Amendment_1_Bid_Schedule.pdf
PDF 44 KB Posted
- Attached to
- West Basin Scour Repair Phase 2 Federal contract opportunity
- Solicitation number
- W912EQ18B0008
About this file
Amendment 1 Bid Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912EQ18B0008-ABSTRACT_(Autosaved).pdf | ||
| 18B0008_Amendment_2.pdf | ||
| Plan_Sheet_C-300_-_Amendment_01.pdf | ||
| 01_22_00.00_11_-_Amendment_01.pdf | ||
| 18B0008_Amendment_1_.pdf | ||
| 31_11_00.00_11_-_Amendment_01.pdf | ||
| West_Basin_Scour_Repairs_Phase_2_Plans_-_For_Solicitation.pdf | ||
| A07D_IFB_16Jul18.pdf | ||
| WB_Specifications_13Jul18.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
West Basin Scour Repairs Levee B/L Sta. 705+54 to B/L Sta. 570+81
DOCUMENT 00 41 00.00 11 Page 2
FOR SOLICITATION - AMENDMENT 01
f
DOCUMENT 00 10 00
BIDDING SCHEDULE
10/8/15
PART 1 BIDDING SCHEDULE
ST. FRANCIS BASIN MAINTENANCE
WEST BASIN LEVEE - HEADWATER
DIVERSION CHANNEL SCOUR REPAIRS
LEVEE B/L STA. 705+54 TO B/L STA. 570+81
LITTLE RIVER DRAINAGE DISTRICT
CAPE GIRARDEAU COUNTY, MISSOURI
1.1 LINE ITEMS
This contract will be awarded as one lump sum with unit prices required for specifically selected work. A schedule of the unit price work is contained in Standard Form SF 1442, "Solicitation, Offer and Award." See Contract Clauses, "FAR 52.211-18, Variation in Estimated Quantity" and "FAR 52.236-16, Quantity Surveys," "DFARS 52.236-7008, Contract Prices."
Bid Items with Unit Prices Form
ITEM DESCRIPTION Estimated
Quantity
Unit
Unit Price
Amount
Mobilization and Demobilization
JA
XXX.XX
0002 Environmental Protection 1 JA XXX.XX $ .
0003 Storm Water Pollution Prevention
0003AA Write/Amend and Maintain SWPPP 1 JA XXX.XX $ .
0003AB Silt Fence or Equivalent 510 LF $ .
0003AC Erosion Control Berm or Equivalent
10,470
LF
0004 Riprap, R-400 102,670 TN $ .
0005 Semi-Compacted Backfill 8,485 CY $ .
NOTE 1: Offerors shall furnish unit prices for all items listed on the schedule of offer items, which require unit prices. If the offeror fails to insert a unit price in the appropriate blank for required items, but
0006 Seeding & Mulching 6.3 AC
0007 Grubbing & Snagging 15 AC
Grand Total Items 0001 thru 0007 $
1.2 NOTES
West Basin Scour Repairs Levee B/L Sta. 705+54 to B/L Sta. 570+81
DOCUMENT 00 41 00.00 11 Page 3
FOR SOLICITATION - AMENDMENT 01
f does furnish an extended total or an estimated amount for such items, the Government will deem his unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE
OFFEROR OMITS BOTH THE UNIT PRICE AND THE EXTENDED ESTIMATED AMOUNT FOR ANY
ITEM, HIS OFFER WILL BE DECLARED NONRESPONSIVE.
In the event there is a difference between a unit price and the extended total, the unit price will be held to be the intended offer. If the offeror shows only the total price but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended unit price.
Any offer price for items indicated above which are unbalanced as to price may be rejected as non-responsive. An unbalanced offer is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.
Award will be made as a whole to one offeror.
AC = Acre CF = Cubic Feet CY = Cubic Yard DH = Miles EA = Each FC = 1000 Cubic Feet FT = Foot HF = 100 Feet HH = 100 Cubic Feet HL = 100 Linear Feet HR = Hours HS = 100 Square Feet HY = 100 Yards LB = Pound LF = Linear Foot LH = Labor Hour JA = Job (lump sum) LY = Linear Yard MO = Months SB = Square Mile SF = Square Foot SQ = Square SY = Square Yard TL = 1000 Linear Feet TN = Net Ton UN = Unit YD = Yard YL = 100 Linear Yards YM = Cubic Yards Per Mile
All quantities are estimated except where unit is given as "JA" or "EA".
NOTE 2: If as offer or modification to a offer based on unit prices is submitted and provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price, including lump sum units, in offer schedule must be stated, or, if it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the offer schedule.
NOTE 3: Offerors are cautioned to read FAR Clause entitled "System for Award Management (52.204-7)located in Section 00 21 13 Instructions to Bidders.
-- End of Document --
| 10/8/15 |
| 10/8/15 |
File details come from the government source that posted it.