RFI_Taxiway_Repair.docx

DOCX document 20 KB Posted

Attached to
Taxiway Repair
Solicitation number
W912K6-15-R-0011
Issued by

About this file

RFI 2

View the file

Other files

File Type Posted
W912K6-15-R-0011_RFI_Regarding_Mix_Design_(Response).docx DOCX document
RFI_Taxiway_Repair.docx DOCX document
DOWELLED_SLAB_LOCATION.pdf PDF
sign_in_sheet_10_Aug.pdf PDF
Preproposal_slides_taxiway.pptx PPTX presentation
RFI_Taxiway_Repair.docx DOCX document
Section_008001.docx DOCX document
Exhibit_G_Environmental_Protection_Plan_for_Contractors.pdf PDF
Statement_of_Work-PJMS132017_-_Final.pdf PDF
PJMS132017-SLAB_REPLACEMENT_Plan.pdf PDF
175th_WING_INSTALLATION_ACCESS_APPLICATION.pdf PDF
PJMS132017-SLAB_REPLACEMENT_Work_Zone_Plan.pdf PDF
PJMS132017-Rapid_Set_Cement_Specs.pdf PDF
Exhibit_H.docx DOCX document
PJMS132017-SLAB_REPLACEMENT_Details.pdf PDF
EXHIBIT_F.docx DOCX document
W912K6-15-R-0011.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT F

PROPOSAL INQUIRY FORMAT

SOLICITATION W912K6-15-R-0011

NOTE: ALL PRE-PROPOSAL INQUIRIES SHALL BE SUBMITTED VIA EMAIL IN THIS FORMAT!!

EMAIL: 175WG.MSC@ang.af.mil

Date of RFI Answer: 14 Aug 15

14 Aug 15

2.7.4.7 Rapid Set Cement ; Direction is needed, with a specific scope of concrete prep, precautions, procedures, psi strengths, mix requirements, exact testing required, placement , finishing, cold weather requirments and curing to protect the Maryland Air National Guard and the contractor.

1). Want is the concrete’s psi strength that Maryland Air National Guard is trying to achieve and in how many days of curing does the concrete have to meet that psi strength ?

2). What temperatures do you want the concrete poured in.

3). What procedures is required if temperatures fall.( Cold weather or Winter pouring) Blanketing? Double Blanketing , Chemicals, Temp heat etc.

4). Will theses days be credited back if the weather is to cold to pour concrete.

1. Concrete shall be 650 psi at 90 days (Specified Flexural Strength R)

2. Paving in hot weather: Concrete must not exceed 90 degrees F.

2a. Follow Practices found in ACI 305R.

3. Paving in cold weather: When the ambient temperature is less than 50 degrees F ensure temperature of concrete is not less than 50 degrees F. Do not place concrete unless the ambient temperature is at least 35 degrees F and rising.

3a Mixture Proportion: An accelerating admixture may be used when ambient temperature is below 50 degrees. Provide covering and other means for maintaining the temperature above freezing for not less than 72 hours.

4. An appropriate credit will be applied if applicable.

21 Aug 15

Our office has recently migrated our email accounts. Please send all correspondence to :

usaf.md.175-wg.list.msc@mail.mil

Michael.a.dombkiewicz.mil@mail.mil

Frank.d.harris.mil@mail.mil

File details come from the government source that posted it. Updated .