Bid_Schedule_Updated_(revised_13_Dec_2016).pdf

PDF 56 KB Posted

Attached to
Submission of proposals update #2 Federal contract opportunity
Solicitation number
W9128F-16-T-0053
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

Updated Bid Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Submission of proposals update #2, newest first.
File Type Posted
Q&As,_Amend__9_(3_Feb_2017).pdf PDF
W9128F-16-T-0053-0009.pdf PDF
Revised_Bid_Schedule,_Amend__9_(3_Feb_2017).pdf PDF
W9128F-16-T-0053-0008.pdf PDF
Bid_Schedule(revised_30_Jan_2017.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Drawing-MRN4OA101_Amend_8.pdf PDF
Spec_01_11_00_Amendment_8.pdf PDF
Drawing_83E304.10_THREE_LINE_SHEET_1.pdf PDF
Bid_Schedule(revised_23_Jan_2017.pdf PDF
Amendment__7,__W9128F-16-T-0053.pdf PDF
Amendment__6,_W9128F-16-T-0053.pdf PDF
Drawing_Updates_(Amendment_5).pdf PDF
Amendment__5,_W9128F-16-T-0053.pdf PDF
Summary_of_Work_(01_11_00_Amendment_5).pdf PDF
Drawings_for_Oahe_(Addional_For_Information_Only)_.pdf PDF
Summary_of_Changes.pdf PDF
Questions_and_Answers.pdf PDF
Amendment__4_,_W9128F-16-T-0053.pdf PDF
Amendment__3_ _W9128F-16-T-0053.pdf PDF
W9128F-16-T-0053_(Amendment__1).pdf PDF
W9128F-16-t-0053_(Amendment__2).pdf PDF
Site_vist_POCs.docx DOCX document
Site_vist_POCs.docx DOCX document
Replace_Powerhouse_Potential_and_Current_Transformer_Dwgs.pdf PDF
FBO_Solicitation_copy.pdf PDF
Replace_Powerhouse_Potential_and_Current_Transformers_Specs.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 10 00 Page 3

BID (PRICING) SCHEDULE

BASIC ITEMS

(30 December 2018)

ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT

Mobilize/demobilize for all work (Fort Peck)

Job

Fabricate and supply of all potential and current transformers, and all associated hardware (Fort Peck)

0002AA Units1 & 3 Meter CTs (2500/5A) (Fort Peck)

6 Ea. $_____________________

0002AB Unit 2 Meter CTs (1000/5) (Fort Peck)

3 Ea. $_____________________

0002AC Unit 1-3 Meter PTs (7960/66.4V) (Fort Peck)

9 Ea. $_____________________

0002AD Unit 1-3 Exciter PTs (7960/66.4V) (Fort Peck)

9 Ea. $_____________________

0002AE Units 4 &5 Meter CTs (2500/5A) (Fort Peck)

6 Ea. $_____________________

0002AF Units 4 & 5 Meter PTs (14400/120) (Fort Peck)

4 Ea. $_____________________

0002AG Units 4 & 5 Exciter PTs (14400/120V) (Fort Peck)

4 Ea. $_____________________

0002AH Station Service Meter CTs (300/5A) (Fort Peck)

6 Ea. $_____________________

0002AJ Station Service Meter PTs (2400/120V) (Fort Peck)

6 Ea. $_____________________

Installation of each unique set of potential and current transformers per requirements (Fort Peck)

0004 Spare Parts (Fort Peck) 1 Kit $_____________________ work (Oahe) transformers, and all associated hardware (Oahe)

0006AA Units 1-7 Meter CTs (5000/5A) (Oahe)

Ea.

0006AB Unit 1-7 Meter PTs (14400/120) (Oahe)

00 10 00 Page 4

BASIC ITEMS

(30 December 2018)

ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT

0006AC Unit 1-7 Exciter PTs

(14400/120) (Oahe)

Ea.

0006AD Jack Bus PTs (14400/120) (Oahe)

0006AE 13.8kV Auto XFMR Station Service Meter CTs (150/5A) (Oahe)

0006AF 480V Station Service Meter CTs (1500/5A) (Oahe)

0006AG Station Service Meter PTs (Oahe) requirements (Oahe)

0008 Spare Parts (Oahe) 1 Kit $_____________________ work (Fort Randall) transformers, and all associated hardware at (Fort Randall)

0010AA Unit 1-8 Meter PTs (14400/120) (Fort Randall)

0010AB Unit 1-8 Exciter PTs (14400/120) (Fort Randall)

0010AC Jack Bus PTs (14400/120) (Fort Randall)

0010AD 13.8kV Station Service Meter CTs (150/5A) (Fort Randall) transformers per requirements (Fort Randall)

0012 Spare Parts (Fort Randall) 1 Kit $_____________________

TOTAL BASIC AMOUNT (Items 0001 thru 0012) $_____________________________

00 10 00 Page 5

Option (If option for the separately priced line items are not exercised at the time of award and later exercised, ten (10) months will be added to extend the delivery date (delivery not to exceed 30 October 2019)

ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT

work (Big Bend) transformers, and all associated hardware (Big Bend)

0014AA Units 1-8 Meter CTs (3000/5A) (Big Bend)

24 Ea. $_____________________

0014AB Unit 1-8 Meter PTs (14400/120) (Big Bend)

0014AC Unit 1-8 Exciter PTs (14400/120) (Big Bend)

0014AD Jack Bus PTs (14400/120) (Big Bend)

0014AE 13.8kV Station Service SS1 and SS2 Meter CTs (2000/5A) (Big Bend)

0014EF 13.8kV Station Service SS3 Meter CTs (2000/5A) (Big Bend)

0014EG Station Service Meter PTs (480/120V) (Big Bend) requirements (Big Bend)

0016 Spare Parts (Big Bend) 1 Kit $_____________________ work (Gavins Point) transformers, and all associated hardware (Gavins Point)

0018AA Units 1-3 Meter CTs (2000/5A) (Gavins Point)

0018AB Unit 1-3 Meter PTs & Drawers (14400/120) (Gavins Point)

0018AC Unit 1-3 Exciter PTs & Drawers (14400/120) (Gavins Point)

0018AD 13.8kV Station Service Meter CTs (100/5A) (Gavins Point)

00 10 00 Page 6

Option

(If option for the separately priced line items are not exercised at the time of award and later exercised, ten (10) months will be added to extend the delivery date (delivery not to exceed 30 October 2019)

ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT

000018AE Station Service Meter PTs (Gavins Point) transformers per requirements (Gavins Point)

Installation of all remaining potential and current transformers per requirements (Gavins Point)

0021 Spare Parts (Gavins Point) 1 Kit $_____________________

TOTAL OPTION (Items 0013 thru 0021) $_____________________________

TOTAL BASE PLUS OPTION (Items 0001 thru 0021) $_____________________________

NOTES:

1. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job prices and the total amount, the lump-sum prices will be considered the price submitted.

2. A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump-sum price affected. If the modification is not so apportioned, the single adjustment will be applied on a pro rata basis to all bid items.

BID (PRICING) SCHEDULE
BASIC ITEMS
BASIC ITEMS

File details come from the government source that posted it. Updated .