AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REFERENCE: INVITATION FOR BIDS NO. W912P6-17-B-0005, "RIVER RIPARIAN CONNECTIVITY AND HABITAT, SECTION 506"
-- THE DESCRIPTION OF THIS AMENDMENT FOLLOWS ON THE NEXT PAGES--
1. CONTRACT ID CODE PAGE OF PAGES
1 77
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Sep-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P617B0005
X 9B. DATED (SEE ITEM 11)
16-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Sep-2017
CODE
U.S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P617B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
A. BID OPENING DATE AND TIME:
The BID OPENING DATE for the referenced Solicitation IS NOT EXTENDED by this Amendment.
The bid opening will be held on September 20, 2017 as the USACE has received the required Real Estate for this project; therefore, the contingency statement is no longer applicable and bids can now be accepted (more details provided in the below paragraph B). Accordingly, bids are due by 3:00 p.m. (Central Time) on September 20, 2017. Detailed information regarding the submission of bids is located at Section 00100 of the Solicitation document.
B. REAL ESTATE - EASEMENT CERTIFICATION AND CHICAGO PARK DISTRICT & METROPOLITAN
WATER RECLAMATION DISTRICT OF GREATER CHICAGO (MWRD) PERMITS:
CONTINGENCY STATEMENT IS RELEASED: By way of this Amendment, prospective Bidders are hereby informed that the required Channel Improvement Easement Certification and Chicago Park District & Metropolitan Water Reclamation District of Greater Chicago (MWRD) permits have been received for the project. Thus, whereas the contingency statement had been previously stated in the Solicitation, it is hereby removed.
C. AMENDED BID SCHEDULE (SECTION 00010 – SOLICITATION CONTRACT FORM) : By this Amendment, quantities have been updated to the following Contract Line Items Numbers:
0002AQ, 0002AW, 0002AX, 0003AH, 0003AL, 0004AQ, 0004AW, 0004AX, 0005AM, 00005AS,
0005AT, 0006AR, 0006AX, and 0006AY. Accordingly, Bidders shall remove and replace the previously issued respective Bid Schedule (Solicitation Contract Form) with the Revised Bid Schedule enclosed hereunder AND ensure that it is fully completed and furnished with the other deliverables required by this Solicitation.
D. AMENDED PLAN SHEETS (REVISED PLAN SHEETS ARE ENCLOSED HEREUNDER):
Sheets CS115: Note #2 was revised to include an approximate depth of concrete removal at the east bank of Ronan Park.
E. AMENDED SPECIFICATION SECTIONS (REVISED PAGES ARE ENCLOSED HEREUNDER):
a. SECTION 01 22 00.00 10, MEASUREMENT AND PAYMENT PROCEDURES, para
1.3.15 and 1.3.16 – Seed pay items for the Big Marsh site was removed from paragraph 1.3.15. A new payment paragraph (para. 1.3.16) was added to clarify the measurement and payment procedures for the seeding activities at the Big Marsh site.
b. SECTION 31 00 00, EARTHWORK, para 1.1 & 1.2: The measurement and payment paragraphs were removed and notes added to reference Section 01 22 00.00 10 for the measurement and payment procedures for earthwork.
c. SECTION 31 00 00, EARTHWORK, para 1.3: The base bid criteria ‘b’ was revised to remove the statement that pipes or other artificial obstructions will not be encounter. A statement was added that pipes encounters will be not be in conflict with the proposed work. To be consistent with the drawings, a note was also added stating that the contractor must locate all pipe outlets into the river prior to grading.
d. SECTION 32 93 00, PLANTS, Plant List: The plant list was revised to remove the quantities of the trees/shrubs from the “Restoration Species List” and refer the contractors to the “Tree and Shrub Species List” for quantities. There was a typo in the seed quantities for Juncus Tenuis under the savanna seed mix, which was corrected.
e. SECTION 35 31 19.52, STREAM HABITAT RESTORATION: Para. 2.1.4.2 – the paragraph was revised to address a question from a bidder. The IDOT FA-7 gradation sand specified for fine sand may not be locally available. The fine sand type from Thelan Sand & Gravel or approved equal was added to allow for other gradations of fine sand.
F. WAGE DETERMINATION: This Amendment incorporates and encloses the most recently released Wage Determination, General Decision IL9, dated 9/15/2017.
G. CONTRACTOR’S INQUIRIES: By this Amendment, the Chicago District, USACE responds to Contractor’s inquiries. See Below.
USACE’S RESPONSES TO CONTRACTOR’S INQUIRIES FOLLOW:
Question 1: The Tree and Shrub Species List totals for 5 Gallon and 1.5” appear to be off from the quantities in the bid schedule for both the Bank and Savanna areas for all the options.
USACE Response Q1: The 5 Gallon and 1.5” caliper quantities are per acre. There are revision to the quantities of the 1.5” caliper trees. There will be no change to the 5 Gallon tree/shrub quantities.
The “Tree and Shrub Species List” table in Section 32 93 00, Plants, will be revised to show that the species quantities are per acre.
Question 2: Currently the Bank Restoration Species List has quite a few trees and shrubs listed as plugs.
