W912BU19B00050002.pdf
PDF 204 KB Posted
- Attached to
- 2989 Floating Crane Barge Federal contract opportunity
- Solicitation number
- W912BU19B0005
About this file
Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sign_In_Sheet.pdf | ||
| 19B0005_Abstract_(Audited)(KO).pdf | ||
| W912BU19B00050005.pdf | ||
| W912BU19B00050004.pdf | ||
| W912BU19B00050003.pdf | ||
| 380-427_series.pdf | ||
| 200-330_series.pdf | ||
| 500-600_series.pdf | ||
| 100_series.pdf | ||
| 700_series.pdf | ||
| W912BU19B0005_01.pdf | ||
| Q_and_A-12Aug19.pdf | ||
| 850-B405-01_Cathodic_Protection.pdf | ||
| 850-B406-01_MDC_STANDARD_FLOATING_PLANT_PAINT_SCHEDULE.pdf | ||
| DRAWING_2.pdf | ||
| DRAWINGS_3.pdf | ||
| DRAWINGS_5.pdf | ||
| DRAWINGS_4.pdf | ||
| DRAWINGS_1.pdf | ||
| W912BU19B0005.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W25PHS90302541
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Incorporate Q&A as of 22 August 2019.
2. Add ABS Revised Draw ings Package
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU19B0005
X 9B. DATED (SEE ITEM 11)
02-Aug-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Aug-2019
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BU19B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
QUESTIONS AND ANSWER 2
QUESTIONS AND ANSWER PER AMENDEMENT 0002
Questions that may be of general interest of all Bidders/Government will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or clarify and simplify the question(s). Questions and answers are issued to the Offerors for information purposes only.
Question 4. Drawing 850-B205-01 sheet 4 shows maximum air draft of 72’-3-5/8”. This causes some problems for bridge height restrictions. Is the upper mast/flag pole removable as shown on the attached drawing, if the contractor comes into issues with bridge height restrictions?
Answer 4. Per Reference Drawing 4836A General Arrangement (Page 47 of 52 in Drawing package 4), the flagpole is hinged to assist with air draft requirement. Per the drawing dimensions, this will reduce the height of the crane by approximately 7’ 11-3/4".
Question 5. The Drawing 850-B554-01 conflicts specification Section C554 Spud Handling System. The drawing line pull ratings are conflicting and only possible to meet using a 2 speed motor, but that cannot be used with a VFD.
Please clarify spec vs. drawing requirement for line pulls, and at what layer.
Answer 5. The spud winches shall be capable of developing a full drum single line pull of 17,500 lbs. at a minimum speed of 45 ft./min. on the first layer. At near zero line speed the line pull shall increase to a minimum of twice that force (35,000 lbs.) on the first layer. This shall be accomplished using a VFD as specified in the solicitation.
(End of Summary of Changes)