Statement_of_Work-PJMS132017_-_Final.pdf

PDF 138 KB Posted

Attached to
Taxiway Repair
Solicitation number
W912K6-15-R-0011
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
W912K6-15-R-0011_RFI_Regarding_Mix_Design_(Response).docx DOCX document
RFI_Taxiway_Repair.docx DOCX document
DOWELLED_SLAB_LOCATION.pdf PDF
RFI_Taxiway_Repair.docx DOCX document
sign_in_sheet_10_Aug.pdf PDF
Preproposal_slides_taxiway.pptx PPTX presentation
RFI_Taxiway_Repair.docx DOCX document
Section_008001.docx DOCX document
Exhibit_G_Environmental_Protection_Plan_for_Contractors.pdf PDF
PJMS132017-SLAB_REPLACEMENT_Plan.pdf PDF
175th_WING_INSTALLATION_ACCESS_APPLICATION.pdf PDF
PJMS132017-SLAB_REPLACEMENT_Work_Zone_Plan.pdf PDF
PJMS132017-Rapid_Set_Cement_Specs.pdf PDF
Exhibit_H.docx DOCX document
PJMS132017-SLAB_REPLACEMENT_Details.pdf PDF
EXHIBIT_F.docx DOCX document
W912K6-15-R-0011.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE PAVEMENT ON TRANSIENT RAMP

PARKING AREA

STATEMENT OF WORK

PROJECT NUMBER: PJMS #132017

MARYLAND AIR NATIONAL GUARD

MARTIN STATE AIRPORT

NATIONAL GUARD BASE

BALTIMORE, MARYLAND 21220

9 JULY 2015

1. General Project Information:

1.1 Project Location and Background: This Project is to take place on the entrance to the

Transient Aircraft Parking Apron entrance, where it meets Tango Taxiway, at the

Maryland Air National Guard (MDANG) portion of Martin State Airport, Maryland Air

National Guard, 2701 Eastern Boulevard, Baltimore, MD 21220.

The primary purpose of the project is to remove and replace approximately 14500 SF of reinforced concrete pavement.

1.2 Use of Premises:

1.2.1. Contractor shall assume full responsibility for protection and security of materials and equipment stored on site.

1.2.2. Contractor shall move any stored products, under their control, which interfere with operations of the Government.

1.3 Government Equipment: Contractor use of Government owned or leased equipment such as: hoists, forklifts, compressors, welding machines, cutting rigs, etc. shall not be permitted on either a reimbursable or non-reimbursable basis. Cost for all equipment required to accomplish the work shall be included in the Contractor’s final bid price.

1.4. Permits and Inspections:

1.4.1. Normally no permits or inspections by local building officials are required. Daily inspections will be performed by the COR.

1.5. Contractor Passes: Contractor Passes are only issued to personnel who have properly submitted a locally generated 175 th

Wing Installation Access Application (available from the Contracting Office or from the COR) and have been cleared through an approved background investigation by the 175 th

Security Forces Squadron. The

Installation Access Application contains required information necessary to conduct a

National Criminal Information Center (NCIC) background check or a Defense

Biometric Identification System (DBIDS) check.

Contractor Passes are only issued to contractors who will be required to work more than 14-days on the installation in the performance of their contract. For contractors requiring less than 14 days of access, an AF FM 75, Visitors Pass, will be issued upon a favorable background investigation.

The Defense Forces Commander (DFC) maintains the right to deny contractors access to the installation based on unfavorable information obtained through NCIC or DBIDS.

1.6. Hours of Operations: The hours of operations at Martin State Airport for the Air

National Guard are 10 hours per day (0700 – 1700) Tuesday – Friday. Coordinate access to premises with COR, for execution of work. Emergency situations, military operations, or other contingencies, may cause suspension of work or restrictions on access to the construction site.

