Amendment_0005_Project_Table_of_Contents_IFB_final.pdf

PDF 49 KB Posted

Attached to
Pershing Barracks Renovation/Modernization, West Point New York Federal contract opportunity
Solicitation number
W912DS-16-B-0010
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

Amendment 0005_Project Table of Contents IFB final

View the file

Other files for this federal contract opportunity

Other files attached to Pershing Barracks Renovation/Modernization, West Point New York, newest first.
File Type Posted
Bid_Abstract.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0005_Sections_Specsrr.pdf PDF
Amendment_0005_CD101_-_Exhibit_-_Temporary_Fence.pdf PDF
Amendment_0005_Pershing_Submittal_Register_IFB.pdf PDF
Amendment_0003_Historical_Pictures.pdf PDF
Amendment_0003_Drawings.pdf PDF
Amendment_0003_Pershing_Field_Investigation_Report.pdf PDF
Amendment_0003_EXHIBIT_-_SITE_UTILITIES.pdf PDF
B-1_Pershing_751_Framing_plbg_roof.pdf PDF
Pershing_738_740_751_Repair Shower Rooms.pdf PDF
6833.tif TIF image
Amendment_0002_Site_Visit_Sign_In_Sheet.pdf PDF
Amendment_0002.pdf PDF
7687-5942.tif TIF image
B-7_Pershing_751_painting.pdf PDF
36993_00751_01.dwg DWG drawing
Amendment_0002_Geotechnical_Evaluation.pdf PDF
36993_00751_04.dwg DWG drawing
Pages from C-6_Pershing_751_fixtures_roof plan_windows.pdf PDF
1261.tif TIF image
7687-5941.tif TIF image
A-1_Pershing_751_Maint and Repairs.pdf PDF
LIFE SAFETY Pages from A-1_Pershing_751_Maint and Repairs 1.pdf PDF
36993_00751_02.dwg DWG drawing
C-7_Pershing_751_flooring_painting.pdf PDF
36993_00751_03.dwg DWG drawing
NO. 2.tif TIF image
A-8_Pershing_751_Roof Repl and insul.pdf PDF
7687-5947.tif TIF image
B-8_Pershing_conversion_arch_plbg_HVAC_elec.pdf PDF
C-6_Pershing_751_fixtures_roof plan_windows.pdf PDF
7687-5943.tif TIF image
A-6_Pershing_751_Maint Rep_conversion.pdf PDF
C-8_Pershing_751_floor plans_roof plan.pdf PDF
7687-5939.tif TIF image
7687-5945.tif TIF image
7687-5940.tif TIF image
B-6_Pershing_751_Floor_roof plans.pdf PDF
36993_00751_L1.dwg DWG drawing
Amendment_0002_Asbestos_Report.pdf PDF
Amendment_0001_Section_28_08_10.pdf PDF
Amendment_0001_Section_28_10_05.pdf PDF
Amendment_0001.pdf PDF
PLANS_Pages_51-100rd.pdf PDF
PLANS_Pages_251-320.pdf PDF
PLANS_Pages_1-50.pdf PDF
W912DS-16-B-0010.pdf PDF
2016_0608_Pershing_IFB_Specs_Volume_2.pdf PDF
Show all 50

Pershing Barracks Renovation/Modernization, West Point New York has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RENOVATION AND MODERNIZATION OF PERSHING BARRACKS W912DS-16-B-0010

USMA West Point, New York

Project Table of Contents Page 1 Issue for Bid June 8, 2016 Amendment 5

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 SEALS PAGE

00 10 00 SF 1442 AND BIDDING SCHEDULE (Section Supplies or Services and Price)

00 21 16 INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00.00 18 SPECIAL CONTRACT REQUIREMENTS 03/15

00 75 95 ROOF SYSTEM 20-YEAR DIAGNOSTICS/PERFORMANCE WARRANTY

00 90 00 WAGE RATES

00 90 01 Staging Area and Laydown

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK 08/11

01 32 01.00 10 PROJECT SCHEDULE: NETWORK ANALYSIS SYSTEM (NYD) 02/15

• FLOW CHART FOR HVAC TESTING, BALANCING, AND

COMMISSIONING (FIGS. 1 AND 2)

• STANDARD DATA EXCHANGE FORMAT (ER-1-11)

01 33 00 SUBMITTAL PROCEDURES (NON-UFGS)

01 33 29 LEED(TM) DOCUMENTATION 05/12

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS 02/12

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS 08/10

01 45 02.00 18 QUALITY CONTROL SYSTEM (QCS) 07/10

01 45 04.00 18 CONTRACTOR QUALITY CONTROL 06/01

01 45 20.00 18 TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS (NYD) 08/08

