Questions_Set_6.doc

DOC document 24 KB Posted

Attached to
Construct Fence
Solicitation number
W912GY16B0005
Issued by

View the file

Other files

File Type Posted
OF_1419.xls XLS spreadsheet
Questions_Set_7.doc DOC document
Questions_Set_5.doc DOC document
Lot_23.png PNG image
Lot_33.png PNG image
Questions_Set_4.doc DOC document
Site_Visit_Sign_In_Sheet.pdf PDF
420-7_Fire.pdf PDF
SIAD_385-1_Safety_Regulation_2012-04-26_FINAL.DOC DOC document
Questions_and_Answers_Set_3.doc DOC document
TS-33_Fence_-_2015-07-28_VER_2.pdf PDF
Questions_and_Answers_Fence_Set_2.doc DOC document
Questions_and_Answers_Fence_Projects.doc DOC document
Plan_-_TS-33_Fence_-_2015-07-27.pdf PDF
Drawing_TS-23_Fence_-_2015-12-02.pdf PDF
Solicitation_16-B-0005.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions Set 6

1. We were wanting to confirm that the fence lines and gate locations for the new fence and gates will be staked by the Army/Sierra Depot at no cost to the contactor or are we to responsible for the marking of the fence and gate locations?

ANSWER: All corners will be marked by Government. Gate locations are per the drawings and shall be marked by the contractor.

2. In reading the question/ answers on list 5 I see that the ground rod quantities has changed to one at each corner. Originally it called out to have a ground rod at opposite corners, which I interpreted as meaning two

(2). Am I wrong?

ANSWER: Each corner a ground rod shall be placed.

3. On set #5 of questions and answers, the answer for question #2 dealing with the top rail says that the top rail is 1 7/8" OD, on the drawings in the Steel Post Schedule it states that the top rail is a 1.66 OD (1 5/8"), which is the standard for top rail. Can this please be clarified, is the top rail to be used on this project a 1 5/8" OD or is 1 7/8" OD. Your help in this matter would be very much appreciated.

ANSWER: Follow the drawing requirement.