1. SOLICITATION NO.2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 3 PAGES
1/25/2018 2/26/2018
4. ISSUING OFFICE
DISTRICT ENGINEER CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
PORTLAND DISTRICT, CORPS OF ENGINEERS
P.O. BOX 2946
PORTLAND, OR 97208-2946
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
(CHECK A, B, OR C AND COMPLETE NO.1 NO.2 NO.3
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR
A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURITY
X (WITHOUT PROFIT) 20% of bid price or $3 million 20% of bid price or $3 million 20% of bid price or $3 million
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED (INCLUDING PROFIT) Amd. 0001 through 0003 Amd. 0001 through 0003 Amd. 0001 through 0003
6. NUMBER OF ADDENDA ISSUED 4
7A.
ITEM E. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED NO. QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT No. 1 vs IGE No. 2 vs IGE No. 3 vs IGE
0001 Mobilization and Demobilization 1 JOB 6,220,127.00$ 6,220,127.00$ 7,460,000.00$ 7,460,000.00$ 7,540,000.00$ 7,540,000.00$ 6,193,555.00$ 6,193,555.00$ 19.9% 21.2% -0.4%
San Francisco Mainship Channel (MSC) Bin Measure to Required Depth, OBDS & SF8 Ocean Disposal 150000 CY 5.00$ 750,000.00$ 4.50$ 675,000.00$ 5.75$ 862,500.00$ 3.45$ 517,500.00$ -10.0% 15.0% -31.0%
San Francisco Mainship Channel (MSC) Bin Measure to Required Depth, OBDS & SF8 Ocean Disposal (OPTION)
150000 CY 5.00$ 750,000.00$ 4.30$ 645,000.00$ 5.20$ 780,000.00$ 2.00$ 300,000.00$ -14.0% 4.0% -60.0%
San Francisco Mainship Channel (MSC) Contractor Survey
1 JOB 50,440.00$ 50,440.00$ 35,000.00$ 35,000.00$ 80,000.00$ 80,000.00$ 15,000.00$ 15,000.00$ -30.6% 58.6% -70.3%
San Francisco Mainship Channel (MSC) Contractor Survey (OPTION) 1 JOB 25,220.00$ 25,220.00$ 35,000.00$ 35,000.00$ 35,000.00$ 35,000.00$ 15,000.00$ 15,000.00$ 38.8% 38.8% -40.5%
San Francisco Mainship Channel (MSC) Contractor Survey (OPTION) 1 JOB 25,220.00$ 25,220.00$ 35,000.00$ 35,000.00$ 35,000.00$ 35,000.00$ 15,000.00$ 15,000.00$ 38.8% 38.8% -40.5%
Humboldt Bay Bar/Entrance Channel (HUM) Bin Measure to Required Depth, HOODS Ocean Disposal 500000 CY 4.09$ 2,045,000.00$ 3.45$ 1,725,000.00$ 3.50$ 1,750,000.00$ 4.25$ 2,125,000.00$ -15.6% -14.4% 3.9%
Humboldt Bay Bar/Entrance Channel (HUM) Bin Measure to Required Depth, HOODS Ocean Disposal (OPTION)
150000 CY 4.01$ 601,500.00$ 3.40$ 510,000.00$ 3.30$ 495,000.00$ 2.00$ 300,000.00$ -15.2% -17.7% -50.1%
Humboldt Bay Bar/Entrance Channel (HUM) Bin Measure to Required Depth, HOODS Ocean Disposal (OPTION)
150000 CY 4.01$ 601,500.00$ 3.35$ 502,500.00$ 3.30$ 495,000.00$ 2.00$ 300,000.00$ -16.5% -17.7% -50.1%
Humboldt Bay Bar/Entrance Channel (HUM) Bin Measure to Required Depth, Increment For One Foot Paid Overdepth, HOODS Ocean Disposal (OPTION) 500000 CY 0.45$ 225,000.00$ 0.05$ 25,000.00$ 0.15$ 75,000.00$ 2.00$ 1,000,000.00$ -88.9% -66.7% 344.4%
Humboldt Bay Bar/Entrance Channel (HUM) Bin Measure to Required Depth, Increment For One Foot Paid Overdepth, HOODS Ocean Disposal (OPTION) 300000 CY 0.57$ 171,000.00$ 0.05$ 15,000.00$ 0.15$ 45,000.00$ 2.00$ 600,000.00$ -91.2% -73.7% 250.9%
ABSTRACT OF OFFERS
W9127N18B0001
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
Manson Construction Co.