Will these be bareroot seedlings or do they need to be potted as plugs?
USACE Response Q2: Trees and shrubs sizes must follow the specifications listed in Section 32 93 00, Plants, paragraph 2.3.2. For more clarification, the “Restoration Species List” tables will be revised to remove the quantity of trees and shrubs from the plug column and refer to the “Tree and Shrub Species List” table for trees and shrubs quantity.
Question 3: Specification SECTION 32 93 00 PLANTS- 3.4 PLUG INSTALLATION mentions in paragraph 6 that “After planting is complete for any area, appropriate erosion control must be installed as needed to ensure all permit regulations are followed.” What are the appropriate erosion control measures for each area? What type of erosion control blanket will be required for the project? Why are there no separate line items for erosion control blanket?
USACE Response Q3: The erosion control measure will be provided by the Contractor as required under the Section 01 57 20.01 03, Environmental Protection for IL. There are no separate line items for erosion control blankets. Erosion control measures will be incidental to the appropriate bid items for plugs.
Question 4: Does the Big Marsh site require establishment activities? The RIVER PARK-BASE WORK has a line item for SEEDS-BIG MARSH but does not have a SITE PREPERATIONS, ETC. line item (for site preparations, invasive species control, and establishment activities).The Big Marsh site is also not included in the Performance Criteria Per Year table. Please clarify.
USACE Response Q4: There is no establishment activities for the Big Marsh site. A separate paragraph clarifying the seeding requirements for Big Marsh site will be added to Section 01 22
00.00 10, Measurement and Payment.
Question 5: Specification SECTION 32 01 90.56 ESTABLISHMENT ACTIVITIES-3.4 PERFORAMANCE CRITERIA AND ACCEPTANCE mentions end of the year monitoring. Will this be performed by USACE or the contractor?
USACE Response Q5: USACE will perform the end of year monitoring.
Question 6: Juncus tenuis in the Savanna mix shows 25 oz/acre. Can you please clarify if that is correct or if it really is suppose to be 0.25 oz/ acre.
USACE Response Q6: Quantity for Juncus tenuis should be 0.25 oz/ac. The plant list quantity in Section 32 93 00, Plants, will be updated accordingly.
Question 7: In reviewing the “VF” sheets for the limits of clearing and grubbing, there appears to be no work in the base bid. More specifically, there is no clearing and grubbing limits shown on the west bank of the main channel, nor either side of the North Branch on sheet VF008. Is this your intention?
USACE Response Q7: There is no clearing and grubbing for the base contract. Therefore, there will be no clearing/grubbing on either side of the NBCR as shown on VF008. Clearing and grubbing on the west bank is limited to the area shown on sheet VF009.
Question 8: Specification section 31 00 00 indicates in several places that Earthwork will be paid by a measured cubic yard quantity. However, Specification section 01 00 00.00 as well as the pay items themselves show that the Earthwork items will be paid as 1 Job. Please clarify.
USACE Response Q8: Section 31 00 00, Earthwork will be revised to remove references to earthwork payment in cubic yards. Earthwork payment will be as indicated in Section 01 22 00.00 10, Measurement and Payment Procedures.
Question 9: Does this Contract require (3) separate, full-time, on-site individuals for Quality Control Manager, Site Superintendent and SSHO during earth moving / civil construction activities?
USACE Response Q9: Yes, the contract requires three separate personnel for the duration of the contract except during the plant establishment periods. During the plant establishment periods, the SSHO and Quality Control person can be the same person as stated in paragraph 1.5.1.1.1 of Section
01 35 26, GOVERNMENTAL SAFETY REQUIREMENTS.
Question 10: In Specification section 35 31 19.52, Paragraph 2.1.4.2 Identifies FA-7. Further, Paragraph
3.3.2 identifies that the Channel Stone Fill is to consist of 50% Torpedo Sand, 25% sand and 25% Pea Gravel. Please confirm that when using the term "sand", you mean FA7. If not, what sand size do you require. Also, FA-7 is not locally available. Please identify a sand that is locally available.
USACE Response Q10: “25% sand” in paragraph 3.3.2 refers to “fine sand” or FA7 as defined in paragraph 2.1.4.2. Mason sand by Thelan Sand and Gravel or approved equal can be used for fine sand. Para 2.1.4.2 of the specification will be updated accordingly.
Question 11: The requirements for concrete removal on the east bank of Ronan Park are vague. Are you looking for all concrete pieces in the top 2' of the surface, bigger than 2' in any direction to be removed along the entire length of the bank, or just a few pieces in a particular location?
USACE Response Q11: All concrete pieces must be removed at the approximate location shown on Sheet CS115 and not along the entire length of the bank. An assumed depth of 2’ of less of concrete to be removed at this location is appropriate. It is recommended that bidders visit the site to review the proposed work.
Question 12: The plans and specification are deficient in discussing topsoil needs for these project: Can existing topsoil be reused or is all excavated material being hauled off site? What thickness is required for topsoil re-spread/import? Is the dumpsite at Big Marsh to be restored with new topsoil, or is that material to be stripped and re-spread?