1.7. Off-Hours Work: Except as otherwise specified, all work shall be performed during regular work hours (indicated above). If the Contractor desires or is required to work on Mondays, Saturdays, Sundays, Holidays or other hours outside normal work schedule, the Contractor shall be required to seek written approval from the Contracting

Officer. The Contractor is not entitled to premium time if the request is approved.

1.8. Clean-up: The work site is an active civilian and military airport. Site cleanliness and

Foreign Object Debris (FOD) control is essential. The Contractor will clean up all construction debris and refuse and will remove it from the work site and the Base daily at their own expense.

1.9. Safety: The Contractor is responsible for performing all work In Accordance With (IAW)

State and Federal OSHA requirements as well as compliance with the most current

USACE EM 385-1-1. This is available at: http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html.

1.10. Environmental Protection and Waste Disposal: The Contractor shall, at their own expense, remove all sludge, dust and debris from the property of the Martin State

Airport Air National Guard Base which have resulted from specific work described in

Paragraph 2 of these specifications. The disposal of all such materials, which may include hazardous or toxic liquids that are used to perform the work, shall conform to all Federal, State, and Local environmental regulations with regards to both transportation and ultimate disposal. This project must comply with all Federal, State, and Local environmental regulations. All dumpster service and waste management shall be provided at no additional cost to the Government. All recyclable metal shall be placed into Martin State Airport scrap metal recycling containers.

Please contact the Base Environmental Engineer, Lt Col Peter Loebach, at (410) 918-

6486 for detailed information. Also, for more information, review “Environmental

Protection Plan for Contractors”, which will be provided during the solicitation phase.

1.11. Drawings: Drawings furnished by the government to the Contractor may be used for general information only and shall not be relied upon in determining utility locates and documentation without complete on-site verification by the Contractor.

2. Specific Project Information:

2.1. References and Standards: All materials, installation and workmanship shall comply with applicable construction guidelines and standards.

2.2. Cost Proposal: Provide a detailed lump sum cost proposal (as well as hourly rates) indicating costs and itemized breakdown for:

- Surveying

- Excavation

- Concrete and formwork

- Breakouts for Materials; e.g., building materials, piping material, insulation, electrical, disconnect, etc..

2.3 Description of Work: The Contractor shall describe in his or her proposal how they will manage the project.

http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html

2.4. Construction Performance Period: The Contractor shall identify what s/he considers the performance period to be. The proposed performance period will be included in the

Cost Proposal.

2.5. Meetings: A “Preconstruction” Meeting will be required post-award and prior to initiation of the Scope of Services.

2.6. Sundry Elements: Any material, devices or services not specifically mentioned or indicated in this specification that are reasonably required for a complete, finished and first class operating installation, shall be provided by the Contractor at no additional cost to the owner. The work shall be installed in accordance with this specification and best industry practices.

2.7. Detailed Requirements:

2.7.1. Security Cordon and Barriers

2.7.1.1. The contractor will supply temporary traffic barriers to demarcate the limits of the work zone and the access route through the controlled area.

2.7.1.2. The barriers shall be Airport Low profile lighted and installed so that they are always in the extended position, properly oriented and securely fastened to eliminated jet engine ingestion.

2.7.1.3. Barricade shall be constructed of high impact UV-resistant polyethylene model No.

NAC PC 2410 Neubert Aero Corp or approved equal

2.7.1.4. Each unit shall include a Neubert Aero Corp Solar Red LED Barricade Safety Light, attached with 2 Inch screw base or approved equal.

2.7.1.5. Barricades shall comply with FAA AC 150/5370-2E Regulations.

2.7.2. Site survey

2.7.2.1. The contractor will perform a detailed survey of the existing slab elevations (each slab corner) within the project area and 50 ft. beyond the perimeter of the project area, as well as the centerline of any ditches and any inlet inverts. The contractor shall provide an AutoCAD file, 2010 to the BCE, showing the elevations and distances. The drawing shall be coordinately accurate. The preferred horizontal and vertical datum shall be NAD 83 to beginning the survey.

