Amendment_0006_Narrative.docx

DOCX document 14 KB Posted

Attached to
Repair Roof, Bldg 6900
Solicitation number
W912JB-17-B-8003
Issued by

About this file

Amendment 06 Narrative

View the file

Other files

File Type Posted
Amendment_0006.docx DOCX document
Amendment_0005.pdf PDF
Amendment_0004_attachment.pdf PDF
Amendment_0004.pdf PDF
Sign_IN_Sheet.pdf PDF
Site_Visit_MFR.docx DOCX document
PreBid_Meeting_Slides.ppt PPT presentation
Amendment_0003.pdf PDF
Wage_Determination.pdf PDF
Amendment_0001.docx DOCX document
Solicitation.docx DOCX document
Repair_Roof_6900_Drawings.pdf PDF
Repair_Roof_6900_Specifications.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The purpose of this amendment is to re-establish the bid due date, and to issue an addendum to the scope of work.

1. Change the bid opening date to 30 Jan 2018, 1300 EST.

2. All questions must be submitted to the government NLT 24 Jan 2018, 1600 EST. Submit questions to jonathan.d.bodus.mil@mail.mil. Questions will be answered in the form of an amendment to the solicitation.

3. Add Addendum 01 to the solicitation drawings to remove the requirement to demolish the existing parachute tower from the project scope of work:

a. Sheet A-100 - Remove existing roof and wall construction to below existing metal decking – there is transite siding insulation underneath the metal siding – asbestos remediation will be required.

b. Sheet A-100 – the note “Remove existing metal roof panels” at the west end of “Roof Plan B” will not be removed.

c. Sheet A-101 – Detail F will not be included in the scope of work.

d. Sheet A-200 – at the west end of ‘Roof Plan B’ the requirement for “new metal roof Panels to match existing” is eliminated from the scope of work.

e. Sheet A-200 – Detail F as called out will be removed from the scope of work.

4. Add to the scope of work: Furnish and install a new roofing system on the roof of the parachute tower as depicted in Detail A on sheet A-300. The roof will be installed per the drawings and specifications.

5. All other terms and conditions shall remain the same.