Solicitation No. W912P519B0008
US Army Corps Of Engineers Nashville District
CABLE TRAYS REPLACEMENT
Dale Hollow Dam Clay County, Tennessee
Technical Specifications
Ready to advertise
April 2019
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Cable Trays Replacement Dale Hollow Dam W912P519B0008 Clay County, Tennessee
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 22 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION OF EXISTING CABLE TRAYS
02 82 14 ASBESTOS ABATEMENT WORK
DIVISION 26 - ELECTRICAL
26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 LOCATION AND ACCESS
1.2.1 Location
1.2.2 Powerhouse Point of Contact
1.2.3 Access to Site
1.3 COORDINATION CONFERENCES
1.3.1 SCHEDULE COORDINATION MEETING
1.4 CONTRACTOR'S STAGING AREA
1.5 DAILY CLEANUP AND DISPOSAL
1.6 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.7 EVALUATION OF CONTRACTOR PERFORMANCE
1.8 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.9 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 General
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.2.1 Contractor Responsibilities
3.2.2 Interruptions of Utilities
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
1.2 LOCATION AND ACCESS
1.2.1 Location
Dale Hollow Dam Powerhouse 305 Powerhouse Road Celina Tennessee 38551
1.2.2 Powerhouse Point of Contact
Stanley Carter Phone Number: (931) 243-3135
1.2.3 Access to Site
The contractor will only be allowed to work between the hours of 0700 and 1630, Monday - Thursday. Special crcumstannces will be considered as they arise. The contractor shall determine the on-site delivery location and storage location for any materials related to the project with the powerhouse point of contact.
1.3 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.3.1 SCHEDULE COORDINATION MEETING
The Contractor shall participate in a schedule coordination meeting with the Government. The schedule coordination meeting shall occur prior to the submission of the preliminary project schedule. The Contracting Officer will schedule this meeting. Unless the Contracting Officer determines a face-to-face meeting is necessary, the schedule coordination meeting shall be conducted via teleconference using a Government provided conference number. Attendance by the Contractor's site superintendent, quality control manager, project manager, and project scheduler is mandatory. The
SECTION 01 00 00 Page 2 intent of this meeting is for the Contractor to ask relevant questions about the format of the baseline schedule, the structure of the schedule, necessary cost loaded activities, or any other questions which may arise with respect to the Contractor's project schedule. If the Contractor presents no questions to the Government, then the Government will verbally reiterate the contract requirements related to the project schedule.
1.4 CONTRACTOR'S STAGING AREA
The staging/laydown and storage area will be provided. Details will be provided after contract award as multiple contractors will be on site. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.5 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.6 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.7 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov. This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
SECTION 01 00 00 Page 3
1.8 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information: www.fedshirevets.gov/index.aspx
c. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
e. U.S. Army Warrior Transition Command Employment Index:
http://www.wct.army.mil/modules/employers/index.html
f. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
g. Guide to Hiring Veterans:
www.whitehouse.gov/sites/default/files/docs/white_house_business_council_ -_guide_to_hiring_veterans_0.pdf
1.9 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 General
During the course of this contract there will be multiple other Contractors, and power house personnel, working within the powerhouse and around the dam. The Contractor will make every effort to coordinate activities so as to avoid conflicts with the other Contractors or power house personnel. Any issues which arise, or are foreseen based on scheduled activities, shall be communicated to the Contractor Officer immediately."
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.2.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Electrical utilities will be provided for a trailer. An advance notice is needed for electrical utilities.
Powerhouse restrooms are authorized for use by the contactor and the contractor must assist in maintaining cleaniness. The contractor is
SECTION 01 00 00 Page 4 required to provide their own internent/hotspot. The contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.
3.2.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
e. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
-- End of Section --
SECTION 01 00 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
1.1.1 Performance and Payment Bonds (Base Contract)
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Demolition and Installation of Cable Trays (Base Contract)
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Asbestos Abatement (Base Contract)
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Performance and Payment Bonds for Cable Trays (Option 1)
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Demolition and Installation of Cable Trays (Option 1)
1.1.5.1 Payment
1.1.5.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
Payment items for the work of this contract are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Performance and Payment Bonds (Base Contract)
1.1.1.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.1.2 Unit of Measure
Unit of measure: Job.
1.1.2 Demolition and Installation of Cable Trays (Base Contract)
1.1.2.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays."
