W912P5-16-R-0004_TSpecs.pdf

PDF 4 MB Posted

Attached to
Excitation Equipment Replacement Federal contract opportunity
Solicitation number
W912P5-16-R-0004
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

Technical Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Excitation Equipment Replacement, newest first.
File Type Posted
W912P5-16-R-0004_Plans-Am1Sheets.pdf PDF
W912P5-16-R-0004_TSpecs-Am1Pages.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
W912P5-16-R-0004-0001.pdf PDF
W912P5-16-R-0004_Plans2_Reference_Drawings.pdf PDF
W912P5-16-R-0004_Plans1_Contract_Drawings.pdf PDF
Foreign_National_Security_Site_Visit_Form.pdf PDF
W912P5-16-R-0004_TSpecsAppA.pdf PDF
Site_Visit_Request_Form.pdf PDF
W912P5-16-R-0004_TSpecsAppB.pdf PDF
W912P5-16-R-0004_.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. W912P5-16-R-0004

US Army Corps Of Engineers Nashville District

EXCITER EQUIPMENT REPLACEMENT

Barkley Power Plant Lyon County, Kentucky

Technical Specifications

July 2016

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Exciter Equipment Replacement Barkley Power Plant W912P5-16-R-0004 Lyon County, Kentucky

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 10 STATEMENT OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01 QUALITY CONTROL

01 45 02 QUALITY CONTROL SYSTEM (QCS)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATIONS AND MAINTENANCE DATA

01 95 00 FORMS AND ATTACHMENTS

DIVISION 02 - EXISTING CONDITIONS

02 82 14 ASBESTOS ABATEMENT

DIVISION 03 - CONCRETE

03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND

EQUIPMENT FOUNDATIONS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

DIVISION 26 - ELECTRICAL

26 25 00.00 26 BUS STRUCTURES

DIVISION 48 - ELECTRICAL POWER GENERATION

48 19 00.00 26 DIGITAL EXCITERS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.2 SITE WORKING HOURS

1.2.1 Government Project Personnel Working Hours

1.2.2 Contractor's Working Hours

1.3 COORDINATION CONFERENCES

1.4 PARTNERING

1.5 REFERENCES

1.6 PROJECT SIGNS

1.7 CONTRACTOR'S STAGING AREAS

1.8 SAFE CLEARANCE PROCEDURES

1.9 DAILY CLEANUP AND DISPOSAL

1.10 STORAGE OF EQUIPMENT AND MATERIALS

1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.12 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

1.13 EVALUATION OF CONTRACTOR PERFORMANCE

1.14 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.15 MEASUREMENT AND PAYMENT

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

3.1.2 Interruptions of Utilities

3.1.3 Installation Procedure

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.

1.2 SITE WORKING HOURS

1.2.1 Government Project Personnel Working Hours

The scheduled working hours of the Project staff are Mondays through Thursdays from 6:30 a.m. until 5:00 p.m. Fridays, Saturdays and Sundays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours.

1.2.2 Contractor's Working Hours

The Contractor's normal working hours shall be between 6:30 a.m. and 5:00 p.m., Monday through Thursday. The schedule of work hours, shifts and days of the week shall be coordinated with the Government Quality Assurance Representative (GQAR). Notification of any proposed changes of the schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site shall be coordinated with the GQAR.

1.3 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of the contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to the required work. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.

1.4 PARTNERING

In order to most effectively accomplish the work required by the contract, the Government urges the Contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project’s intended results are achieved, within budget and on schedule.

This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from

SECTION 01 00 00 Page 2 each organization representing management and the key jobsite staff of each entity. The initial conference would be held within the first thirty (30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.

Additional partnering sessions would be held no less than biannually.

Implementation of the partnering concept and philosophy would be an on-going process.

1.5 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

ER 385-1-31 (2009) The Control of Hazardous Energy

1.6 PROJECT SIGNS

a. General. The Contractor shall furnish and erect, within 30 days after issue of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed. The signs shall be lettered on one side only and shall conform to EP 310-1-6a, EP 310-1-6b, and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:

EXCITER EQUIPMENT REPLACEMENT

b. Materials. The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.

c. Painting. The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.

d. Erection and Maintenance. The signs shall be erected at the designated locations. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. The signs shall be maintained in good condition until

SECTION 01 00 00 Page 3 completion of the contract, shall remain the property of the Contractor, and shall be removed from the site upon final acceptance of the contract work.

