Amendment_0001_released.pdf

PDF 588 KB Posted

Attached to
Truman Protective Relay and Governor Upgrades
Solicitation number
W912DQ18B1022
Issued by

About this file

Amendment 0001 change to specs

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DQ18B1022

469651

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Change in section 01 11 00.00 26 - answ er to contractor question

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jul-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ18B1022

X 9B. DATED (SEE ITEM 11)

19-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jul-2018

CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

01 11 00.00 26 - 2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGE

This section replaces previous section.

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL

REQUIREMENTS SECTION 01 11 00.00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Locations and Descriptions

1.3 REFERENCE DRAWINGS

1.4 OCCUPANCY OF PREMISES

1.5 EXISTING WORK

PART 2 PRODUCTS - NOT

USED PART 3 EXECUTION -

NOT USED

-- End of Section Table of Contents --

01 11 00.00 26 - 3

SECTION 01 11 00.00 26

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their relationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The scope of work for this contract consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to upgrade governor controls and the protection systems at Harry S. Truman powerhouses.

All work will be in strict accordance with the detailed requirements of this contract. The contractor is responsible for field verifying existing drawings and creating as-built drawings. The work includes, but is not limited to, the following:

a. Remove existing Woodward Atlas I Digital Governor Controllers and

HMIs in accordance with Section 48 19 00.00 26.

b. Provide new Digital Governor programmable logic controllers (PLCs) and new HMIs in accordance with Section 48 19 00.00 26.

c. Remove existing SEL-300G Relays in accordance with Section 26 28

01.00 26.

d. Provide new SEL-300G Relays with expanded I/O in accordance with

Section 26 28 01.00 26.

e. Remove existing Station Service Relays in accordance with Section 26 28 01.00 26.

f. Provide new Station Service Relays in accordance with Section 26 28

01.00 26.

1.2.2 Locations and Descriptions

Harry S. Truman Dam is located on the Osage River, a tributary of the Missouri River and near the town of Warsaw, Missouri. Harry S. Truman powerhouse has 6 units rated at 27 MW each.

1.3 REFERENCE DRAWINGS

a. One set of Reference Drawings and Specifications will be furnished to the Contractor without charge per Section 00700 Contract Clause

252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS.

b. Reference Drawings are not as built. The contractor is responsible for furnishing as-built drawings of the installation.

c. Upon mobilization to the job site, immediately check furnished reference drawings and notify the Government of any discrepancies.

1.4 OCCUPANCY OF PREMISES

a. Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

b. Before work is started, the Contractor shall arrange with the

Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.5 EXISTING WORK

In addition to Section 00700 Contract Clause 52.236-9, PROTECTION OF

EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portion of the existing work to remain.

b. Upon completion of the work, repair or replace portions of existing work, which have been damaged by Contractor's operations, to preconstruction conditions at the expense of the Contractor.

PART 2 PRODUCTS - NOT

USED PART 3 EXECUTION - NOT

USED

-- End of Section