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS 08/09

01 52 60.00 18 CONSTRUCTION INDOOR AIR QUALITY MANAGEMENT (NYD) 02/10

01 57 20 .00 10 ENVIRONMENTAL PROTECTION 04/06

01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS 05/13

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT 01/07

01 78 00.00 18 CLOSEOUT SUBMITTALS (NYD) 06/12

01 78 23.00 18 OPERATION AND MAINTENANCE DATA (NYD) 07/06

01 81 13 SUSTAINABLE DESIGN REQUIREMENTS (NON-UFGS)

01 91 00 COMMISSIONING (NON-UFGS)

DIVISION 02 – EXISTING CONDITIONS

02 04 00 SHORING AND BRACING (NON-UFGS)

02 41 00 DEMOLITION AND DECONSTRUCTION 05/10

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES 02/10

02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT 02/10

DIVISION 03 – CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE (NON UFGS)

DIVISION 04 – MASONRY

04 01 00 MASONRY RESTORATION (NON-UFGS)

04 01 10 EXTERIOR REPOINTING (NON-UFGS)

Project Table of Contents Page 2

Amendment 5

04 20 00 INTERIOR MASONRY 02/11

DIVISION 05 – METALS

05 05 23 WELDING, STRUCTURAL 11/08

05 12 00 STRUCTURAL STEEL FRAMING (NON-UFGS)

05 21 00 STEEL JOISTS (NON-UFGS)

05 30 00 STEEL DECKING (NON-UFGS)

05 40 00 COLD FORMED METAL FRAMING 05/10

05 50 13 MISCELLANEOUS METAL FABRICATIONS 05/10

05 51 00 METAL STAIRS 02/12

05 51 33 METAL LADDERS 05/10

05 72 00 DECORATIVE METAL RESTORATION (NON-UFGS)

05 73 00 INTERIOR DECORATIVE METAL RAILINGS AND GATES 11/13

DIVISION 06 – WOOD, PLASTIC, AND COMPOSITES

06 10 00 ROUGH CARPENTRY 02/12

06 20 00 FINISH CARPENTRY 02/12

06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS 08/10

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 11 13 BITUMINOUS DAMPPROOFING 08/11

07 13 53 ELASTOMERIC SHEET WATERPROOFING 04/06

07 21 10 SPRAYED FOAM INSULATION FOR BUILDING ENVELOPE 12/13

07 21 13 BOARD INSULATION 05/11

07 21 16 MINERAL FIBER BLANKET INSULATION 11/11

07 22 00 ROOF AND TRAFFIC DECK INSULATION 08/11

07 41 13.16 COPPER ROOF PANELS 08/09

07 42 13 METAL WALL PANELS 05/11

07 52 00 MODIFIED BITUMINOUS ROOFING MEMBRANE 05/12

07 60 00 FLASHING AND SHEET METAL 08/08

07 61 14.00 20 STEEL STANDING SEAM ROOFING 05/11

07 81 00 SPRAY-APPLIED INTUMESCENT FIREPROOFING 02/11

07 84 00 FIRESTOPPING 05/10

07 92 00.01 EXTERIOR JOINT SEALANTS 01/07

07 92 00.02 INTERIOR JOINT SEALANTS 01/07

DIVISION 08 – OPENINGS

08 11 13 STEEL DOORS AND FRAMES 02/10

08 14 00 WOOD DOORS 08/11

08 14 10 WOOD DOOR RESTORATION (NON-UFGS)

08 51 13 ALUMINUM WINDOWS 05/11

08 60 45 SKYLIGHTS AND TRANSLUCENT PANELS 02/12

08 71 00 DOOR HARDWARE 08/08

08 81 00 GLAZING 08/11

DIVISION 09 – FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD 02/10

Project Table of Contents Page 3

Amendment 5

09 22 36 LATH 01/08

09 23 00 GYPSUM PLASTERING 08/10

09 24 23 STUCCO 05/09

09 29 00 GYPSUM BOARD 05/11

09 30 00 CERAMIC TILE 08/10

09 30 10 CERAMIC TILE RESTORATION (NON-UFGS)

(09 51 00 DELETED)

09 62 38 STATIC CONTROL FLOORING 11/12

09 64 00 WOOD FLOORING RESTORATION (NON-UFGS)

09 65 00 RESILIENT FLOORING 08/10

09 66 23 RESINOUS TERRAZZO FLOORING 08/10

09 67 23.14 CHEMICAL-RESISTANT RESINOUS FLOORING 08/10

09 68 00 CARPET 05/10

09 90 00 PAINTS AND COATINGS 05/11

09 97 30 PAINTING HISTORIC METAL SURFACES (NON-UFGS)