USACE Response Q12: On-site topsoil must be reused for seeding. Section 31 00 00, Earthwork, specifies the requirements for topsoil stripping and placement. At the Big Marsh site, there will be no topsoil imported to the site nor stripping of topsoil on site. Seeds will be planted over the excess soil from River Riparian project area placed on the site.
Question 13: Boulder/Cobble Stone: Will it be acceptable to use quarried limestone for D50 and D100 size materials?
USACE Response Q13: Quarried limestones is not acceptable except as otherwise specified on the contract drawings and Section 35 31 19.52, Stream Bank Habitat.
Question 14: Bid item 1AH Channel Sediment Seeding, indicates the quantity to be 510 Tons. This is a lot of seed. Should this unit be in ounces like the other seeding items?
USACE Response Q14: Channel sediment seeding refers to the sand and gravel mix placement in the channel as defined in Section 35 31 19.52, Stream Habitat Restoration.
Question 15: There are a variety of Trees and Shrubs listed as being provided as plugs. Would bareroot be an acceptable alternative? The species Junus tenuis is listed in the Savanna Seed Mix as 25 oz/ac. Should this really be 0.25 oz/ac?
USACE Response Q15: Trees and shrubs sizes must follow the specifications listed in Section 32 93 00, Plants, paragraph 2.3.2. For more clarification, the “Restoration Species List” tables will be revised to remove the quantity of trees and shrubs from the plug columns and refer to the “Tree and Shrub Species List” table for trees and shrubs quantity. Quantity for Juncus tenuis should be 0.25 oz/ac. The plant list quantity in Section 32 93 00, Plants, will be updated accordingly.
Question 16: Note 3 on CS112 states fil and grading work within the river channel must be completed under dry conditions. Does that include from the dam to the East (Sta ~3+75 - 4+65)?
USACE Response Q16: The note 3 is correct, it also references Demolition Specs 02 41 00. In Paragraph 1.7, ...... Dam and concrete liner removal and stream channel restoration activities must be performed under dry conditions. In addition Specs 02 41 00 paragraph 3.2(5)(c), "water must be isolated from the in-stream work area using a cofferdam constructed of nonerodible materials". Any equipment placed into the channel to perform the dam removal work, in order to comply with paragraph 02 41 00 paragraph 3.2(5)(d), the contractor's work area had to be dry. The same requirement for demo work applies for East or/and West Side of the dam.
END OF QUESTIONS AND ANSWERS
H. POINT OF CONTACT: The Point of Contact (POC) for this Amendment is Ericka Hillard at (312) 846-5378; email ericka.d.hillard@usace.army.mil.
END OF AMENDMENT
(The aforementioned Wage Determination, Revised Bid Schedule, Revised Plans and Revised Specifications follow) mailto:ericka.d.hillard@usace.army.mil
Section 00010 - Solicitation Contract Form
REVISED BID SCHEDULE (VIA AMENDMENT 0002)
ITEM
NO
SUPPLIES/SERVI
CES
QUANTITY UNIT UNIT PRICE AMOUNT
RIVER PARK - BASE WORK
FFP
Bidders shall provide their pricing at sub-items 0001AA through 0001AT, as this Item 0001 identifies the information that relates directly to sub-items 0001AA through 0001AT. Therefore, this Item 0001 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0001 is not to be separately priced for payment purposes.
PURCHASE REQUEST NUMBER: W81G6671388022
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AA 1 Job
MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.
0001AB 1 Job
DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0001AC 1 Job
TEMPORARY CONSTRUCTION FACILITIES
FFP
0001AD 1 Job
MAINTENANCE OF TRAFFIC
0001AE 1 Job
DEMOLITION AND REMOVAL
0001AF 1 Job
EARTHWORK
0001AG 3,500 Cubic
Yard
SOIL PLACEMENT AT BIG MARSH
0001AH 510 Net Ton
(2,000
LB).
CHANNEL SEDIMENT SEEDING
0001AJ 1,800 Net Ton
CHANNEL IMPROVEMENT-SAND AND PEA GRAVEL
0001AK 4,100 Net Ton
CHANNEL IMPROVEMENT - COBBLE
0001AL 1,120 Net Ton
CHANNEL IMPROVEMENT - IDOT RR-3
0001AM 610 Net Ton
CHANNEL IMPROVEMENT - IDOT CA-6
0001AN 680 Linear
Foot
NATURAL FIBER LOG
0001AP 45 Linear
PLAYGROUND ASPHALT PATH
0001AQ 1 Job
ORNAMENTAL GATE
0001AR 50 Linear
STEEL SHEET PILE, PZ-22
0001AS 300 Ounce -
Av
SEEDS - BIG MARSH
0001AT 1 Lot
PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0001AA THROUGH 00001AS.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions associated with contract price changes.
OPTION GROUP 1 OPTIONS - RIVER PARK
FFP
Bidders shall provide their pricing at sub-items 0002AA through 0002BB, as this Item 0002 identifies the information that relates directly to sub-items 0002AA through 0002BB. Therefore, this Item 0002 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0002 is not to be separately priced for payment purposes.
