Questions_and_Answers_Set_2_Baler.doc

DOC document 25 KB Posted

Attached to
Furnish and Install Baler
Solicitation number
W912GY16B0003
Issued by

View the file

Other files

File Type Posted
OF1419.xls XLS spreadsheet
Questions_and_Answers_Baler_Set_7.dot DOT file
Question_and_Answer_Baler_Set_6.doc DOC document
Questions_and_Answers_Baler_Set_5.doc DOC document
Conveyor_Specifications.pdf PDF
Questions_ _Answers_Set_4.doc DOC document
Questions_and_Answers_Baler_Set_3.doc DOC document
IMG_8792.JPG JPG image
IMG_8793.JPG JPG image
IMG_8791.JPG JPG image
Interested_Vendors_List.pdf PDF
SF30_amendment_0001_ver_2.pdf PDF
Baler_Questions_and_Answers_Set_1.doc DOC document
W912GY-16-B-0003.pdf PDF
Baler_Plan.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Set 2 Baler

1. Call for using linear transducers (1.3.2) you limit the options to one company, and this option is very costly to repair in the future---

ANSWER: Linear Transducers - measures internal ram positioning (Ram Travel -in-out) without using an external laser system. The unit shall have an internal device to achieve this. An external device is not acceptable do to potential damage and dirt build up.

2. External Light System (1.3.9) This only for an Excel and exclude all other manufacturers.

ANSWER: External Lights System - a series of lights provide Bale Completion Status in percentage of completion in 25% increments. Lights or gages are acceptable.

3. Early Bale Complete (1.3.10) Controlling a baler from a remote source is dangerous and this option is not recommended.

ANSWER: The government understands the need for safety and feels this system is necessary for operation.

4. 9" Ejection Cylinder (1.3.21) Exclude other manufactures. Most manufactures use a 8" bore cyclinder.

ANSWER: The unit must facilitate the ejection process of overcharged bales.

5. It is strongly recommended that you call out bale overcharge release door in the specs.

ANSWER: An overcharge door is not required if the ejection ram is sized properly.

6. (1.3.34) Specifically called US Wire Tier Model 342, when there is more than one options (Accent Model 470, etc).

ANSWER: Baling Wire - No recommended size or type needed in solicitation as the unit shall accept all standard sizes and types.

7. Who is responsible for supplying and installation of a dedicated phone line to the new modem supplied in the controls?

ANSWER: No phone needed. The system may have cellular communication or a standalone computer port dedicated for down-loading baling operation reporting.