1.7 CONTRACTOR'S STAGING AREAS

The Contractor will be assigned the following areas for use as staging areas:

a. A portion of the concrete area in the powerhouse parking adjacent to the switchyard,

b. A portion of the assembly bay, and

c. A portion of the generator floor area.

The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner.

Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.

1.8 SAFE CLEARANCE PROCEDURES

Project personnel use A Safe Clearance System, as stated in ER 385-1-31 and amended by the Nashville District to ensure continuity of service and safety to personnel and equipment. Any work performed which requires taking the Project's operating equipment out of service will be done only after a formal clearance is obtained by the Contracting Officer with 48-hour minimum notice. Contractor personnel shall not violate clearance.

Any violation of Safe Clearance Procedures will be grounds for removal of the offender(s). Up to five copies of the Nashville District Safe Clearance Procedure will be supplied to the Contractor upon request.

1.9 DAILY CLEANUP AND DISPOSAL

Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.

1.10 STORAGE OF EQUIPMENT AND MATERIALS

Storage of equipment and materials will be permitted only in designated staging areas. A minimum access space of three feet shall be maintained between the Contractor's stored items and existing facility equipment.

1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES

Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in

SECTION 01 00 00 Page 4 the contract price.

1.12 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor shall coordinate as necessary.

1.13 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each area. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov. This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.14 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and Subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE Contractors in their outreach efforts:

Federal Veteran employment information at:

http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance:

http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act:

http://benefits.va.gov/vow/

Army Wounded Warrior Program:

http://wtc.army.mil/modules/employers/index.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material:

http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_guide_t

SECTION 01 00 00 Page 5

1.15 MEASUREMENT AND PAYMENT

No separate payment will be made for the work covered under this section.

The costs thereof shall be included in the item to which the work pertains.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The Contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.

b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.

c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.

3.1.2 Interruptions of Utilities

a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.

b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:

(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)

(2) Size of line and location of shutoff.

(3) Buildings and services affected.

(4) Hours and date of shutoff.

(5) Estimated length of time services will be interrupted.

c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.

d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.

e. Operation of valves on water mains will be by Government personnel.

Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.

SECTION 01 00 00 Page 6

3.1.3 Installation Procedure

Only one unit shall be out of service (under construction) at a time unless written permission is given by the Government. The Government will coordinate with the Contractor to determine the allowable unit-outage sequence prior to start of physical work.

-- End of Section --

SECTION 01 00 00 Page 7

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 10

STATEMENT OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.2 SPECIFICATIONS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

SECTION 01 11 10 Page 1

SECTION 01 11 10

STATEMENT OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

The scope of work for this contract consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following work in strict accordance with the detailed requirements of this contract:

a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver f.o.b. destination four complete digital static excitation systems for the Barkley Power Plant.

b. Remove four existing excitation systems.

c. Install, test, commission, and make ready for commercial operation four excitation systems at Barkley Power Plant, including floor repair and including furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.

d. Conduct equipment model validation tests and prepare test report suitable for use by SERC.

1.2 SPECIFICATIONS

Technical specifications listed below cover the detailed requirements for the equipment and services listed in the Price Schedule:

SECTION TITLE

01 00 00 GENERAL REQUIREMENTS

01 11 10 STATEMENT OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURE

01 35 26 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 SOURCE OF REFERENCED PUBLICATIONS

01 45 01 QUALITY CONTROL

01 45 02 QUALITY CONTROL SYSTEM (QCS)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMTTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 95 00 FORMS AND ATTACHMENTS

02 82 14 ASBESTOS ABATEMENT WORK

03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES,

AND EQUIPMENT FOUNDATIONS

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

26 25 00.00 26 BUS STRUCTURES

48 19 26.00 26 DIGITAL EXCITERS

SECTION 01 11 10 Page 2

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

SECTION 01 11 10 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 PAYMENT ITEMS

1.2.1 CLIN 0001 Mobilization and Preparatory Work: Design, manufacture, test and deliver excitation system and appurtenances