0002AA 1 Job
OPTION MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0002AB 1 Job
OPTION DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0002AC 1 Job
OPTION MAINTENANCE OF TRAFFIC
0002AD 1 Job
OPTION DEMOLITION AND REMOVAL
0002AE 1 Job
OPTION CLEARING AND GRUBBING
0002AF 1 Job
OPTION EARTHWORK
0002AG 5,100 Cubic
OPTION SOIL PLACEMENT AT BIG MARSH
0002AH 730 Linear
OPTION 2-FT MULCH TRAIL
0002AJ 700 Net Ton
OPTION WOODY BANK HABITAT, IDOT RR-7 -FIRST 700
WOODY BANK HABITAT, IDOT RR-7 - FIRST 700 TONS
0002AK 490 Net Ton
OPTION WOODY BANK HABITAT, IDOT RR-7 - OVER 700
WOODY BANK HABITAT, IDOT RR-7 - OVER 700 TONS; FOR AN
ADDITIONAL 490 TONS.
0002AL 700 Net Ton
OPTION WOODY BANK HABITAT, COBBLE
0002AM 330 Net Ton
OPTION WATER WILLOW COBBLE BAR
0002AN 5 Acre
OPTION PRESCRIBED BURN
0002AP 1,126 Ounce -
OPTION SEEDS FOR BANK
0002AQ 1,029 Ounce -
OPTION SEEDS FOR SAVANNA
0002AR 440 Ounce -
OPTION SEEDS FOR BIG MARSH
0002AS 888 Each
OPTION PLUGS FOR BANK
0002AT 5,952 Each
OPTION PLUGS FOR SAVANNA
0002AU 1,687 Each
OPTION PLUGS FOR WETLAND SHELF
0002AV 600 Each
OPTION PLUGS FOR WATER WILLOW COBBLE BAR
0002AW 45 Each
OPTION 1.5" CALIPER TREES
0002AX 91 Each
OPTION 5 GALLON SHRUBS/TREES
0002AY 6,180 Linear
OPTION LANDSCAPE FENCE
0002AZ 1 Job
OPTION FLAGSTONE OBSERVATION AREA AND ACCESS
0002BA 1 Job
OPTION SITE PREPARATION, ETC.
FFP
SITE PREPARATION, INVASIVE SPECIES CONTROL, AND
ESTABLISHMENT ACTIVITIES
0002BB 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0002AA THROUGH 0002BA.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
OPTION GROUP 2 OPTIONS - RONAN PARK
FFP
Bidders shall provide their pricing at sub-items 0003AA through 0003AQ, as this Item 0003 identifies the information that relates directly to sub-items 0003AA through 0003AQ. Therefore, this Item 0003 is not to be scheduled separately for
Item 0003 is not to be separately priced for payment purposes.
0003AA 1 Job
OPTION MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions:
The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer or its Representative may require the Contractor to furnish cost data to justify its submitted price for this item if the Contracting Officer deems there's no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0003AB 1 Job
OPTION DEMOBILIZATION
FFP
Under this CLIN, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions:
The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer or its Representative may require the Contractor to furnish cost data to justify its submitted price for this item if the Contracting Officer deems there's no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0003AC 1 Job
0003AD 6 Acre
0003AE 1,100 Linear
OPTION 2 FT MULCH TRAIL
0003AF 1 Job
OPTION DEBRIS REMOVAL
0003AG 248 Ounce -
OPTION SEEDS FOR ENHANCEMENT
0003AH 788 Ounce -
0003AJ 10,204 Each
OPTION PLUGS FOR ENHANCEMENT
0003AK 4,557 Each
0003AL 13 Each
0003AM 4 Each
0003AN 2,930 Linear
0003AP 1 Job
OPTION SITE PREPARATION, ETC.
FFP
0003AQ 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0003AA THROUGH 0003AP.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
OPTION GROUP 3 OPTIONS - LEGION PARK SOUTH
FFP
Bidders shall provide their pricing at sub-items 0004AA through 0004BC, as this Item 0004 identifies the information that relates directly to sub-items 0004AA through 0004BC. Therefore, this Item 0004 is not to be scheduled separately for
Item 0004 is not to be separately priced for payment purposes.
0004AA 1 Job
OPTION MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0004AB 1 Job
OPTION DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0004AC 1 Job
0004AD 1 Job
0004AE 1 Job
0004AF 1 Job
0004AG 9,100 Cubic
0004AH 810 Net Ton
OPTION FLAGSTONE RETAINING WALL
0004AJ 500 Net Ton
OPTION IDOT CA-7 STONES - FIRST 500 TN
0004AK 200 Net Ton
OPTION IDOT CA-7 STONES - OVER 500 TN
IDOT CA-7 STONES - OVER 500 TN; ADDITIONAL 200 TONS.
