinge, 83 mm high, with polyamide rings

Dimensions:

All different types of new frame works to be installed are shown on drawings.

Dimensions are given for guidance. The Contractor shall have to check all dimensions on spot in order to avoid problems during the installation.

TP-2-02:

METALLIC DOORS

The doors shall be constructed according to the requirements as described below. Before starting the work, the Contractor will submit a shop drawing showing details of the doors and hardware to be installed.

Minimal free open width : 0.95 meter a) Door frame Continuous welded rectangular metal profiles. All weldings shall be accomplished by skilled, professional welders. Surfaces of finished weldings shall be smooth and invisible.

b) Metal plates The inner and outer faces shall consist of one metal plate, 2 mm thick minimum, with continuous weldings to the frame.

c) Door stiles The vertical and horizontal door stiles shall consist of folded or continuous welded metal profiles, minimum 8 mm thick. The door stiles shall be anchored into the masonry, 40 cm center to center.

The tightness between the stiles and the walls shall be insured by adding caulking compound type "SECOMASTIC" or similar (see also paragraph TP-2-04). The tightness between the stiles and the door leaves shall be insured by a neoprene joint.

d) Inside The inside of the door will be filled with a thermic and acoustic insulation.

e) Doorstops In the electrical substations, a device will be installed to be able to keep the door in open position.

f) Painting Profiles will be protected by galvanization on all sides, class Zn 40, and a paint coat with zinc chromate basis before installation. A paint finish complying with the provisions of index 07.1.8.22.1c or 10.1.1c of Standard Specifications 104 will be applied.

The color of the wooden elements and hardware will be RAL 7040 outside and inside.

g) Aluminium alloy ventilation grills The grills will be suitable for the element in which they will be integrated. Louvre with chevron section blades Renson type 412 or equivalent.

Elements

· Mosquito screens: stainless steel AISI 304. Replaceable at opening points

· Outside slats: aluminum alloy. The slats at the outside must throw off water from bad weather.

Materials: Extruded aluminium according to N573-3, EN AW-6063 alloy

Finish: Polyester powder lacquer RAL7040 (60-70 microns)

h) Hardware for Anti-panic doors

The hardware for the doors will be composed of:

- 4 three-knuckle hinges with reinforcing pin, with minimum load capacity of 150kg per hinge, for a length of 160mm minimum. The hinge is fitted with an axis made of special steel with permanent greasing system. A nylon casing tinted in the mass hides the blades and fastening points.

- 1 double-locking device. However, the door must be operated from the inside by a “panic” handle, even if the door is locked. The lock must be designed for the standard keys of the existing electrical substations.

Inside, over the length of the door leaf, a panic bar of horizontal push type allows the unlocking and opening of the door by single push.

Outside, the door leaf is fitted with tinted in the mass nylon roses with stainless steel insert. A heavy duty stainless steel handle will be installed (mobile handle not authorized).

i) Installation:

The doors will be fixed to the building with a perfect horizontal and vertical alignment and at right angles. The door will be installed with appropriate stainless steel anchoring elements. The static loads of the work cannot be transmitted to the gable elements.

The anchoring elements are fitted with oblong screw holes allowing the best setting of the structural elements and the free expansion of the work. Anchoring elements are fixed by means of lag screws and pegs or pre-set rails in the masonry.

Any contact between the masonry and the metallic profiles must be avoided. To this purpose, the contractor will put an EPDM watertight membrane.

The perimeter connections of the door with the walls are adapted to the configuration of the building. They take into account the nature, thickness and position of the adjacent materials. The junction between the metallic elements and the walls is done with permanent elastic joints laid on a flexible joint bottom.

Measures will be taken to comply with the protection requirements against indirect contacts according to article 98 of the RGIE.

The door will be installed by a certified firm.

The finish will be perfect and all opening parts will work properly.

This item also includes all necessary work for the replacement of the door. The contractor will submit to the GPOC approval all constitutional elements of the door as well as detailed drawings after having taken the exact dimensions of the door (the dimensions on the drawings are given as an indication).

TP-2-03:

BLAST RESISTANT STEEL DOOR

The requirements of paragraph TP-2-02 remain.

a) Force Protection (extra requirements) All windows on the plans and schedules considered as blast resistant shall be designed and manufactured by a firm with experience in the design and the fabrication of blast resistant windows. Reference: SÄLZER or equal.

Blast window specifications require that only manufacturers of security related products with blast resistant design and manufacturing experience are acceptable.

Manufacturers shall provide test results of open air-blast testing indicating independent laboratory certification of appropriate glass fragment hazard mitigation for all blast resistant windows required for this project. Blast tube test s are permitted if they are able to simulate the actual properties of the concerned windows (size, anchorage, material of properties of the concerned windows (size, anchorage, material of substructure).

