Questions_3.docx

DOCX document 13 KB Posted

Attached to
461 VTC Upgrade
Solicitation number
W912JM19R0008
Issued by

View the file

Other files

File Type Posted
Questions_2.docx DOCX document
SOW_--_461_Command_Section_VTC_Upgrade.pdf PDF
461st_Site_Visit_Answers.docx DOCX document
Site_Visit_Instructions_VTC.docx DOCX document
Questions_1.docx DOCX document
CLAUSES.docx DOCX document
SOW_--_461_Command_Section_VTC_Upgrade.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7/18/2019

1. Are we expected to install the power drops above the ceiling or will the site electrician will be doing this?

a. The power requirements for the monitors will need to be completed by the vendor during the install.

2. Does the client prefer to use as much of the existing equipment as they can or would they prefer a bid that includes upgrading the entire system?

a. The customer is requesting all new hardware for the entire system that will provide a “turnkey’ solution.

3. Are there any VTC brands that are not preferred?

a. No, as long as the proposed equipment meets the requirement of the SOW.