0004AL 900 Net Ton
0004AM 630 Linear
OPTION 2FT MULCH TRAIL
0004AN 6 Acre
0004AP 2,380 Ounce -
0004AQ 1,209 Ounce -
0004AR 786 Ounce -
0004AS 1,876 Each
0004AT 6,997 Each
0004AU 2,636 Each
0004AV 1,413 Each
OPTION PLUGS FOR WATER WILLOW COBBLE BAR
0004AW 80 Each
0004AX 187 Each
0004AY 5,810 Linear
0004AZ 595 Linear
OPTION PERMANENT CHAINLINK FENCE
0004BA 1 Job
OPTION ORNAMENTAL FENCE
0004BB 1 Job
OPTION SITE PREPARATION, ETC.
FFP
0004BC 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0004AA THROUGH 0004BB.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
OPTION GROUP 4 OPTIONS-LEGION PARK NORTH, E.B.
FFP
GROUP 4 OPTIONS - LEGION PARK NORTH, EAST BANK. Bidders shall provide their pricing at sub-items 0005AA through 0005AW, as this Item 0005 identifies the information that relates directly to sub-items 0005AA through 0005AW. Therefore, this Item 0005 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0005 is not to be separately priced for payment purposes.
0005AA 1 Job
OPTION MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0005AB 1 Job
OPTION DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0005AC 1 Job
0005AD 1 Job
0005AE 1 Job
0005AF 1 Job
0005AG 10,900 Cubic
0005AH 1,300 Cubic
OPTION EXCESS MATERIAL DISPOSAL OFFSITE
0005AJ 1,100 Linear
0005AK 7.50 Acre
0005AL 3,124 Ounce -
0005AM 1,267 Ounce -
OPTION SEEDS FOR SAVANNAH
0005AN 349 Ounce -
0005AP 2,463 Each
0005AQ 7,330 Each
OPTION PLUGS FOR SAVANNAH
0005AR 3,111 Each
0005AS 99 Each
0005AT 244 Each
OPTION 5-GALLON SHRUBS/TREES
0005AU 6,250 Linear
0005AV 1 Job
OPTION SITE PREPARATION, ETC.
FFP
SITE PREPARATION, INVASIVE SPECIES CONTRO, AND
0005AW 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0005AA THROUGH 0005AV.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
OPTION GROUP 5 OPTIONS -LEGION PARK NORTH, W.B.
FFP
GROUP 5 OPTIONS - LEGION PARK NORTH, WEST BANK. Bidders shall provide their pricing at sub-items 0006AA through 0006BA, as this Item 0006 identifies the information that relates directly to sub-items 0006AA through 0006BA. Therefore, this Item 0006 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0006
0006AA 1 Job
OPTION MOBILIZATION
FFP
Under this line item, the contractor is required to perform mobilization activities.
The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0006AB 1 Job
OPTION DEMOBILIZATION
FFP
Under this line item, the contractor is required to perform demobilization activities.
The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force from the project site.
Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment
0006AC 1 Job
0006AD 1 Job
0006AE 1 Job
0006AF 1 Job
0006AG 9,500 Cubic
0006AH 1,400 Net Ton
0006AJ 1,000 Net Ton
OPTION WOODY BANK HABITAT, IDOT RR-3-FIRST 1000
WOODY BANK HABITAT, IDOT RR-3 - FIRST 1000 TONS
0006AK 680 Net Ton
OPTION WOODY BANK HABITAT, IDOT RR-3 - OVER 100
WOODY BANK HABITAT, IDOT RR-3 - OVER 1000; ADDITIONAL 680
TONS.
0006AL 900 Net Ton
OPTION WOODY BANK HABITAT, COBBLE
0006AM 450 Linear
0006AN 1,150 Linear
OPTION ASPHALT TRAIL REPLACEMENT
0006AP 9.80 Acre
0006AQ 2,625 Ounce -
0006AR 2,370 Ounce -
0006AS 817 Ounce -
0006AT 2,070 Each
0006AU 13,713 Each
OPTION PLUGS FOR SAVANNAH
0006AV 2,620 Each
0006AW 1,200 Each
OPTION PLUGS FOR WATER WILLOW COBBLER BAR
0006AX 105 Each
0006AY 212 Each
OPTION 5-GALLON SHRUBS/TREES
0006AZ 8,350 Linear
0006BA 1 Job
OPTION SITE PREPARATION, ETC.
FFP
0006BB 1 Lot
OPTION PERFORMANCE AND PAYMENT BONDS
FFP
THIS IS A REIMBURSABLE LINE ITEM FOR BOND COVERAGE FOR LINE
ITEMS 0006AA THROUGH 0006BA.
The Government will reimburse the Contractor for the actual cost of acceptable bonds upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the
0007 1 Job
OPTION GOVT. ALLOWANCE - ADAPTIVE MANAGEMENT
FFP
GOVERNMENT PRICE ALLOWANCE FOR ADAPTIVE MANAGEMENT. -
Adaptive Management applies where remedial actions is necessary, as determined by the COR, to address significant deficiencies of the instream habitat features within the base and option project areas and in accordance to Section 35 31 19.52 STREAM HABITAT RESTORATION. This allowance is a reimbursable item and not to exceed $25,000. Payments will be reimbursed in an amount for accepted work orders approved by the COR. (1) The Contractor shall NOT incur any additional costs or perform any additional services outside of the ceiling price established hereunder. Should the Contractor determine that the allocated amount is insufficient because additional related services are deemed necessary, the government may negotiate a fair and reasonable price with the contractor to make price adjustments to the Contract. (2) The Contractor shall coordinate all services with the Contracting Officer's Representative (COR) such that compliance with the ceiling price of this item and the tasks performed, the associated level of effort, and scheduling can be verified. (3) The COR is responsible for processing payments.