All blast resistant windows and glazing assemblies provide a minimum GSA level 3a or Very Low Hazard, per ASTM F1642-96, glass fragment harzard classification. These two classifications are defined as follows: Glass may fracture, frames may deflect but cause no glass or frame fragmentation hazard to penetrate the interior of the facility by more than one meter (1m)

Blast parameter values:

Standoff Distance
Pressure
Impulse kN/m²-msec
Duration

82,0 ft 98,4 ft 25 m 35 m 12,61 psi 9,06 psi 87,1 kN/m² 62,6 kN/m² 77,8 psi-msec 63,7 psi-msec 536,84 439,74 18,1 msec 19,3 msec

Duration: Real Pressure-Time History

Operable blast resistant windows shall be specified to provide the above required level of fragment hazard protection in closed and all open positions (tilled and swing position < 10°)

The entire window or glazing assembly including anchoring devices shall achieve the required fragment protection levels. Anchoring and fastening of the windows to the existing concrete wall shall transfer all the loads and moments as well as the shear forces into the existing wall structure.

The Contractor is responsible for the design and suitability of the window anchoring system.

Window and door submittals shall include testing reports in English and French languages, certification, all installation details, installation training, and frame anchoring method for installation into the reinforced concrete wall construction.

Since different building elevations may have different blast resistance values, but have to be similar in appearance, the contractor has to cross-coordinate those different types of windows. This coordination will be required by the window submittals.

Unusually large or complex glazing assemblies may omit air-blast testing and may be designed using an equivalent static load analysis method only when approved by ATFP technical review staff.

b) The door will be of following type:

The door will have a design similar to the existing one (2 parts glazed door at building 20182 and glazed door with fixed glazed transom at building 20191).

Safety door made of steel, type SYSTEM SALZER Series S4 (or equal) constituted of a certificated structure.

Frame made of galvanized steel with an overall thickness of 111mm.

Door leaf made of galvanized steel, size ± 72mm and continuous joint on three sides.

Following items will be included:

· reinforced hinges compatible with the door in sufficient numbers

· one safety lock of elastic multi-point type and anti-panic function compatible with the existing badge reader (cabling and connection included)

· one anti-panic handle of horizontal push bar type for the unlocking and opening of the door leaf with a single push on this bar

· one automatic door closing device adapted to the weight of the door

· two door stops

· one automatic joint for the bottom part of the door

· one heavy duty exterior handle made of stainless steel

The color of the wooden elements and hardware will be:

Building # 20182: RAL 7015 outside and inside Building # 20191: RAL 9007 outside and 9010 inside.

TP-2-04:

SPECIAL ELASTIC JOINTS FOR EXTERIOR JOINERY AROUND THE DOOR

FRAME

Composition

The permanent elastic joint has been composed of 2 component putties : basically a thiocol and a vulcanizer. After mixing it becomes a thermostable and permanent elastic long lasting rubber mass with a perfect adherence to the edges.

Color

To be determined with the Contracting Officer's Representative. A sample and a color chart is to be submitted.

Application the openings shall be free of dust and dry.

foam rubber strips shall be incorporated first.

the mastics are applied with a pistol.

minimum temperature of 6 degrees Celsius.

the joint is at least as thick as the opening to be filled.

drying time : 2 days to be vulcanized.

no shrinking.

TP2-05:

FINISHING WORK

Remark : Items described under this paragraph are listed as a reminder to the offerors. only. The cost of these items must be included in the price of the doors and windows.

a) Move badge reader to building 20191 Concerns all required work to move the badge reader located on the right side of the blast resistant door to be replaced. The reader will be moved to the left side of the door to correspond with the new door opening direction.

Following items will be included:

- careful dismounting of the badge reader

- installation of new cables

- drilling work to hide the cables

- repair existing exterior masonry

b) Inside finish of building 20182 Concerns all plastering work, paint work and repair as existing of the finish of all interior walls (tile, baseboards, etc…)

c) Inside finish of building 20191

Concerns all plastering work, paint work and repair as existing of the finish of all interior walls (wall papers, baseboards, etc…)

d) Inside finish of electrical substations

Inside finish on masonry and around the door frame for a perfect finish. Method of finish to be submitted to the GPOC approval before execution.

TP-2-06:

MEASUREMENT

The lump sum price will include:

supply and installation of both opening and fixed joinery as well as accessories study and design costs supply and installation of the glazing or other cladding all accessories for attachment to the rough work hardware and protection devices tightening of the joints between joinery and rough work protection of the joinery, to provide all parts permanently with a resistance against dry, humid or electrolytic corrosion fastening and covering cleaning of the joinery and removal of the waste from the work required certificates, approvals and/or tests implementation of supports and sills in masonry work clearing and cleaning of the spaces and bays for layout and installation of the exterior joinery stuffing and caulking at the inside and caulking joints rectifications to the rough work if it does not allow compliance with the installation tolerances removal of any temporary protection cleaning upon completion of the work.