DIVISION 10 – SPECIALTIES

10 14 00.00 20 INTERIOR SIGNAGE 11/12

10 21 13 TOILET COMPARTMENTS AND SOLID PHENOLIC CASEWORK 01/07

10 26 13 CORNER GUARDS 08/10

10 28 13 TOILET ACCESSORIES 07/06

10 44 16 FIRE EXTINGUISHERS 05/12

10 51 13 METAL LOCKERS AND CABINETS 05/11

10 56 13 STEEL SHELVING 04/06

10 74 13 EXTERIOR CLOCK RESTORATION (NON-UFGS)

DIVISION 11-– EQUIPMENT

(11 31 13 DELETED)

DIVISION 12 – FURNISHINGS

12 21 00 WINDOW BLINDS 08/10

12 93 00 SITE FURNISHINGS 02/09

DIVISION 14 – CONVEYING EQUIPMENT

14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS 02/09

DIVISION 21 – FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION 05/09

21 30 00 FIRE PUMPS 04/08

DIVISION 22 – PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE 11/11

22 05 83.63 CURED-IN-PLACE PIPE (CIPP) LINING 11/13

22 07 19 PLUMBING PIPING INSULATION 08/13

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

Project Table of Contents Page 4

Amendment 5

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST

SYSTEMS 08/10

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS 08/10

23 05 15 COMMON PIPING FOR HVAC 02/09

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT 02/11

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC 08/09

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS 02/13

23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS 01/08

23 09 23 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER

BUILDING CONTROL SYSTEMS 05/11

23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM 04/06

23 22 13.35 40 STEAM TRAPS 02/11

23 22 23.00 40 STEAM CONDENSATE PUMPS 02/11

23 22 25.00 40 STEAM VALVES 02/11

23 23 00 REFRIGERANT PIPING 10/07

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS 11/08

23 31 13.00 40 METAL DUCTS 11/12

23 34 23.00 40 HVAC POWER VENTILATORS 02/11

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS 05/10

23 57 10.00 10 FORCED HOT WATER HEATING SYSTEMS USING WATER AND

STEAM HEAT EXCHANGERS 01/08

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING

SYSTEMS 08/09

23 70 03.00 10 HEATING AND UTILITIES SYSTEMS, CENTRAL STEAM 01/08

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT 04/08

23 82 19.00 40 FAN COIL UNITS 02/11

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS 07/06

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL 08/13

26 05 13.00 40 MEDIUM-VOLTAGE CABLES 08/10

26 05 19.00 10 INSULATED WIRE AND CABLE 11/08

26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES 05/11

26 08 00 APPARATUS INSPECTION AND TESTING 08/08

26 09 13 POWER MONITORING SYSTEM 11/08

26 09 23.00 40 LIGHTING CONTROL DEVICES 08/13

26 11 16 SECONDARY UNIT SUBSTATIONS 02/10

26 12 19.00 40 PAD-MOUNTED, LIQUID-FILLED MEDIUM-VOLTAGE

TRANSFORMERS 02/11

26 20 00 INTERIOR DISTRIBUTION SYSTEM 08/08

26 22 00.00 10 480-VOLT STATION SERVICE SWITCHGEAR AND TRANSFORMERS 10/07

26 23 00 SWITCHBOARDS AND SWITCHGEAR 02/11

26 24 16.00 40 PANELBOARDS 08/10

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION 10/07

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS 04/06

26 51 00 INTERIOR LIGHTING 07/07

26 56 00 EXTERIOR LIGHTING 05/13

26 56 10 HISTORIC EXTERIOR LIGHTING RESTORATION (NON-UFGS)

Project Table of Contents Page 5

Amendment 5

DIVISION 27 – COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM 04/06

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS 08/11

27 10 00 TELECOMMUNICATIONS CABLING SYSTEM 08/11

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING 11/08

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

(28 16 01.00 10 DELETED)

(28 20 01.00 10 DELETED)

28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING 05/16

28 10 05 ELECTRONIC SECURITY SYSTEM (ESS) 05/16

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM 08/11

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK 08/08

31 48 00 UNDERPINNING (NON-UFGS)

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS 08/08

32 10 00 BITUMINOUS CONCRETE PAVEMENT 08/08

32 11 10 RAPID DRAINAGE MATERIAL 08/08

32 11 16.16 STRUCTURAL SOIL BASE COURSE FOR RIGID PAVING 11/11

32 16 13 CONCRETE SIDEWALKS AND CURBS 04/08

32 17 24.00 10 PAVEMENT MARKINGS 04/08

32 84 24 IRRIGATION SPRINKLER SYSTEMS 08/11

32 92 23 SODDING 04/06

32 93 00 EXTERIOR PLANTS 02/10

DIVISION 33 – UTILITIES

33 11 00 WATER DISTRIBUTION 02/11

33 40 00 STORM DRAINAGE UTILITIES 02/10

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION 02/15

APPENDIX

GEOTECHNICAL EVALUATION

--End of Section --