The contractor shall provide the COR with paid invoices and all other supporting cost information (Labor, travel, per Diem, subcontractor costs, etc.) For the verification of the Contractor's expenditures for this line item. ANY UNUSED
BALANCE WILL BE DEOBLIGATED AT THE END OF THE CONTRACT
PERIOD.
OPTION VERNAL POOL EROSION PROTECTION
FFP
VERNAL POOL EROSION PROTECTION. The option items described below will be exercised in the event there is active seepage, as determined by the COR, during grading activities along the river banks within the option project areas.
Bidders shall provide their pricing at sub-items 0008AA AND 0008AB, as this Item 0008 identifies the information that relates directly to sub-items 0008AA and 0008AB. Therefore, this Item 0008 is not to be scheduled separately for delivery, nor is it to be identified separately for shipment or performance. Further, Item 0008
0008AA 60 Net Ton
OPTION FIRST 60 TONS
VERNAL POOL EROSION PROTECTION - FIRST 60 TON.
0008AB 30 Net Ton
OPTION
VERNAL POOL EROSION PROTECTION - OVER 60 TONS; ADDITIONAL
30 TONS.
SUMMATION OF BID PRICES
SUM FOR BASE BID ITEMS 0001AA THROUGH 0001AT $____________
SUM FOR OPTION GROUP 1 – BID ITEMS 0002AA THROUGH $____________
0002BB (RIVER PARK)
SUM FOR OPTION GROUP 2 – BID ITEMS 0003AA THROUGH $____________
0003AR (RONAN PARK)
SUM FOR OPTION GROUP 3 – BID ITEMS 0004AA THROUGH $____________
0004BC (LEGION PARK SOUTH)
SUM FOR OPTION GROUP 4 – BID ITEMS 0005AA THROUGH $____________
0005AW (LEGION PARK NORTH - EAST BANK)
SUM FOR OPTION GROUP 5 – BIG ITEMS 0006AA THROUGH $____________
0006BB (LEGION PARK NORTH - WEST BANK)
BID FOR ITEM 0007 – GOVERNMENT PRICE ALLOWANCE FOR $25,000.00
ADAPTIVE MANAGEMENT
IMPORTANT NOTE: THE AMOUNT OF THIS PRICE ALLOWANCE SHALL BE INCLUDED IN THE
BIDDER’S TOTAL PRICE.
SUM FOR CLIN 0008 – 0008AA AND 0008AB $____________
(Option items for vernal pool erosion)
TOTAL OVERALL BID PRICE, ITEMS 0001AA THROUGH 0008AB (Inclusive of all biddable items and subitems plus the Government Price Allowance of $25K)
END OF REVISED BID SCHEDULE
In accordance with the above Paragraph F, below is the updated Wage Determination:
General Decision Number: IL170009 09/15/2017 IL9
Superseded General Decision Number: IL20160009
State: Illinois
Construction Types: Building, Heavy, Highway and Residential
County: Cook County in Illinois.
BUILDING, RESIDENTIAL, HEAVY, AND HIGHWAY PROJECTS (does not include landscape projects).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.
The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/06/2017 1 01/13/2017 2 01/27/2017 3 02/24/2017 4 04/07/2017 5 04/28/2017 6 05/05/2017 7 06/02/2017 8 06/09/2017 9 06/23/2017 10 06/30/2017 11 07/07/2017 12 07/21/2017 13 07/28/2017 14 08/04/2017 15 08/25/2017 16 09/08/2017 17 09/15/2017
* ASBE0017-001 06/01/2017
Rates Fringes
ASBESTOS WORKER/INSULATOR
Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems..........$ 50.50 25.80 Fire Stop Technician.............$ 40.40 24.54
HAZARDOUS MATERIAL HANDLER
includes preparation, wetting, stripping removal scrapping, vacuuming, bagging and disposal of all insulation materials, whether they contain asbestos or not, from mechanical systems..........$ 37.80 24.54
BOIL0001-001 05/01/2017
Rates Fringes
BOILERMAKER......................$ 46.18 29.58
BRIL0021-001 06/01/2016
Rates Fringes
BRICKLAYER.......................$ 44.88 26.62
BRIL0021-004 06/01/2017
Rates Fringes
Marble Mason.....................$ 44.63 26.83
BRIL0021-006 06/01/2017
Rates Fringes
TERRAZZO WORKER/SETTER...........$ 44.38 25.14
TILE FINISHER....................$ 38.56 22.10
TILE SETTER......................$ 45.49 24.91
BRIL0021-009 06/01/2017
Rates Fringes
MARBLE FINISHER..................$ 33.95 26.03
BRIL0021-012 06/01/2017
Rates Fringes
Pointer, cleaner and caulker.....$ 45.42 24.06
CARP0555-001 06/01/2017
BUILDING, HEAVY, AND HIGHWAY
Rates Fringes
CARPENTER
Carpenter, Lather, Millwright, Piledriver, and Soft Floor Layer Building...................$ 46.35 31.29 Heavy & Highway............$ 46.35 31.31
CARP0555-002 10/01/2016
RESIDENTIAL CONSTRUCTION