1.2.1.1 Payment

1.2.1.2 Unit of Measure

1.2.2 CLIN 0002 Mobilization and Demobilization for Installation Work

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.3 CLIN 0003 Performance & Payment Bonds

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.4 CLIN 0004 Perform Special Factory Tests

1.2.4.1 Payment

1.2.4.2 Unit of Measure

1.2.5 CLIN 0005 Special Tools and Spare Parts

1.2.5.1 Payment

1.2.5.2 Unit of Measure

1.2.6 CLIN 0006 Model Validation Testing and Reports

1.2.6.1 Payment

1.2.6.2 Unit of Measure

1.2.7 CLIN 0007 Disassemble and Remove Existing Excitation Systems

1.2.7.1 Payment

1.2.7.2 Measurement

1.2.7.3 Unit of Measure

1.2.8 CLIN 0008 Install and Test Excitation Systems and

Appurtenances; Modify Existing Powerhouse Control Panels; and Deliver and Install External Wiring, Cabling, Conduits, and Bus

1.2.8.1 Payment

1.2.8.2 Measurement

1.2.8.3 Unit of Measure

1.2.9 CLIN 0009 Perform Special Field Tests

1.2.9.1 Payment

1.2.9.2 Unit of Measure

1.2.10 CLIN 0010 Concrete Removal and Repair

1.2.10.1 Payment

1.2.10.2 Unit of Measure

1.2.11 CLIN 0011 Training

1.2.11.1 Payment

1.2.11.2 Unit of Measure

1.2.12 CLIN 0012 Asbestos Abatement Work

1.2.12.1 Payment

1.2.12.2 Unit of Measure

1.2.13 CLIN 0013 Test and Refurbish Existing Collector Ring

Assembly (As-Needed)

1.2.13.1 Payment

1.2.13.2 Measurement

1.2.13.3 Unit of Measure

SECTION 01 22 00 Page 1

1.2.14 CLIN 0014 Furnish, Install, and Test New Collector Ring Assembly

1.2.14.1 Payment

1.2.14.2 Measurement

1.2.14.3 Unit of Measure

1.2.15 CLIN 0015 Install Government Furnished Brushes and Holders for Units 2 and 4

1.2.15.1 Payment

1.2.15.2 Measurement

1.2.15.3 Unit of Measure

1.2.16 CLIN 0016 Convert Applicable Reference Drawings Into CADD

Format

1.2.16.1 Payment

1.2.16.2 Measurement

1.2.16.3 Unit of Measure

1.2.17 CLIN 0017 Machinist Hire (As Needed)

1.2.17.1 Payment

1.2.17.2 Unit of Measure

1.2.18 CLIN 0018 Electrician Hire (As Needed)

1.2.18.1 Payment

1.2.18.2 Unit of Measure

1.2.19 CLIN 0019 Welding Services (As Needed)

1.2.19.1 Payment

1.2.19.2 Unit of Measure

1.2.20 CLIN 0020 Painter Hire (As Needed)

1.2.20.1 Payment

1.2.20.2 Unit of Measure

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 22 00 Page 2

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance, the contract price for a contract line item number (CLIN) will constitute full compensation as herein specified, as shown, or as otherwise approved. The contract price and payment will also constitute full compensation for all work incidental to completion of the CLIN, unless such work is otherwise specifically mentioned for separate payment under another CLIN. In the event any work is required by the specification sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs separate or direct payment will not be made. All costs are therefore incidental to, and included in, the contract prices and payment for all CLINs listed in the price schedule.

1.2 PAYMENT ITEMS

Payment items for the work of this contract for which contract payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular price payment item, are included in the listed item most closely associated with the work involved. The payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

CLINs measured as a Job will be measured for payment as a complete job in the locations indicated. This measurement includes all incidental work and materials such as fasteners, electrical materials, and O&M manuals that are necessary to make a complete job. Unless the CLIN paragraph makes a specific exception of any item, incidental items will not be measured under any other CLIN, even though there is another listing for the work or material.

