B.08.Q&A_3-6.docx

DOCX document 13 KB Posted

Attached to
Renovate FM Area - XGFG152004
Solicitation number
W912J2-19-B-6003
Issued by

About this file

Questions and Answers 3-6

View the file

Other files

File Type Posted
Attendance_Sheet_for_Bid_Opening.pdf PDF
Abstract_of_Offers_1419_Abstract_FM.pdf PDF
Q&A_11-12.docx DOCX document
W912J2-19-B-6003-0003_Conform_Copy.pdf PDF
Bid_Opening_FBO_Instructions.docx DOCX document
B.08.Q&A_7-10.docx DOCX document
W912J2-19-B-6003-0003.pdf PDF
W912J2-19-B-6003-0001.pdf PDF
Q&A_1-2.docx DOCX document
W912J2-19-B-6003-0002.pdf PDF
Site_Visit_Attendance_Sheet.pdf PDF
W912J2-19-B-6003.pdf PDF
Drawing_Set_xgfg152004_B500_set_DEC_2018.pdf PDF
SOW_XGFG152004_Ren_FM_Area_B500_DEC.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q3: PLEASE CONFIRM BID DUE DATE AND TIME, AND WHAT TIME TO MEET IN THE VISITOR PARKING LOT

A3: Bid due date and time can be found in the solicitation document. If you are planning on attending the bid opening, please be in the small parking lot outside the front gate no later than 8:50am CST. We will be escorting contractors in at precisely 8:45am.

Q4: PLEASE CONFIRM ROOM DIMENSIONS FOR WANSCOTTING FOR SHEETS A.5, A.7, A.9, A.10 FOR BIDDING PURPOSES

A4: Measuring and verifying is the responsibility of the contractor, especially with regard to the wainscot, because of the way that the panels have to be balanced for symmetry. The overall dimensions UNVERIFIED and scaled from drawings without allowances for doorways is 19’-6” x 26’-6”.

Q5: PLEASE CONFIRM CONTRACTOR ACCESS PLAN, PER THE WALK THRU IT WAS NOTED TO BE CHANGED FROM THE CONTRACT PLANS

A5: There is no change of “Access Plan.” Perhaps there was misunderstanding. The plans (T1, A1, A2) are clear about staging area and project entry access.

Q6: PLEASE PROVIDE WORK HOURS FOR THIS PROJECT AND IF THERE IS ANY "NOISY WORK" TO BE CONSIDERED OFF HOURS

A6: Right now the work hours will normally be 7:30 – 4:00 Monday through Friday except Holidays or special situations that may arise. However; these will be discussed at the preconstruction conference and agreed to by consensus. The building occupants have been briefed (on more-than one occasion) about the noisy\messy nature of our work. We will work with the contractor toward schedule fluctuations that benefit all parties and make the most efficient progress.