This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
SECTION 01 22 00 Page 2
1.1.2.2 Unit of Measure
Unit of measure: Linear Foot.
1.1.3 Asbestos Abatement (Base Contract)
1.1.3.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air monitoring personnel.
1.1.3.2 Unit of Measure
Unit of measure: Linear Foot.
1.1.4 Performance and Payment Bonds for Cable Trays (Option 1)
1.1.4.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.4.2 Unit of Measure
Unit of measure: Job.
1.1.5 Demolition and Installation of Cable Trays (Option 1)
1.1.5.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays." This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
SECTION 01 22 00 Page 3
1.1.5.2 Unit of Measure
Unit of measure: Linear Foot.
1.1.6 Asbestos Abatement for Cable Trays (Option 1)
1.1.6.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air monitoring personnel.
1.1.6.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.7 Performance and Payment Bonds for Cable Trays (Option 2)
1.1.7.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.7.2 Unit of Measure
Unit of measure: Job.
1.1.8 Demolition and Installation of Cable Trays (Option 2)
1.1.8.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays." This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
1.1.8.2 Unit of Measure
Unit of Measure: Linear Foot.
SECTION 01 22 00 Page 4
1.1.9 Asbestos Abatement for Cable Trays (Option 2)
1.1.9.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air monitoring personnel.
1.1.10 Performance and Payment Bonds for Cable Trays (Option 3)
1.1.10.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.10.2 Unit of Measure
Unit of Measure: Job.
1.1.11 Demolition and Installation of Cable Trays (Option 3)
1.1.11.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays." This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
1.1.11.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.12 Asbestos Abatement for Cable Trays (Option 3)
1.1.12.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be
SECTION 01 22 00 Page 5 made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air monitoring personnel.
1.1.12.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.13 Performance and Payment Bonds for Cable Trays (Option 4)
1.1.13.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.13.2 Unit of Measure
Unit of Measure: Job.
1.1.14 Demolition and Installation of Cable Trays (Option 4)
1.1.14.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays." This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
1.1.14.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.15 Asbestos Abatement for Cable Trays (Option 4)
1.1.15.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will
SECTION 01 22 00 Page 6 include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air monitoring personnel.
1.1.15.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.16 Performance and Payment Bonds for Cable Trays (Option 6)
1.1.16.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items.
1.1.16.2 Unit of Measure
Unit of Measure: Job.
1.1.17 Demolition and Installation of Cable Trays (Option 6)
1.1.17.1 Payment
Payment will be made for costs associated with removal of existing cable trays as specified in Section 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS as well as furnishing, transporting, delivering, and installing replacement cable trays as specified in Section 35 01 46 DALE HOLLOW DAM POWERHOUSE CABLE TRAY REPLACEMENT. Payment will be made at the contract price per linear foot of cable tray for "Demolition and Installation of Cable Trays." This payment includes consideration for removal, temporary support of existing cables, disposal offsite, furnishing, transporting, delivering, and installing replacement cable trays.
1.1.17.2 Unit of Measure
Unit of Measure: Linear Foot.
1.1.18 Asbestos Abatement of Cable Trays (Option 6)
1.1.18.1 Payment
Payment will be made for costs associated with asbestos abatement as specified in Section 02 82 14 ASBESTOS ABATEMENT WORK. Payment will be made at the contract price per Linear Foot for "Asbestos Abatement." This payment includes full compensation for furnishing all materials, equipment, and labor required to remove all asbestos containing materials. This will include consideration for all costs associated with bulk sampling, testing, submittal preparation, asbestos work mobilization and demobilization, disposal of ACM, and services of certified asbestos abatement and air
SECTION 01 22 00 Page 7 monitoring personnel.
