US Army Corps of Engineers
BUILDING STRONG®
Mud Mountain Dam Fish Passage Facility Pre-Proposal Site Visit
Leah Hauenstein, PE Senior Project Manager
Sara Deyermond Contracting Officer
Michael Peele, PE Care & Diversion Lead
Seattle District | October 24, 2017
Agenda
1. Itinerary Review
2. Project Background
3. Rules of Engagement
4. Procurement Information
5. Care & Diversion of Water
6. Depart for Busses
Itinerary Review
1. Buckley Armory (Pick-Up)
2. MMD Fish Passage Facility Left Bank
► Existing Trap & Haul ► Cascade Water Alliance Facilities
3. MMD Fish Passage Facility Right Bank ► Muckleshoot Fish Hatchery
4. MMD Fish Release Site ► Limited seats ► Primarily a road improvement project ► See Leah to send a representative on this leg of the tour
5. Buckley Armory (Drop-Off)
MMD Fish Passage Left Bank
Project Background
BUILDING STRONG®6
Vicinity Map
Fish Trap
Mud Mountain
Dam
Release Site
Introduction to MMD
BACKGROUND:
Mud Mountain Dam is a flood risk reduction dam protecting the lower White and Puyallup River valleys The U.S. Army Corps of Engineers built the dam on the White River in the 1940s.
The Corps also made channel improvements and built levees on the lower Puyallup River.
Together, these structures have saved an estimated $722 million in flood damages.
The project currently helps protect the homes and businesses of about 400,000 people.
PARTNERS
Mud Mountain Dam - Empty
Mud Mountain Dam - Flood
Work Site
Existing Conditions
Diversion Structure
USACE Fish Trap
NOAA BiOp National Oceanic & Atmospheric Administration (NOAA) Biological
Opinion (BiOp) Issued on October 3rd 2014
Three RPA’s:
► RPA 3 – upstream fish passage:
• 95% safe and timely attraction of adults to facility;
• 98% survival of adults through the facility to their release upstream of MMD;
• Design criteria to safely handle up to 1.25 million salmon per year; and
• Transfer up to 60,000 fish per day.
Rules of Engagement
Site Visit is for Informational Purposes Only
No Questions Beyond what is Posted in the Solicitation will be Discussed
Offerors are to Prepare their Proposal in Accordance with the RFP & any Changes will be by Amendment
All Questions Must be Submitted in ProjNet-BID
Solicitation Information
RFP Number W912DW-18-R-0001
• Issued 2 October 2017
• Due 22 December 2017 at 1pm
Amendments Issued to Date: 2
• Block 19 of SF 1442
Bid Guarantee of 20% or $3 Million (whichever is less)
• FAR 52.228-1
Caution to Offerors
Must Submit on All CLINs to be Considered for Award
No Optional CLINs
Current in SAM
Small Business Sub-Contracting Plan is Required
Offeror Questions
Potential Offerors Must Submit Questions using ProjNet BID found at www.Projnet.org
• Must be Registered to Submit and Review
• Key Access: UC4PMG-DDBFYD
CLOSES on 2 December 2017
Volume I – Technical Proposal
Factor 1 – Project Schedule Factor 2 – Care and Diversion of Water Work Plan Factor 3 – Company Experience Factor 4 – Past Performance Factor 5 – Small Business Participation
Technical Proposal MUST be Complete & in Compliance with ALL Requirements of the RFP
Technical Evaluation
Section 00 22 00
Order of Importance
Submission Requirements & Evaluation Method
Technical Evaluation of Proposals
• Conforms to the Minimum Requirements of the RFP
• Determined Technically Acceptable by Board
Volume II – Price Proposal
SF1442, Solicitation, Offer, & Award
Price Schedule
Representations & Certifications (Section 00 45 00)
Banking & Bonding Points of Contact
Offer Guarantee (Bid Bond)
Evaluation & Basis of Award
Price Evaluation
• Fairness & Reasonableness
• Unbalance Line Items
• Accept Other than Lowest Price or Reject All Offerors
Tradeoff Process in Accordance with FAR 15.101-1
IT IS THE INTENT OF THE GOVERNMENT TO
AWARD BASED ON INITIAL OFFERS,
without discussions.
Contract Clauses & Highlights 52.211-10, Commencement, Prosecution, and
Completion of Work
52.211-12, Liquidated Damages
52.219-9, SB Subcontracting Plan (ALT II)
52.236-1, Performance of Work by the Contractor
Section 00 73 46, Wage Determinations WA1 & WA95
Magnitude of Construction $100,000,000 to $250,000,000 (DFARS 236.204)
USACE Points of Contact
Monique Paano, Contract Specialist monique.a.panno@usace.army.mil
Curt Stepp, Contract Specialist curt.d.stepp@usace.army.mil
Sara Deyermond, Contracting Officer sara.l.deyermond@usace.army.mil
FACTOR 2
Care & Diversion of Water
Mike Peele, PE
C&D Overview Design Build Feature of work.
