Bid Abstract for IFB 17-Jan-2017

View the file

Other files

File Type Posted
E-16_Award_Notice_EBS_W912DR-17-C-0017.pdf PDF
C-5_Amendment_0002_w-attachment.pdf PDF
C-5_Amendment_0001_w-attachment.pdf PDF
A-2_Drawings_Orig-Full.pdf PDF
Attachment_2_-_SF_LLL.pdf PDF
C-5_Solicitation.pdf PDF
Attachment_1_-_EFT_UFC_Form_23.pdf PDF
A-11_Wage_Determination_DC160002.pdf PDF
A-2_Spec's.pdf PDF
Attachment_3_-_S-1_02.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chart1

SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 0 6301993 36202 6338195 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 0 6405000 127000 6532000 -3.0577317359279731E-2 193805 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 0 1572000 275000 177000 28000 28000 130000 2210000 -5.9952038369304558E-2 -125000 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 0 1 -6532000 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 SERVICE All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified. TOTAL = PERCENT ABOVE/BELOW IGE = AMOUNT OVER IGE = BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades LOCATION: Washington , DC LINE CLIN 0001 CLIN 0002 Sheet1 BID ABSTRACT FOR W912DR-17-B-0003 Dalecarlia Chemical Building Electrical Upgrades

LOCATION: Washington , DC
LINESERVICEIGEJohn C. Grimberg Co., Inc.W.M. Schlosser Company, Inc.BuildersQSS International, Inc.Ritz Construction Inc.Grunley Construction, Inc.CPP ConstructionNorair Engineering Corp.
CLIN 0001All costs in connection with construction of the Dalecarlia Chemical Building Electrical Upgrade project, complete as shown on the drawings and as specified, but exclusive of the work covered under Optional Item 0002 below$6,301,993.00$6,405,000.00$7,033,000.00$8,209,635.00$6,951,034.00$7,645,000.00$7,700,000.00$7,620,000.00
CLIN 0002All costs in connection with construction of Bid Option 1 complete, as shown on the drawings and as specified.$36,202.00$127,000.00$100,000.00$250,000.00$92,050.00$90,000.00$200,000.00$70,000.00
TOTAL =$6,338,195.00$6,532,000.00$7,133,000.00$8,459,635.00$7,043,084.00$7,735,000.00$7,900,000.00$7,690,000.00
PERCENT ABOVE/BELOW IGE =-3.06%-12.54%100.00%100.00%ERROR:#DIV/0!ERROR:#DIV/0!-33.47%-11.12%-22.04%-24.64%-21.33%
AMOUNT OVER IGE =$193,805.00$794,805.00-$6,532,000.00-$7,133,000.00$0.00$0.00$2,121,440.00$704,889.00$1,396,805.00$1,561,805.00$1,351,805.00

Sheet2