5209 E. Marginal Way S.
Seattle, WA 98134
West Coast Hopper Maintenance Dredging 2018
7B. DESCRIPTION OF OFFERED ITEM
7C. EST D.
Great Lakes Dredge & Dock Company, LLC
2122 York Road Oak Brook, IL 60523
B. BID SECURITY B. BID SECURITY
The Dutra Group 2350 Kerner Boulevard, Suite 200 San Rafael, CA 94901-5595
Humboldt Bay Bar/Entrance Channel (HUM) Contractor Survey 1 JOB 50,440.00$ 50,440.00$ 30,000.00$ 30,000.00$ 50,000.00$ 50,000.00$ 15,000.00$ 15,000.00$ -40.5% -0.9% -70.3%
Humboldt Bay Bar/Entrance Channel (HUM) Contractor Survey (OPTION) 1 JOB 25,220.00$ 25,220.00$ 30,000.00$ 30,000.00$ 35,000.00$ 35,000.00$ 15,000.00$ 15,000.00$ 19.0% 38.8% -40.5%
Humboldt Bay Bar/Entrance Channel (HUM) Contractor Survey (OPTION) 1 JOB 25,220.00$ 25,220.00$ 30,000.00$ 30,000.00$ 35,000.00$ 35,000.00$ 15,000.00$ 15,000.00$ 19.0% 38.8% -40.5%
Columbia River (LCR) Maintenance, RM 3+00 to RM 25+00, Bin Measure, Flow Lane (FL) Placement 200000 CY 3.71$ 742,000.00$ 2.50$ 500,000.00$ 4.00$ 800,000.00$ 2.65$ 530,000.00$ -32.6% 7.8% -28.6%
Columbia River (LCR) Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement 400000 CY 3.15$ 1,260,000.00$ 2.90$ 1,160,000.00$ 7.10$ 2,840,000.00$ 2.65$ 1,060,000.00$ -7.9% 125.4% -15.9%
Columbia River (LCR) Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION)
150000 CY 3.08$ 462,000.00$ 2.80$ 420,000.00$ 6.80$ 1,020,000.00$ 2.25$ 337,500.00$ -9.1% 120.8% -26.9%
Columbia River (LCR) Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION)
150000 CY 3.08$ 462,000.00$ 2.80$ 420,000.00$ 6.80$ 1,020,000.00$ 2.25$ 337,500.00$ -9.1% 120.8% -26.9%
Columbia River (LCR) Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth 400000 CY 2.65$ 1,060,000.00$ 2.60$ 1,040,000.00$ 5.00$ 2,000,000.00$ 2.25$ 900,000.00$ -1.9% 88.7% -15.1%
Columbia River (LCR) Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth (OPTION) 300000 CY 2.60$ 780,000.00$ 2.60$ 780,000.00$ 4.60$ 1,380,000.00$ 2.25$ 675,000.00$ 0.0% 76.9% -13.5%
Columbia River (LCR) Increment Times Transit Mile for Material Placement Site (other than five miles one-way), Pre/Post (INFORMATIONAL) -$ -$ -$ -$
0021AA Columbia River (LCR) First 250,000 Cubic Yards 250000 CY 0.11$ 27,500.00$ 0.20$ 50,000.00$ 0.40$ 100,000.00$ 0.11$ 27,500.00$ 81.8% 263.6% 0.0% 0021AB Columbia River (LCR) Over 250,000 Cubic Yards 350000 CY 0.11$ 38,500.00$ 0.20$ 70,000.00$ 0.40$ 140,000.00$ 0.11$ 38,500.00$ 81.8% 263.6% 0.0%
Columbia River (LCR) Increment Time Transit Mile for Material Placement Site (other than five miles one-way), Bin Measure and/or Bin Measure to Required Depth
(INFORMATIONAL) -$ -$ -$ -$
0022AA Columbia River (LCR) First 250,000 Cubic Yards 250000 CY 0.11$ 27,500.00$ 0.20$ 50,000.00$ 0.35$ 87,500.00$ 0.11$ 27,500.00$ 81.8% 218.2% 0.0% 0022AB Columbia River (LCR) Over 250,000 Cubic Yards 350000 CY 0.11$ 38,500.00$ 0.20$ 70,000.00$ 0.35$ 122,500.00$ 0.11$ 38,500.00$ 81.8% 218.2% 0.0%