Significant Constraints due to site constraints and environmental constraints Requirements covered under Specification 01 56 00 Government Phasing Concept Provided
► Phase 1: Barrier and Intake Structure ► Phase 2: Presort Pools, Trap and Haul, General Site ► Phase 3: CWA Improvements and Existing Trap Demo
Designed for 6,500 cfs at the site (6,000 from
MMD)
Work Site
C&D Requirements White River Flows Cofferdam Temporary Flood Protection Fish Barrier Fish Passage
► Temporary Fish Passage ► Modification to the Existing Fish Trap
CWA Diversion MIT Hatchery Fish Release Site
White River
► Maximum Flow Capacity of no less than 6,500 CFS ► Manage Sediment and Debris coming into the site
Cofferdams ► Maximum Flow Capacity of no less than 6,500 CFS ► Forebay Elevation not to exceed 674’ within design flow
Temporary Flood Protection ► CWA and MIT facilities protected to 12,000 cfs
Fish Barrier
► Must be maintained at the site throughout Construction ► Must Pass 3,600 cfs within NMFS Criteria ► Must Pass 5,000 cfs and still recover the fish barrier as flows recede below 3,600 cfs
Fish Passage ► Must be maintained at the site throughout construction ► Must maintain the current level of service ► Contractor is responsible for modification to existing facilities and any necessary temporary facilities
CWA Diversion
► Must provide CWA with the ability to divert their water right throughout construction (1,000 cfs max)
► Reduced flow periods have been provided
MIT Hatchery ► Must maintain the Hatchery Effluent ► Provide a place to release juvenile fish ► Must maintain the ability to use the emergency water supply
Fish Release Site ► Must maintain a functional release site or provide a temporary release site ► 4 options provided for temporary release sites
Work Windows In Water Work Window: June 1st to February 15th allowable time to work in the river outside of cofferdams Flood Season: October 15th – March 15th , high flows possible in river Fish Trap Outage: November 15th – January 31st, no fish passage required CWA Diversion:
► Restricted Diversion: 250 cfs for 24 consecutive months with 12 months before the next restricted diversion
► Minimum Diversion: 30 cfs for 14 days between June 1st – August 31st
► Diversion Outage: No flow required between Sept 1st - January 31st (only 3 times throughout construction)
Temporary Release Site: August 1st – October 31st, temporary release sites not allowed (odd years only)
Operations Fish Passage
► Government will continue to sort and transport fish ► Contractor to operate any modifications or temporary facilities at the governments direction ► Government will operate the existing fish trap
Fish Barrier ► Contractor responsible for operations, maintenance, and repairs.
► Government will direct as necessary to maintain flow capacity and safe/timely passage of fish ► USACE Designed Barrier
• Operated by the contractor at the Governments direction
• Guide lines for operations will be provided
Temporary Facilities ► Contractor responsible for operations, maintenance, and repairs
Government Concept
C&D Phasing Schematic
C&D Phase 1 Schematic
C&D Phase 2 Schematic
C&D Phase 3 Schematic
C&D Phase 1 Fish Ladder Extension
C&D Temporary Fish Passage Facility
C&D Phase 2 Fish Ladder Extension
DEPART FOR BUSSES
• Use the restroom
• Return your badges at security
• Check-in with Leah if you were on the Waitlist
• Check-in with Leah if you would like to see the
| Mud Mountain Dam Fish Passage Facility Pre-Proposal Site Visit� |
| Agenda |
| Itinerary Review |
| MMD Fish Passage Left Bank |
| Project Background |
| Slide Number 6 |
| Introduction to MMD |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| NOAA BiOp |
| Rules of Engagement |
| Solicitation Information |
| Caution to Offerors |
| Offeror Questions |
| Volume I – Technical Proposal |
| Technical Evaluation |
| Volume II – Price Proposal |
| Evaluation & Basis of Award |
| Contract Clauses & Highlights |
| USACE Points of Contact |
| FACTOR 2�Care & Diversion of Water |
| C&D Overview |
| Slide Number 28 |
| C&D Requirements |
| C&D Requirements |
| C&D Requirements |
| C&D Requirements |
| Work Windows |
| Operations |
| Government Concept |
| Slide Number 36 |
| Slide Number 37 |
| Slide Number 38 |
| Slide Number 39 |
| Slide Number 40 |
| Slide Number 41 |
| Slide Number 42 |
File details come from the government source that posted it. Updated .