1.2.1 CLIN 0001 Mobilization and Preparatory Work: Design, manufacture, test and deliver excitation system and appurtenances

1.2.1.1 Payment

Mobilization and preparatory work shall be paid for at the contract price per Job for "Mobilization and Preparatory Work". Payment shall be done in accordance with Contract Clause 252.236-7003, PAYMENT FOR MOBILIZATION AND PREPARATORY WORK, and as described below:

Payment will be made on a per Job basis under CLIN 0001. Payment shall be made for all materials, labor, equipment, and facilities needed to design, manufacture, test, submit design documents and deliver the excitation systems in accordance with Section 48 19 00.00 26 DIGITAL EXCITERS.

SECTION 01 22 00 Page 3

1.2.1.2 Unit of Measure

Unit of measure: Job.

1.2.2 CLIN 0002 Mobilization and Demobilization for Installation Work

1.2.2.1 Payment

Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clause 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION, and as described below:

Payment will be made on a per Job basis under CLIN 0002. Payment shall be made for all costs incurred prior to arriving onsite (mobilization) or immediately after departing the work site (demobilization). These costs include, but are not limited to, all preparatory work at the Contractors shop, labor costs associated with travel to and from the work site, and transportation costs.

1.2.2.2 Unit of Measure

Unit of measure: Job.

1.2.3 CLIN 0003 Performance & Payment Bonds

1.2.3.1 Payment

Payment will be made for the performance and payment bonds that are required as part of this contract. The Government will pay the actual cost of acceptable performance and payment bonds or the Contractor's bid price, whichever is less. The Contractor shall provide evidence of payment (paid invoice) from the bonding company or agency. If the actual cost of the bonds is less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes.

1.2.3.2 Unit of Measure

Unit of measure: Job.

1.2.4 CLIN 0004 Perform Special Factory Tests

1.2.4.1 Payment

Payment will be made on a per Job basis under CLIN 0004. Payment shall be made for all materials, labor, and equipment needed to perform the special factory testing in accordance with Section 48 19 00.00 26.

1.2.4.2 Unit of Measure

Unit of measure: Job.

1.2.5 CLIN 0005 Special Tools and Spare Parts

1.2.5.1 Payment

Payment will be made on a per Job basis under CLIN 0005. Payment shall be made for providing and deliverying to site all spelcial tools and all spare

SECTION 01 22 00 Page 4 parts in accordance with Section 48 19 00.00 26.

1.2.5.2 Unit of Measure

Unit of measure: Job.

1.2.6 CLIN 0006 Model Validation Testing and Reports

1.2.6.1 Payment

Payment will be made on a per Job basis under CLIN 0006. Payment shall be made for all materials, labor, and equipment needed to perform all specified pre-installation submittals including but not limited to:

procedures for exciter and PSS tuning and model validation testing, and computer simulation models of the excitation system and PSS as specified in Section 48 19 00.00 26 paragraph 3.5.7 Model Validation Testing.

1.2.6.2 Unit of Measure

Unit of measure: Job.

1.2.7 CLIN 0007 Disassemble and Remove Existing Excitation Systems

1.2.7.1 Payment

Payment will be made on a per unit basis under CLIN 0007. Payment shall be made for all materials, labor, and equipment needed to disassemble and remove the existing excitation systems in accordance with Section 48 19 00.00 26.

1.2.7.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily disassembled and removed excitation system units.

1.2.7.3 Unit of Measure

Unit of measure: Each (EA).

1.2.8 CLIN 0008 Install and Test Excitation Systems and Appurtenances;

Modify Existing Powerhouse Control Panels; and Deliver and Install External Wiring, Cabling, Conduits, and Bus

1.2.8.1 Payment

Payment will be made on a per each basis under CLIN 0008. Payment shall be made for all materials, labor, and equipment needed to install and test the new excitation systems, including modifying existing panels and delivery and installtions of external wiring, cabling, conduits, and bus in accordance with the Section 48 19 00.00 26.

1.2.8.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily installed and tested excitation system units and appurtenances; modified existing Powerhouse control panels; and delivered and installed external wiring, cabling, conduits, and bus.

SECTION 01 22 00 Page 5

1.2.8.3 Unit of Measure

Unit of measure: Each (EA).