Columbia River (LCR) Intra-Project Transit Miles
(INFORMATIONAL) -$ -$ -$ -$
0023AA Columbia River (LCR) First 150 Miles 150 MILES 442.49$ 66,373.50$ 300.00$ 45,000.00$ 600.00$ 90,000.00$ 320.00$ 48,000.00$ -32.2% 35.6% -27.7% 0023AB Columbia River (LCR) Over 150 Miles 50 MILES 416.48$ 20,824.00$ 300.00$ 15,000.00$ 575.00$ 28,750.00$ 320.00$ 16,000.00$ -28.0% 38.1% -23.2%
Mouth of the Columbia River (MCR) Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement
1600000 CY 2.61$ 4,176,000.00$ 2.40$ 3,840,000.00$ 2.95$ 4,720,000.00$ 2.30$ 3,680,000.00$ -8.0% 13.0% -11.9%
Mouth of the Columbia River (MCR) Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement (OPTION) 400000 CY 2.63$ 1,052,000.00$ 2.20$ 880,000.00$ 2.75$ 1,100,000.00$ 1.60$ 640,000.00$ -16.3% 4.6% -39.2%
Mouth of the Columbia River (MCR) Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement (OPTION) 250000 CY 2.60$ 650,000.00$ 2.10$ 525,000.00$ 2.50$ 625,000.00$ 1.60$ 400,000.00$ -19.2% -3.8% -38.5%
Mouth of the Columbia River (MCR) Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement 300000 CY 1.57$ 471,000.00$ 1.60$ 480,000.00$ 1.60$ 480,000.00$ 0.70$ 210,000.00$ 1.9% 1.9% -55.4%
Mouth of the Columbia River (MCR) Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION) 300000 CY 1.57$ 471,000.00$ 1.60$ 480,000.00$ 1.40$ 420,000.00$ 0.70$ 210,000.00$ 1.9% -10.8% -55.4%
Mouth of the Columbia River (MCR) Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION) 250000 CY 1.55$ 387,500.00$ 1.60$ 400,000.00$ 1.35$ 337,500.00$ 0.70$ 175,000.00$ 3.2% -12.9% -54.8%
East Sand Island Erosion Repair (ESI) Incremental Mobilization and Demobilization for Pump-ashore Operations (OPTION) 1 JOB 341,565.31$ 341,565.31$ 1,500,000.00$ 1,500,000.00$ 2,075,000.00$ 2,075,000.00$ 1,000,000.00$ 1,000,000.00$ 339.2% 507.5% 192.8%
East Sand Island Erosion Repair (ESI) Bin Measure, Increment for Operations and Maintenance, Shoreline Placement, Borrow Site Within MCR/LCR RM -2-10 to RM 12+00 (OPTION)
80000 CY 2.67$ 213,600.00$ 12.00$ 960,000.00$ 12.75$ 1,020,000.00$ 14.20$ 1,136,000.00$ 349.4% 377.5% 431.8%
East Sand Island Erosion Repair (ESI) East Sand Island, Piling Removal, Demolition, and Disposal AND Rock Relocation (OPTION) 1 JOB 236,546.25$ 236,546.25$ 350,000.00$ 350,000.00$ 295,000.00$ 295,000.00$ 315,000.00$ 315,000.00$ 48.0% 24.7% 33.2%
SUBTOTAL FOR MANDATORY LINE ITEMS 17,044,204.50$ 17,245,000.00$ 21,691,250.00$ 15,442,055.00$ 1.2% 27.3% -9.4% SUBTOTAL FOR OPTIONAL LINE ITEMS 7,506,091.56$ 8,542,500.00$ 11,322,500.00$ 7,786,000.00$ 13.8% 50.8% 3.7%
24,550,296.06$ 25,787,500.00$ 33,013,750.00$ 23,228,055.00$ 5.0% 34.5% -5.4%
NSN 7540-01-150-0981 1419-101
TOTAL
ACCEPTANCE LIMITATION - DAYS
INFORMALITIES
STANDARD FORM 1419 (10-3)