1.1.18.2 Unit of Measure
Unit of Measure: Linear Foot.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Contractor Software
2.1.1.1 Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Contract Milestones and Constraints
3.3.6.1 Project Start Date Milestone
3.3.6.2 End Project Finish Milestone
3.3.7 Calendars
3.3.8 Open Ended Logic
3.3.9 Default Progress Data Disallowed
3.3.10 Out-of-Sequence Progress
3.3.11 Added and Deleted Activities
3.3.12 Original Durations
3.3.13 Leads, Lags, and Start to Finish Relationships
3.3.14 Retained Logic
3.3.15 Percent Complete
3.3.16 Remaining Duration
3.3.17 Cost Loading of Closeout Activities
3.3.17.1 As-Built Drawings
3.3.18 Anticipated Adverse Weather
3.3.19 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
SECTION 01 32 01 Page 1
3.5.1 Narrative Report
3.5.2 Schedule Reports
3.5.2.1 Activity Report
3.5.2.2 Logic Report
3.5.2.3 Total Float Report
3.5.2.4 Earnings Report by CLIN
3.5.3 Network Diagram
3.5.3.1 Continuous Flow
3.5.3.2 Project Milestone Dates
3.5.3.3 Critical Path
3.5.3.4 Banding
3.5.3.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Contractor Software
Scheduling software used by the contractor must be capable of meeting all
SECTION 01 32 01 Page 3 requirements of this specification.
2.1.1.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
SECTION 01 32 01 Page 4
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Long procurement activities
d. Submission and approval of as-built drawings.
e. Contractor's pre-final inspection.
f. Correction of punch list from Contractor's pre-final inspection.
g. Government's pre-final inspection.
h. Correction of punch list from Government's pre-final inspection.
i. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
SECTION 01 32 01 Page 5
3.3.6.1 Project Start Date Milestone
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged,"
3.3.6.2 End Project Finish Milestone
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.
3.3.8 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.9 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
SECTION 01 32 01 Page 6
3.3.10 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.11 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.12 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.13 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.14 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.15 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.16 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
SECTION 01 32 01 Page 7
3.3.17 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.17.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18 Anticipated Adverse Weather
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
3.3.19 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining
SECTION 01 32 01 Page 8 performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.
3.4.3 Periodic Schedule Updates
Update the Project Schedule on a regular basis, monthly at a minimum.
Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.
These updates will enable the Government to assess Contractor's progress.
a. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete is subject to the approval of the Government at the meeting.
b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.
3.5 SUBMISSION REQUIREMENTS
Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.5.1 Narrative Report
Provide a Narrative Report with each schedule submission. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for any problems, either current or potential, which are revealed through that analysis. Include the following information as minimum in the Narrative Report:
a. Identify and discuss the work scheduled to start in the next update period.
b. A description of activities along the two most critical paths where the total float is less than or equal to 20 work days.
c. A description of current and anticipated problem areas or delaying factors and their impact and an explanation of corrective actions taken or required to be taken.
SECTION 01 32 01 Page 9
d. Identify and explain why activities based on their calculated late dates should have either started or finished during the update period but did not.
e. Identify and discuss all schedule changes by activity ID and activity name including what specifically was changed and why the change was needed. Include at a minimum new and deleted activities, logic changes, duration changes, calendar changes, lag changes, resource changes, and actual start and finish date changes.
f. Identify and discuss out-of-sequence work.
3.5.2 Schedule Reports
The format, filtering, organizing and sorting for each schedule report will be as directed by the Contracting Officer. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format. Provide 2 set(s) of hardcopy reports. The following lists typical reports that will be requested:
3.5.2.1 Activity Report
List of all activities sorted according to activity number.
3.5.2.2 Logic Report
List of detailed predecessor and successor activities for every activity in ascending order by activity number.
3.5.2.3 Total Float Report
A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.
3.5.2.4 Earnings Report by CLIN
A compilation of the Total Earnings on the project from the NTP to the data date, which reflects the earnings of activities based on the agreements made in the schedule update meeting defined herein. Provided a complete schedule update has been furnished, this report serves as the basis of determining progress payments. Group activities by CLIN number and sort by activity number. Provide a total CLIN percent earned value, CLIN percent complete, and project percent complete. The printed report must contain the following for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Earnings to Date, Earnings this period, Total Quantity, Quantity to Date, and Percent Complete (based on cost).
3.5.3 Network Diagram
The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review
SECTION 01 32 01 Page 10 compliance with this paragraph:
3.5.3.1 Continuous Flow
Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.
3.5.3.2 Project Milestone Dates
Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.
3.5.3.3 Critical Path
Show all activities on the critical path. The critical path is defined as the longest path.
3.5.3.4 Banding
Organize activities using the WBS or as otherwise directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.
3.5.3.5 Cash Flow / Schedule Variance Control (SVC) Diagram
With each schedule submission, provide a SVC diagram showing 1) Cash Flow…