2.7.2.2. The contractor will also provide a detailed plan, based on the survey data, showing the proposed slab elevations. The plan shall correct any irregularities in the slope of the pavement and ensure the pavement drains as optimally as possible.

2.7.2.3. The new plan should follow the slab layout pattern of the overall airfield and not the existing pattern of the slabs that are being replaced. This topic shall be discussed at the pre-construction meeting. The slab layout with proposed elevations shall be approved by the BCE prior to construction start.

2.7.3. Demolition:

2.7.3.1. Removal of existing concrete slabs 14500 SF at 1 Foot Depth

2.7.3.2. The contractor shall follow procedures outlined in UFC 3-270-04 for removing the existing concrete slabs.

2.7.3.3. Protection of remaining slabs. The contractor will take precautions to ensure no damage is caused to concrete slabs that are not scheduled for replacement. Any damage to existing concrete slabs will be repaired by the contractor, at the contractor’s expense using methods directed by the BCE, up to and including complete slab replacement.

2.7.3.4. The contractor shall also take steps not to damage or disturb the existing underdrain that is installed at the edge of the pavement. Damage to the underdrain shall be repaired at the contractor’s expense.

2.7.3.5. All excavated concrete, rock, soil and unsuitable material will be removed from the base and disposed of at an appropriate location by the contractor and at the contractor’s expense.

2.7.4. Full depth Pavement slab replacement

2.7.4.1. There are approximately 45 concrete slabs, measuring approximately 19’x19’x1’ that are to be replaced. The total area is approximately 14500 SF.

2.7.4.2. The cost of the slab replacement includes all labor and materials necessary to complete the work. This includes, but is not limited to, excavation, backfill, steel, dowels, joint sealant, grout, graded aggregate base, concrete, etc.

2.7.4.3. Excavate all unsuitable material, backfill with graded aggregate base to 10 inch depth below base of the concrete pad which is to be poured. Compact graded Aggregate

Base to 98% density.

2.7.4.4. In areas where the compaction is difficult due to field conditions, the contractor may opt to replace 4 inches of GAB with 4 inches of Concrete Blinding.

2.7.4.5. Construct approximately 14500 SF at 1 Foot Depth Concrete slab according to plans.

2.7.4.6. All work shall be performed in accordance with the UFC 3-270-04

2.7.4.7. Concrete:

Rapid Set Cement shall be used for all pours. Contractor shall adhere to the attached specifications for Rapid Set Cement.

2.7.4.8. Welded wire mesh: shall be 6x6 4W x 4W WWF Mat Wire mesh.

Contractor shall install the dowels, rebar IAW the drawings. Plastic tipped chairs shall be used to maintain the proper height of the steel. Wire mesh shall be independent in each slab and stop 3 inches short of the slab edges. Mesh shall overlap by 1.5 squares, minimum and be wire tied securely together.

2.7.4.9. Testing: is required by an independent third party and will be paid for by the contractor.

Slump Tests

ASTM C 143/C 143M. Take concrete samples during concrete placement. The maximum slump may be increased as specified with the addition of an approved admixture provided that the water-cement ratio is not exceeded.

Perform tests at commencement of concrete placement, when test cylinders are made, and for each batch (minimum) or every 20 cubic yards (maximum) of concrete.

Temperature Tests

Test the concrete delivered and the concrete in the forms. Perform tests in hot or cold weather conditions (below 50 degrees F and above 80 degrees F) for each batch (minimum) or every 20 cubic yards (maximum) of concrete, until the specified temperature is obtained, and whenever test cylinders and slump tests are made.

Compressive Strength Tests

ASTM C 39/C 39M. Make five test cylinders for each set of tests in accordance with ASTM C 31/C 31M. Take precautions to prevent evaporation and loss of water from the specimen. Test two cylinders at 7 days, two cylinders at 28 days, and hold one cylinder in reserve. Take samples for strength tests of each mix design of and for concrete placed each day not less than once a day, nor less than once for each 160 cubic yards of concrete, nor less than once for each 5400 square feet of surface area for slabs or walls. For the entire project, take no less than five sets of samples and perform strength tests for each mix design of concrete placed.

