Questions_and_Answers_201_Set_3.doc
DOC document 27 KB Posted
- Attached to
- Restroom Repair and Fire Suppression Federal contract opportunity
- Solicitation number
- W912GY16B0006
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF_1419_Restroom_and_Fire_Suppression_201.xls | XLS spreadsheet | |
| Question_and_Answer_Set_7.doc | DOC document | |
| Questions_and_Answers_Set_6.doc | DOC document | |
| Questions_Set_5.doc | DOC document | |
| IMG_9203.JPG | JPG image | |
| IMG_9202.JPG | JPG image | |
| IMG_9200.JPG | JPG image | |
| IMG_9198.JPG | JPG image | |
| IMG_9201.JPG | JPG image | |
| IMG_9205.JPG | JPG image | |
| IMG_9199.JPG | JPG image | |
| IMG_9204.JPG | JPG image | |
| Questions_and_Answers_Set_4_201.doc | DOC document | |
| Amendment_0001_-_Extension_of_Closing_Date.pdf | ||
| BLDG._201_1st_FLR_PLN-11x17.pdf | ||
| BLDG._201_2nd_FLR_PLN-Layout1.pdf | ||
| Scope_of_Work_Fire_Suppression_Revision.doc | DOC document | |
| Site_Visit_Sign_In_Sheet.pdf | ||
| Questions_and_Answers_Set_2.doc | DOC document | |
| Question_and_Answer_Set_1_Fire_Suppression_System.doc | DOC document | |
| Drawing_-_Sheet_A-4.pdf | ||
| Drawing_-_Sheet_A-6.pdf | ||
| Drawing_-_Sheet_A-7.pdf | ||
| Solicitation_16-B-0006.pdf | ||
| ConcreteSpecifications.pdf |
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 201 Set 3 1.Can we get a lay out ( drawing) of the building as it sits now?
ANSWER: See attached.
2.
Will they be clearing out the first or second floor so we can perform this work during regular business hours ?
ANSWER: Yes
3.
If so will they be moving desk, tables, computers , and such ?
ANSWER: Yes.
4.
Or will this work be done after hours?
ANSWER: No.
5.
Will they be removing the ceiling tiles and Tee bar so we can remove and install the new pipe ?
ANSWER: No.
6.
On the Statement of work under scope of work items items #1.3.8
Provide four (4) each 100 gallon expansion tanks per building. Can we clarify 4- per building?
ANSWER: Delete the verbiage.
7. Will the building be occupied during construction?
ANSWER: No.
8. Is it the intent to have the backflow prevention device installed at the existing riser connection? If so, we believe the riser room are will need to be enlarged to accommodate for this equipment.
ANSWER: Yes.
9. Will the sprinkler systems on each floor need to be on it's own separate control valve? This is a preferred method to isolate individual floors during future maintenance/repair work.
ANSWER: Yes.