1.2.9 CLIN 0009 Perform Special Field Tests

1.2.9.1 Payment

Payment will be made on a per Job basis under CLIN 0009. Payment shall be made for all materials, labor, and equipment needed to performing the special field tests in accordance with Section 48 19 00.00 26.

1.2.9.2 Unit of Measure

Unit of measure: Job.

1.2.10 CLIN 0010 Concrete Removal and Repair

1.2.10.1 Payment

Payment will be made on a per job basis under CLIN 0010. Payment shall be made for all materials, labor, and equipment needed for concrete work in accordance with Sections 03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND EQUIPMENT FOUNDATIONS and 48 19 00.00 26 DIGITAL

EXCITERS.

1.2.10.2 Unit of Measure

Unit of measure: Job.

1.2.11 CLIN 0011 Training

1.2.11.1 Payment

Payment will be made on a per Job basis under CLIN 0011. Payment shall be made for all materials, labor, and equipment needed to conduct all training sessions required in accordance with Section 48 19 00.00 26.

1.2.11.2 Unit of Measure

Unit of measure: Job.

1.2.12 CLIN 0012 Asbestos Abatement Work

1.2.12.1 Payment

Asbestos abatement will be paid for on a per Job basis under CLIN 0012, "Asbestos Abatement Work." This item shall include all costs for sampling, testing, collecting, analyzing, transporting, and disposing of Asbestos Containing Materials in accordance with Section 02 82 14 ASBESTOS ABATEMENT.

1.2.12.2 Unit of Measure

Unit of measure: Job.

SECTION 01 22 00 Page 6

1.2.13 CLIN 0013 Test and Refurbish Existing Collector Ring Assembly (As-Needed)

1.2.13.1 Payment

Payment will be made on a per each basis under CLIN 0013. Payment shall be made for all materials, labor, and equipment needed to effect the collector ring refurbishment work, and all required testing, in accordance with Section 48 19 00.00 26.

1.2.13.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily refurbished existing collector ring assemblies.

1.2.13.3 Unit of Measure

Unit of measure: Each (EA).

1.2.14 CLIN 0014 Furnish, Install, and Test New Collector Ring Assembly

1.2.14.1 Payment

Payment will be made on a per each basis under CLIN 0014. Payment shall be made for all materials, labor, and equipment needed to effect the collector ring replacement work, and all required testing, in accordance with Section 48 19 00.00 26.

1.2.14.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily furnished, installed, and tested new collector ring assemblies.

1.2.14.3 Unit of Measure

Unit of measure: Each (EA).

1.2.15 CLIN 0015 Install Government Furnished Brushes and Holders for Units 2 and 4

1.2.15.1 Payment

Payment will be made on a per each basis under CLIN 0015. Payment shall be made for the installation of Government furnished slip ring brushes and holders for two units in accordance with Section 48 19 00.00 26. Brushes for Units 1 and 3 have been previouly completed by others.

1.2.15.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily installed Government furnished brushes and holders.

1.2.15.3 Unit of Measure

Unit of measure: Each (EA).

SECTION 01 22 00 Page 7

1.2.16 CLIN 0016 Convert Applicable Reference Drawings Into CADD Format

1.2.16.1 Payment

Payment will be made on a per each basis under CLIN 0016. Payment shall be made for all services, labor, and equipment needed to convert existing electronic reference drawing files in raster format to CADD format in accordance with Section 01 78 00 CLOSEOUT SUBMITTALS.

1.2.16.2 Measurement

Measurement for payment will be made by the quantity of satisfactorily converted reference drawings into CADD format.

1.2.16.3 Unit of Measure

Unit of measure: Each (EA).

1.2.17 CLIN 0017 Machinist Hire (As Needed)

1.2.17.1 Payment

Furnish machinist and shop facilities to perform work on various equipment as directed. Payment for machinist hire will be made on an hourly basis under Item No. 0017. Payment shall include all required labor, material, and equipment.

1.2.17.2 Unit of Measure

Unit of measure: Man-Hour (MH).

1.2.18 CLIN 0018 Electrician Hire (As Needed)

1.2.18.1 Payment

Furnish electrician to perform work on installation and repairs of various electrical machinery, equipment, and wiring as directed. Payment for electrician hire will be made on an hourly basis under Item No. 0018.