Each strength test result must be the average of two cylinders from the same concrete sample tested at 28 days. If the average of any three consecutive strength test results is less than f ‘c or if any strength test result falls below f ‘c by more than 450 psi, take a minimum of three

ASTM C 42/C 42M core samples from the in-place work represented by the low test cylinder results and test. Concrete represented by core test is considered structurally adequate if the average of three cores is equal to at least 85 percent of f ‘c and if no single core is less than 75 percent of f ‘c. Retest locations represented by erratic core strengths. Remove concrete not meeting strength criteria and provide new acceptable concrete. Repair core.

2.7.4.10. Finishing:

Concrete will be finished to match the surface of the existing concrete apron that is not being replaced. Unless the manufacturer recommends otherwise, apply curing compound immediately after the surface loses its water sheen and has a dull appearance, and before joints are sawed. Mechanically agitate curing compound thoroughly during use. Use approved power-spraying equipment to uniformly apply two coats of compound in a continuous operation. The total coverage for the two coats must be 200 square feet maximum per gallon of undiluted compound

Unless otherwise recommended by the manufacturer's written instructions.

The compound must form a uniform, continuous, coherent film that does not check, crack, or peel. Immediately apply an additional coat of compound to areas where the film is defective. Re-spray concrete surfaces subjected to rainfall within 3 hours after the curing compound application.

Protection of Treated Surfaces Prohibit pedestrian and vehicular traffic and other sources of abrasion at least 72 hours after compound application. Maintain continuity of the coating for the entire curing period and immediately repair any damage.

2.7.5. Site Cleanliness:

Before concrete pours, designate Company-owned site for cleaning out concrete mixing trucks. Concrete trucks may not be cleaned out on base. Excess concrete may not be disposed of on base.

2.7.5.1. The contractor is responsible for maintaining a clean site and allowing zero spillover onto the surrounding area. Flying Object Debris (FOD) is a serious issue on an airfield and can be detrimental to the operation of aircraft. The contractor will be held responsible for any damage caused due to negligence and non-compliance.

2.7.6. Joint Sealing – Joints will be sealed with airfield grade sealant, impervious to liquid fuels. Joints will be filled from the bottom in a smooth run to a depth between ¼ and

1/16 inches from surface.

2.7.7. Pavement marking

2.7.7.1. The contractor shall replace all pavement markings that are disturbed during the pavement removal, construction process or by vehicle traffic.

2.7.7.2. Red Controlled Area Markings: To be provided at Pre-Bid Conference

2.7.7.3. Yellow Taxi Markings:

On previously painted markings, surface preparation should consist of, at a minimum, sweeping, blowing with compressed air or rinsing with high pressure water as required to remove all dirt, laitance and loose materials. Contractor shall apply new paint and reflective beads. Apply paint at a wet film thickness of 0.305 millimeters (mm) to

0.356mm (12 mils to 14 mils) for a desired dry film thickness of approximately

0.203mm (8mils). This thickness is needed to properly bind retro reflective beads in the paint. At this rate, coverage will be approximately 3 square meters per liter (121 square feet per gallon).

Contractor shall use Sherwin Williams Setfast Acrylic Waterborne Traffic Marking

Paint with the color of TM227 Lead free yellow or equal product.

Apply retro reflective media (glass beads) immediately at approximately 3.6 kilograms to 3.9 kilograms per 11.2 square meters (8 pounds to 9 pounds per gallon of paint or

121 square feet) of marked surface area. For all retro-reflective markings, use glass beads available under Federal Specification TT-B-1325, Beads, Retro-reflective, Type

I, Gradation A.

Painted markings should not be allowed to build up beyond a total thickness of approximately 1.02mm (40 mils). This will occur after about five marking cycles unless surface abrasion (such as can be caused by snow removal equipment) reduces this build up. Over-painting will cause the marking to eventually crack and peel.