Rates Fringes
CARPENTER........................$ 36.11 30.02
ELEC0009-003 06/04/2017
Rates Fringes
Line Construction Groundman...................$ 39.39 61.37% Lineman and Equipment Operator....................$ 50.50 61.37%
ELEC0134-001 06/05/2017
Rates Fringes
ELECTRICIAN......................$ 47.40 32.21
ELEC0134-003 06/05/2017
Rates Fringes
ELECTRICIAN
ELECTRICAL TECHNICIAN.......$ 43.10 23.95
The work shall consist of the installation, operation, inspection, maintenance, repair and service of radio, television, recording, voice sound vision production and reproduction, telephone and telephone interconnect, facsimile, data appatatus, coaxial, fibre optic and wireless equipment, appliances and systems used for the transmission and reception of signals of any nature, business, domestic, commercial, education, entertainment and residential purposes, including but not limited to communication and telephone, electronic and sound equipment, fibre optic and data communication systems, and the performance of any task directly related to such installation or service whether at new or existing sites, such tasks to include the placing of wire and cable and electrical power conduit or other raceway work within the equipment room and pulling wire and/or cable through conduit and the installation of any incidential conduit.
ELEV0002-001 01/01/2017
Rates Fringes
ELEVATOR MECHANIC................$ 53.18 31.585+a+b
FOOTNOTES:
a) PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Day after Thanksgiving Day; Veterans' Day and Christmas Day.
b) Employer contributes 8% of regular hourly rate as vacation pay credit for employee with more than 5 years of service, and 6% for employee with less than 5 years service
* ENGI0150-006 06/01/2017
Building and Residential Construction
Rates Fringes
OPERATOR: Power Equipment
GROUP 1....................$ 50.10 36.45
GROUP 2....................$ 48.80 36.45
GROUP 3....................$ 46.25 36.45
GROUP 4....................$ 44.50 36.45
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Mechanic; Asphalt Plant*; Asphalt Spreader;
Autograde*; Backhoes with Caisson attachment*:Batch Plant*;
Benoto(Requires two Engineers); Boiler and Throttle Valve;
Caisson Rigs*; Central Redi-Mix Plant*; Combination Backhoe Front Endloader Machine; Compressor and Throttle Valve;
Concrete Breaker (Truck Mounted)*; Concrete Conveyor;
Concrete Conveyor, Truck Mounted; Concrete Paver over 27E
cu. ft.*; Concrete Paver 27E cu ft and Under*; Concrete Placer*; Concrete Placing Boom; Concrete Pump (Truck Mounted); Concrete Tower; Cranes*; Cranes, Hammerhead*;
Cranes, (GCI and similar type Requires two operators only);
Creter Crane; Crusher, Stone, etc; Derricks; Derricks, Traveling*; Formless Curb and Gutter Machine*; Grader, Elevating; Grouting Machines; Highlift Shovels or Front Endloader 2 1/4 yd. and over; Hoists, Elevators, Outside Type Rack and pinion and similar Machines; Hoists, One, Two, and Three Drum; Hoists, Two Tugger One Floor;
Hydraulic Backhoes*; Hydraulic Boom Trucks; Hydraulic Vac (and similar equipment);Locomotives; Motor Patrol*; Pile
Drivers amd Skid Rig*; Post Hole Digger; Pre- Stress Machine; Pump Cretes Dual Ram(Requiring frequent Lubrication and Water); Pump Cretes; Squeeze Cretes-Screw Type Pumps Gypsum Bulker and Pump; Raised and Blind Hole Drill*; Roto Mill Grinder (36" and Over)*; Roto Mill Grinder (Less Than 36")*; Scoops-Tractor Drawn; Slip-Form Paver*; Straddle Buggies; Tournapull; Tractor with Boom, and Side Boom; and Trenching Machines*.
GROUP 2: Bobcat (over 3/4 cu yd); Boilers; Broom, Power Propelled; Bulldozers; Concrete Mixer (Two Bag and over);
Conveyor, Portable; Forklift Trucks; Greaser Engineer;
Highlift Shovels or Front End loaders under 2 1/4 cu yd;
Aotomatic Hoists, Hoists, Inside Elevators; Hoists, Sewer Dragging Machine; Hoists, Tugger Single Drum; Laser Screed;
Rock Drill (Self-Propelled); Rock Drill (Truck Mounted)*;
Rollers; Steam Generators; Tractors; Tractor Drawn Vibratory Roller (Receives an additional $.50 per hour);
Winch Trucks with "A" Frame.