Payment shall include all required labor, material, and equipment.

1.2.18.2 Unit of Measure

Unit of measure: Man-Hour (MH).

1.2.19 CLIN 0019 Welding Services (As Needed)

1.2.19.1 Payment

Furnish the use of a welder with machine, leads and wire to perform miscellaneous welding. Payment for welding services will be made on an hourly basis under Item No. 0019. Payment shall include all required labor, material, and equipment.

1.2.19.2 Unit of Measure

Unit of measure: Man-Hour (MH).

SECTION 01 22 00 Page 8

1.2.20 CLIN 0020 Painter Hire (As Needed)

1.2.20.1 Payment

Provide all labor, material, and equipment to perform painting, as directed, to exciter equipment replacement, related equipment, and surrounding areas. Painting shall include surface cleaning and preparation. Payment for painter hire will be made on an hourly basis under Item No. 0020.

1.2.20.2 Unit of Measure

Unit of measure: Man-Hour (MH).

PART 2 PRODUCTS

(NOT USED)

PART 3 EXECUTION

(NOT USED)

SECTION 01 22 00 Page 9

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Design and Permit Activities

3.3.4 Procurement Activities

3.3.5 Mandatory Tasks

3.3.6 Government Activities

3.3.7 Standard Activity Coding Dictionary

3.3.7.1 Workers Per Day (WRKP)

3.3.7.2 Responsible Party Coding (RESP)

3.3.7.3 Area of Work Coding (AREA)

3.3.7.4 Modification Number (MODF)

3.3.7.5 Bid Item Coding (BIDI)

3.3.7.6 Phase of Work Coding (PHAS)

3.3.7.7 Category of Work Coding (CATW)

3.3.7.8 Feature of Work Coding (FOW)

3.3.8 Contract Milestones and Constraints

3.3.8.1 Project Start Date Milestone and Constraint

3.3.8.2 End Project Finish Milestone and Constraint

3.3.8.3 Interim Completion Dates and Constraints

3.3.8.3.1 Start Phase

3.3.8.3.2 End Phase

3.3.9 Calendars

3.3.10 Open Ended Logic

3.3.11 Default Progress Data Disallowed

3.3.12 Out-of-Sequence Progress

SECTION 01 32 01 Page 1

3.3.13 Added and Deleted Activities

3.3.14 Original Durations

3.3.15 Leads, Lags, and Start to Finish Relationships

3.3.16 Retained Logic

3.3.17 Percent Complete

3.3.18 Remaining Duration

3.3.19 Cost Loading of Closeout Activities

3.3.19.1 As-Built Drawings

3.3.19.2 O & M Manuals

3.3.20 Anticipated Adverse Weather

3.3.21 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.2.1 Design Package Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD/DVDs

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet)

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01 Page 2

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following, in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this

SECTION 01 32 01 Page 3 specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the Contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the Contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.

Subcontractors and suppliers Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

SECTION 01 32 01 Page 4

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Design and Permit Activities

Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.

Also include review and correction periods associated with each item.

3.3.4 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.5 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.

SECTION 01 32 01 Page 5

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.6 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals,acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.7 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. All

SECTION 01 32 01 Page 6

Activity Codes shall be developed and assigned to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil.

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.7.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day shall be the average number of workers expected each day to perform a task for the duration of that activity.

3.3.7.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical Subcontractor); MECH (for the mechanical Subcontractor); and GOVT (for USACE).

3.3.7.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space

SECTION 01 32 01 Page 7 constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.7.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.7.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.7.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase, and construction phase.procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.7.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to design, design submittal, design reviews, review conferences, permits, construction submittals,construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.7.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 01 QUALITY CONTROL.

An activity can have only one Feature of Work Code.

3.3.8 Contract Milestones and Constraints

Milestone activities are to be used for significant project events

SECTION 01 32 01 Page 8 including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.8.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.8.2 End Project Finish Milestone and Constraint

The last activity in the schedule shall be a finish milestone titled "End Project."

The project schedule must be constrained to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.8.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.8.3.1 Start Phase

Use a start milestone as the first activity for a project phase. The start milestone shall be called "Start Phase X" where "X" refers to the phase of work.

3.3.8.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.9 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays.