Additional_QandA.pdf

PDF 6 KB Posted

Attached to
Repair Earthen Roof bldg 2201
Solicitation number
W912D0-16-Q-0010
Issued by

About this file

Additional questions and answers

View the file

Other files

File Type Posted
DPW-10016-2J_-_SOW_(Revision01).pdf PDF
Orig_7_of_12.pdf PDF
Questions_and_Answers.pdf PDF
W912D0-16-Q-0010-0002.pdf PDF
DPW-10016-2J_-_SOW_Amendment_0001.pdf PDF
W912D0-16-Q-0010.pdf PDF
WD_AK160001.pdf PDF
W912D0-16-Q-0010-0001.pdf PDF
DPW-10016-2J_-_SOW.pdf PDF
Details_and_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q: What is the distance from the Soil Stockpile to the work site?

A: Approximately 4 miles one way.

Q: If material is being hauled to site by dump truck will the truck need to be escorted?

A: Escort not needed.

Q: If truck has to be escorted can crew still work while truck is gone?

A: Escort not needed.

Q: When would we expect a NTP if awarded the project?

A: Typically within 10 days of contract award assuming all bonding, permits, and submittals are approved.

Q: How fast can the CSPE submittal be reviewed and approved so that the CSPE liner can be ordered?

A: The Contractor will need all submittals approved before NTP can be made.

Q: We also have concerns that the project cannot be completed before sub-zero weather begins, what are your thoughts on that?

A: Depending upon when NTP occurs, the lead time for the CSPE liner to arrive to the job site, and the weather; it is likely the work could have to wait till next spring when the weather would work. If everything worked out well it is possible the job could be completed before this winter.