ADAL_Questions.pdf

PDF 10 KB Posted

Attached to
Add/Alter Mulitple Facilities Federal contract opportunity
Solicitation number
W912L7-16-B-0003
Issued by
Department of the Army Tennessee Army National Guard

About this file

Amendment 4 questions and answers

View the file

Other files for this federal contract opportunity

Other files attached to Add/Alter Mulitple Facilities, newest first.
File Type Posted
ADAL_Questions.pdf PDF
ADAL_Questions.pdf PDF
Pre_Bid_Sign_In.pdf PDF
W912L7-16-B-0003-0001.pdf PDF
W912L7-16-B-0003.pdf PDF
B120_Canopy_at_600mA 1 .pdf PDF
Add_Alter_Multi_Facilities_Basewide_-_Revised_SOW_June_2016.pdf PDF
B120_Canopy_at_800mA 1 ..pdf PDF
Bldg_120_Canopy_Lights 1 ..pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADAL Questions

Amendment 2

24 August 2016

1. Does the term install means Supply and Install? Or the government has a new package that the contractor will install?

2. That is correct. Throughout the SOW in ALL locations the term install means that the contractor will supply and install the materials and/or equipment described.

Amendment 3

6 September 2016

3. For the MR board replacement in restrooms of dorm rooms, to what extent do we need to figure new board? How many new boards per dorm room? Do we need to figure any touch up of existing finishes in each dorm room?

Answer: MR Board replacement is to occur in the shower stall only and will be required floor to deck. Remaining restroom finishes to remain as existing. The repair area in each of the restrooms is limited to the shower only. With that information, contractors should be able to calculate required amount of material to repair showers as specified. Touch ups will be required for all finishes damaged by construction activities. Pre-existing damage is not required to be repaired by the contractor.

4. The 2 new walls we are to build in the hallway, it says we need to patch back acoustical ceilings at the new walls. What ceiling materials need to be used? Type of ceiling tile?

Answer: Contractor shall match existing suspension ceiling within that area. Per Section 1.10

Performance, it is the contractor's responsibility to acquaint themselves with all available information from including physical survey of the site of the proposed work.

5. On AF-1 and AF-3, it says drywall repair at cove removed with a question mark after it. Do we need to figure drywall repair at those cove locations?

Answer: Referenced question mark was not found when reviewing SOW, however site investigation by the contractor can easily validate existing conditions to identify whether or not minor repairs are required to properly install new cove base. Any damage occurring from the demo of existing cove base will be the contractor's responsibility to repair.

6. Other than the new walls, MR board in dorm room restrooms, and possible touchup at cove locations, is there any other work in this project you would need us to do?

Answer: All project requirements are specified within the SOW.

Amendment 4

7 September 2016

7. Can you verify the size of the new canopy? We measured 22w x 23l x 12h.

Answer: Disregard canopy dimensions listed in SOW. As stated above the new canopy is approximately 22w x 23l x 12h. Contractor shall field verify dimensions.

8. What kind of generator will the ATS be hooked to?

Answer: Generator Type: Generac

NSN or Model#: GTA312A11B114-GEN

Generator serial#: 2118393

Engine Make: Perkins

Engine Model Number: CPKXL152TA2

Engine Serial Number: MGDF5333U18833W

Alternator Make: Generac

Alternator Model Number: GTA312A11B114-GEN

Alternator Serial Number: 2118393

ATS Make, Model and Voltage: 1000 AMP 277/480 VAC Onan Model#ONCU1000G

Spec#3469G Serial#D930505354 3Ph 4Wire

Single or Three Phase: 3

KW Rating: 500Kw

Type of Fuel: Diesel

File details come from the government source that posted it. Updated .