GROUP 3: Air Compressor-Small 250 and Under (1 to 5 not to exceed a total of 300 ft); Air Compressor-Large over 250;
Combination-Small Equipment Operator; Generator- Small 50 kw and under; Generator-Large over 50 kw; Heaters, Mechanical; Hoists, Inside Elevators (Remodeling or Renovatin work); Hydrualic Power Units (Pile Driving, Extracting, and Drilling); Low Boys; Pumps Over 3" (1 To 3 not to exceed a total of 300 ft); Pumps, Well Points;
Welding Machines (2 through 5); Winches, 4 Small Electric Drill Winches; Bobcat (up to and including 3/4 cu yd)
GROUP 4 - Bobcats and/or other Skid Steer Loaders; Brick Forklifts; Oilers
*-Requires Oiler
* ENGI0150-025 06/01/2017
Heavy and Highway Construction
Rates Fringes
OPERATOR: Power Equipment
GROUP 1.....................$ 48.30 36.45
GROUP 2.....................$ 47.75 36.45
GROUP 3.....................$ 45.70 36.45
GROUP 4.....................$ 44.30 36.45
GROUP 5.....................$ 43.10 36.45
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt Plant*; Asphalt Heater and Planer combination; Asphalt Heater Scarfire*, Asphalt Spreader;
Autograder/ GOMACO or similar; ABG Paver*, Backhoes with Caisson attachment*, Ballast Regulator, Belt Loader*;
Caisson Rigs*Car Dumper, Central Redi-Mix Plant*, Combination Backhoe; Front End Loader Machine (1 cu yd or over Backhoe bucket or with attachments); Concrete Breaker (truck mounted); Concrete Conveyor; Concrete Paver over 27E cu ft*; Concrete Placer*; Concrete Tube Float; Cranes, all attachments*; Cranes, Hammerhead, Linden, Peco and machines of a like nature*; Creter Crane; Crusher, stone; All Derricks; Derrick Boats; Derricks, traveling*; Dowell Machine with Air Compressor ($1.00 above Class 1);
Dredges*; Field Mechanic Welder; Formless Curb and Gutter Machine*; Gradall and machines of a like nature*; Grader, Elevating; Grader, Motor Grader, Motor Patrol, Auto Patrol, Form Grader, Pull Grader, Subgrader; Guard Rail Post Driver mounted*; Hoists, one, two, and three Drum; Hydraulic Backhoes*; Backhoes with Shear attachments*; Mucking Machine; Pile Drivers and Skid Rig*; Pre-Stress Machine;
Pump Cretes Dual Ram (requires frequent lubrication and water)*; Rock Drill- Crawler or Skid Rig*; Rock Drill truck mounted*; Rock/ Track Tamper; Roto Mill Grinder, (36" and over)*; Slip-Form Paver*; Soil Test Drill Rig, truck mounted*; Straddle Buggies; Hydraulic Telescoping Form (tunnel); Tractor Drawn Belt Loader*; Tractor Drawn Belt Loader with attached Pusher (two engineers); Tractor with boom; Tractaire with attachment; Traffic Barrier Transfer Machine*; Trenching Machine; Truck Mounted Concrete Pump with boom*; Underground Boring and/or Mining Machines 5 ft in diameter and over tunnel, etc.*; Wheel Excavator* & Widener (Apsco); Raised or Blind Hoe Drill, Tunnel & Shaft*
GROUP 2: Batch Plant*; Bituminous Mixer; Boiler and Throttle Valve; Bulldozer; Car Loader Trailing Conveyors;
Combination Backkhoe Front End Loader Machine, (less than 1 cu yd Backhoe Bucket with attachments); Compressor and Throttle Valve; Compressor, common receiver (3); Concrete Breaker or Hydro Hammer; Concrete Grinding Machine;
Concrete Mixer or Paver 7S series to and including 27 cu ft; Concrete Spreader; Concrete Curing Machine; Burlap Machine; Belting Machine and Sealing Machine; Concrete Wheel Saw; Conveyor Muck Cars (Haglund or similar type);
Drills (all); Finishing Machine-Concrete; Greaser Engineer;
Highlift Shovels or Front End Loader; Hoist- Sewer Dragging Machine; Hydraulic Boom Trucks, all attachments;
Hydro-Blaster (requires two operators); Laser Screed*;
Locomotives, Dinky; Off-Road Hauling Units (including articulating); Pump Cretes; Squeeze Cretes-Screw Type pumps, Gypsum Bulker and Pump; Roller Asphalt; Rotary Snow Plows; Rototiller, Seaman, self-Propelled; Scoops-Tractor Drawn; Self- propelled Compactor; Spreader-Chip-Stone;
Scraper; Scraper-Prime Mover in Tandem regardless of size (add $1.00 to Group 2 hourly rate for each hour and for each machine attached thereto add $1.00 to Group 2 hourly rate for each hour); Tank Car Heater; Tractors, Push, pulling Sheeps Foot, Disc, or Compactor, etc; Tug Boats
GROUP 3: Boilers; Brooms, all power propelled; Cement Supply Tender; Compressor, Common Receiver (2); Concrete Mixer, two bag and over; Conveyor, Portable; Farm type Tractors used for…