Airfield traffic striping is to be 6 inches wide.

Marking Machinery equipment used for marking shall be mounted on pneumatic tires and shall be capable of applying lines of paint only, or paint and beads simultaneously, in widths of ((from) (102 mm (4 inches)) (to) (1 m (3 feet)) at a speed of at least 5 miles per hour. Equipment shall be sufficiently mobile and maneuverable to allow application of straight lines or curves in a true arc. It shall be adjustable to allow application of single lines of single colors or multiple lines (at least two) of different colors, at least 150 mm (6 inches) wide, and skip-lines in variable lengths at least 102 mm (4 inches) wide. All spray applicators and bead dispensers shall produce markings of uniform thickness, width, and appearance, with clean-cut edges, at the rate specified in paragraphs.

2.7.8. Ditch cleaning

2.7.8.1. Upon completion of the project, the contractor shall clean and re-grade the adjacent ditches and swales from the edge of pavement along both sides of the construction area to the next downstream inlets, up to 300 feet in each direction. This work includes cleaning out the existing inlet.

2.8. Safety:

2.8.1. The Contractor shall be fully aware of, and include in the Work Plan, safety measures to assure that its workers are not put at risk at any time while completing the work.

2.8.2. The Contractor shall be fully aware of, and include in the Work Plan, safety measures to assure that its workers are not put at risk at any time while completing the work.

2.8.3. The Contractor shall post any and all required safety or caution flags/signs to protect workers and Base personnel.

2.8.4. The Contractor shall be aware of and protect its workers from noise, dust, and fumes/vapors normally encountered while working on or near an active runway and aircraft.

2.9. Administrative Tasks:

2.9.1. The Contractor shall submit a schedule of events to be completed for task – Replace

Pavement Ramp Parking Area – to the COR for review and approval prior to beginning work.

2.9.2. The Contractor shall use best practice standards when performing work required by this

“Statement of Work”, adhering to all local and national codes, requirements and guidelines.

2.9.3. The Contractor shall prepare and furnish all required engineering and/or shop drawings prior to the completion of the project.

2.9.4. Meetings – The Contractor is required to attend the following meetings:

a. The prospective Contractor(s) may be required to attend a Pre-proposal

Meeting/Site Visit prior to submitting a proposal. The meeting is intended to last

1/2-hour and will convene in the Civil Engineering Conference Room, Building

2100, followed by a visit to the job site.

b. The Contractor shall attend a Pre-construction Meeting post-award and prior to initiation of the Scope of Services.

c. Prior to acceptance of Deliverables the Contractor shall attend a meeting to discuss submitted engineering/shop drawings, if applicable, and final report.

2.9.5. Qualifications: Minimum 10 years of documented large construction project experience specializing in rigid concrete pavement construction.

2.10. Quality Control: The Contractor shall establish and maintain quality control to assure compliance with contract requirements and shall maintain records of his quality control.

A copy of these records, as well as the records of corrective action taken, shall be furnished to the Government.

3. Submittals:

3.1. Product/Equipment Information: All submittals must utilize AF/IMT 3000, Material

Approval Submittal available at http://www.usmilitarycontracting.com/uploads/Attach_6.pdf for approval by the COR prior to start-of-work. Submit 4 sets of all AF IMT 3000 with attachments; 1 set for

BCE, 1 set for Contracting, and 3 sets will be returned to the Contractor. Provide the following product/equipment information for approval by the COR prior to start-of-work.

3.1.1. Contractor is to provide submittals, for COR approval, describing all of the products s/he intends to install and/or use, as well as the equipment and ancillary devices to be used on site in the context of the Contractor’s business operations.

3.1.2. Provide manufacturer’s literature (including capabilities of equipment, specifications, shop drawings if appropriate, etc.) for all products, equipment and ancillary devices to be installed and/or used on site.